1. The point of transfer at a dispensing unit must be ____ from Public ways, including
public streets, highways, thoroughfares, and sidewalks.
A. 10 feet
B. 15 feet
C. 25 feet - CORRECT ANSWERS-A. 10 feet
2. Steel supports on vertical ASME containers shall be protected against fire exposure with
a material having a fire resistance rating of a least _____, except that continuous steel
skirts that have only one opening that is 18 in. or less in diameter shall have fire
protection applied to the ______ of the skirts.
A. 3 hrs; outside
B. 2 hrs; outside
C. 3 hrs; inside - CORRECT ANSWERS-B. 2 hrs; outside
3. Pressure relief devices installed in underground containers serving dispensing systems
shall be piped vertically upward to a point at least _____ above the ground.
A. 2 feet
B. 6 feet