Graded A+
tested☑️Correct Ans-according to osha 1926.1419 before lifting operations begin
communication systems shall be
identify each other☑️Correct Ans-prior to commencing a crane lift the operator and
signalperson shall
perspective☑️Correct Ans-any direction given to the crane operator by the signal person shall
be given from the operator
function and direction☑️Correct Ans-what is the first element of voice signals given to a crane
operator prior to the lift
three☑️Correct Ans-according to osha and asme b30.5 each series of voice signals contain how
many elements
lift director☑️Correct Ans-for lifting operations using voice signals who has the responsibility
of permitting multiple simultaneous crane functions
standard signals☑️Correct Ans-according to asme b30.5 special signals cannot conflict with
, back up☑️Correct Ans-if the operator sounds three short audible signals while loving the crane
he/she intends to
stop☑️Correct Ans-if the operator sounds one short audible signal while moving the crane
he/she intends to
job site location☑️Correct Ans-according to asme b30.5 ant audible emergency signal must be
agreed upon at each
go ahead☑️Correct Ans-if the operator sounds two short audible signals while move crane
he/she intends to
hard wire radio☑️Correct Ans-when signaling a tower crane which of the following is most
reliable
asme b30.3☑️Correct Ans-according to asme which volume listed below must be used to hand
signal a tower crane
asme b30.5☑️Correct Ans-according to asme which volume listed below must be used to hand
signal a mobile crane
continuously☑️Correct Ans-during all crane movements, asme b30.5 states that communication
shall be maintained