100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

CAPM and PMP Exam quetions and answers 2022

Rating
-
Sold
-
Pages
138
Grade
A+
Uploaded on
09-04-2022
Written in
2022/2023

CAPM and PMP Exam quetions and answers 2022












Whoops! We can’t load your doc right now. Try again or contact support.

Document information

Uploaded on
April 9, 2022
Number of pages
138
Written in
2022/2023
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Question No : 1 - Topic 1
Sending letters, memos, reports, emails, and faxes to share information is an example of
which type of communication?
A. Direct
B. Interactive
C. Pull
D. Push
Hide Answer
Answer: D

Question No : 2 - Topic 1
A project manager should document the escalation path for unresolved project risks in the:
A. Change control plan
B. Stakeholder register
C. Risk log
D. Communications management plan
Hide Answer
Answer: D

Question No : 3 - Topic 1
Which Knowledge Area involves identifying the people, groups, or organizations that may
be impacted by or impact a project?
A. Project Risk Management
B. Project Human Resource Management
C. Project Scope Management
D. Project Stakeholder Management
Hide Answer
Answer: D

Question No : 4 - Topic 1
Which input to the Plan Risk Management process provides information on high-level
risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets
Hide Answer
Answer: A

Question No : 5 - Topic 1
Which process identifies whether the needs of a project can best be met by acquiring
products, services, or results outside of the organization?
A. Plan Procurement Management
B. Control Procurements
C. Collect Requirements
D. Plan Cost Management
Hide Answer
Answer: A

Question No : 6 - Topic 1
An example of a group decision-ma king technique is:

,A. Nominal group technique.
B. Majority.
C. Affinity diagram.
D. Multi-criteria decision analysis.
Hide Answer
Answer: B

Question No : 7 - Topic 1
Which type of dependency is established based on knowledge of best practices within a
particular application area or some unusual aspect of the project in which a specific
sequence is desired, even though there may be other acceptable sequences?
A. External
B. Internal
C. Mandatory
D. Discretionary
Hide Answer
Answer: D

Question No : 8 - Topic 1
In a project, total float measures the:
A. Ability to shuffle schedule activities to lessen the duration of the project.
B. Amount of time an activity can be extended or delayed without altering the project finish date.
C. Cost expended to restore order to the project schedule after crashing the schedule.
D. Estimate of the total resources needed for the project after performing a forward pass.
Hide Answer
Answer: B

Question No : 9 - Topic 1
The only Process Group that comprises processes that typically occur from the beginning
to the end of the project life cycle is:
A. Planning.
B. Executing,
C. Monitoring and Controlling.
D. Closing.
Hide Answer
Answer: C

Question No : 10 - Topic 1
Sensitivity analysis is typically displayed as a/an:
A. Decision tree diagram.
B. Tornado diagram.
C. Pareto diagram.
D. Ishikawa diagram.
Hide Answer
Answer: B

Question No : 11 - Topic 1
Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA),
and trend analysis are examples of which tool or technique?
A. Expert judgment
B. Forecasting methods

,C. Earned value management
D. Analytical techniques
Show Answer

Question No : 12 - Topic 1
A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique
used in which process?
A. Identify Risks
B. Control Risks
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis
Hide Answer
Answer: A

Question No : 13 - Topic 1
During which process does a project manager review all prior information to ensure that all
project work is completed and that the project has met its objectives?
A. Monitor and Control Project Work
B. Perform Quality Assurance
C. Close Project or Phase
D. Control Scope
Hide Answer
Answer: C

Question No : 14 - Topic 1
Which tools or techniques are used in the Plan Schedule Management process?
A. Benchmarking, expert judgment, and analytical techniques
B. Statistical sampling, benchmarking, and meetings
C. Negotiations, pre-assignment, and multi-criteria decision analysis
D. Expert judgment, analytical techniques, and meetings
Hide Answer
Answer: D

Question No : 15 - Topic 1
A project charter is an output of which Process Group?
A. Executing
B. Planning
C. Initiating
D. Closing
Hide Answer
Answer: C

Question No : 16 - Topic 1
The organization's perceived balance between risk taking and risk avoidance is reflected in
the risk:
A. Responses
B. Appetite
C. Tolerance
D. Attitude
Hide Answer
Answer: A

, Question No : 17 - Topic 1
Which Plan Schedule Management tool or technique may involve choosing strategic
options to estimate and schedule the project?
A. Facilitation techniques
B. Expert judgment
C. Analytical techniques
D. Variance analysis
Show Answer

Question No : 18 - Topic 1
A key benefit of the Manage Communications process is that it enables:
A. The best use of communication methods.
B. An efficient and effective communication flow.
C. Project costs to be reduced.
D. The best use of communication technology.
Hide Answer
Answer: B

Question No : 19 - Topic 1
An input to the Manage Project Team process is:
A. Work performance reports.
B. Change requests.
C. Activity resource requirements.
D. Enterprise environmental factors.
Hide Answer
Answer: A

Question No : 20 - Topic 1
The definition of when and how often the risk management processes will be performed
throughout the project life cycle is included in which risk management plan component?
A. Timing
B. Methodology
C. Risk categories
D. Budgeting
Hide Answer
Answer: A
Question No : 21 - Topic 1
Which process involves developing an approximation of the monetary resources needed to
complete project activities?
A. Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management
Hide Answer
Answer: A

Question No : 22 - Topic 1
The ways in which the roles and responsibilities, reporting relationships, and staffing
management will be addressed and structured within a project is described in the:
A. Human resource management plan.
B. Activity resource requirements.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
YNA Berkeley College
View profile
Follow You need to be logged in order to follow users or courses
Sold
76
Member since
4 year
Number of followers
68
Documents
616
Last sold
2 months ago

3.7

9 reviews

5
4
4
2
3
1
2
0
1
2

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions