Score for this attempt: 28 out of 30
Submitted May 16 at 3:41am
This attempt took 9 minutes.
Question 1
pts
Once the project schedule is approved, a is established to monitor
the schedule as the project makes progress.
Change Request Plan
Baselin
e
Sponso
r
WBS
A schedule baseline is established after the schedule is agreed upon. It is a
fixed measure by which the project’s schedule is monitored and tracked.
Question 2
pts
The Project Management Plan is a set of planning documents that
cover the entire planning process and can be expected to change
over the life of the project.
True
False
True, the Project Management Plan serves as a roadmap that
provides direction for the project and is viewed as a set of “living
documents” that change over the life of the project.
This study source was downloaded by 100000900991627 from CourseHero.com on 01-18-2026 13:51:02 GMT -06:00
https://www.coursehero.com/file/204070171/PMG-322-Module-1-Quizdocx/
, Question 3
pts
Of the following examples, which has the least direct connection to
project schedule management?