What is Chapter 1 of the ACG Cx Guideline?
Introduction
What is Chapter 2 of the ACG Cx Guideline?
HVAC Commissioning Cost/Benefit Analysis
What is Chapter 3 of the ACG Cx Guideline?
Selecting a Commissioning Provider
What is Chapter 4 of the ACG Cx Guideline?
The HVAC Commissioning Team
What is Chapter 5 of the ACG Cx Guideline?
Comprehensive HVAC Commissioning
,Studies indicate _ to _% savings in building operating costs when
comparing a comissioned building to a non-commissioned building.
8 to 20%
What is commissioning?
A process of documentation, adjustment, testing, verification, and
training performed specifically to ensure that the finished facility
operates in accordance with the owner's documented project
requirements and the construction documents. Commissioning
serves the owner's best interests by delivering a facility with systems
that perform as specified, intended, and paid for.
What does DID mean and provide a brief definition?
Design Intent Document - Details functional requirements and
Owner's expectations of how a building will be used and operated -
Owner's Project Requirements
What does BOD mean and provide a brief definition?
Basis of Design - The concepts, calculations, decisions, and product
selections used to meet the Owner's Project Requirements.
, Designer's (A/E) services typically (do or do not) include field
verification that their design works as intended.
Do NOT
Construction Manager's services typically (do or do not) include
functional verification that the installed systems meet design intent.
Do NOT
The CxA has a distinct responsibility to who?
The Owner
The CxA is not just another layer of inspection, but a catalyst for?
Communication that makes quality solutions possible.
The CxA (is or is not) an inspector.
Is NOT
The commissioning process provides verification that the ____ ____ ____
are implemented in both the ____ and ____.
Owner's Project Requirements; Design and Construction
New construction commissioning costs _ to _% of total construction
cost.
0.5 to 1.5%