True or False: A project manager spends 75% of his or her time communicating.
a. True
b. False ✔Correct Answer-b
Which item would most likely NOT be part of a basic communication plan:
a. The best medium for the communication.
b. What they need to know.
c. With whom to communicate.
d. The amount of their annual bonus. ✔Correct Answer-d
Upward communication is communication to/from:
a. Your social groups.
b. Your senior management.
c. Your direct reports.
d. Your peers. ✔Correct Answer-b
When you report project status you compare actual performance to:
a. The performance of other similar projects.
b. The performance of your competitors.
c. The planned performance or baseline.
d. The performance of previous projects. ✔Correct Answer-c
True or False: Earned value integrates scope, schedule and budget and uses monetary values to
assess project status.
a. False
b. True ✔Correct Answer-b
You are beginning to staff your project. Which of the following will not be used in developing and/or
communicating roles and responsibilities?
a. WBS
b. Pareto chart
c. Responsibility Assignment Matrix
d. Organization chart ✔Correct Answer-b
Which of the following is not likely to be documented in a communications management plan?
a. Time frame and frequency of communication
b. Person responsible for tracking risk events
c. What information will be communicated
d. How information will be communicated ✔Correct Answer-b
True or False: Effective project communication management creates a bridge between stakeholders
based on a shared understanding of the project and the ongoing sharing of information needed for
its success.
a. True
b. False ✔Correct Answer-a