, Question: 1
An element of the project scope statement is:
A. Acceptance criteria.
B. A stakeholder list.
C. A summary budget,
D. High-level risks.
Answer: A
Question: 2
Which document describes the necessary information to determine if a project is worth the required
investment?
A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case
Answer: D
Question: 3
Which input to the Plan Risk Management process provides information on high-level risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets
Answer: A
Question: 4
Which item is an example of personnel assessment?
A. Resource calendar
B. Tight matrix
PMP
Project Management Professional
, Question: 1
An element of the project scope statement is:
A. Acceptance criteria.
B. A stakeholder list.
C. A summary budget,
D. High-level risks.
Answer: A
Question: 2
Which document describes the necessary information to determine if a project is worth the required
investment?
A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case
Answer: D
Question: 3
Which input to the Plan Risk Management process provides information on high-level risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets
Answer: A
Question: 4
Which item is an example of personnel assessment?
A. Resource calendar
B. Tight matrix