Pass C722 Project Management with confidence using this all-in-one, student-friendly study guide. This resource combines highlighted key concepts, JO’s proven exam tips, and a realistic practice test designed to mirror the C722 assessment structure and learning objectives. What’s Included: Highlighted, easy-to-review study guide JO’s insider tips for understanding tricky concepts Practice test with accurate answers Coverage of project lifecycle, scope, cost, risk & quality Agile vs. Waterfall methodologies Stakeholder & communication management Perfect for final review and first-time pass

Show more Read less
Institution
Module











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Module

Document information

Uploaded on
January 18, 2026
Number of pages
82
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

1|Page



C722- Project Management, WGU C722
(Pre), WGU C722 Project Management
Terminology, WGU C722 Project
Management Terminology, WGU C722
Equations 2026
Save



Q1: What is the primary purpose of the Project Charter?
A: Formally authorize the project and define high-level objectives.
Rationale: It gives the project manager authority and establishes initial scope and stakeholders.



Q2: Which role is responsible for ensuring the project delivers the agreed scope?
A: Project Sponsor
Rationale: The sponsor champions the project and authorizes major decisions.



Q3: What process group occurs throughout the project?
A: Monitoring and Controlling
Rationale: This group continuously tracks, reviews, and regulates progress.



Q4: The Project Management Plan is developed during:
A: Planning
Rationale: It integrates subsidiary plans (scope, schedule, cost, risk, etc.).



Q5: The main output of Develop Project Charter is:
A: Project Charter
Rationale: Official authorization to proceed.




practice exam 2026

,2|Page


Q6: Integrated Change Control is performed in:
A: Monitoring and Controlling
Rationale: Ensures changes are evaluated before approval.



Q7: A stakeholder’s needs are documented in:
A: Requirements documentation
Rationale: Basis for defining scope and acceptance criteria.



Q8: Which technique prioritizes objectives by trade-off analysis?
A: Decision tree
Rationale: Supports evaluating risky decisions across outcomes.



Q9: The project manager’s primary responsibility is:
A: Delivering project objectives within constraints
Rationale: Balances scope, schedule, cost, quality, and stakeholders.



Q10: A benefit of strong project integration is:
A: Better alignment of objectives across teams
Rationale: Promotes unified execution and stakeholder satisfaction.



11–20: Scope Management

Q11: What establishes project boundaries and deliverables?
A: Scope Statement
Rationale: Describes what is included and excluded.



Q12: A WBS is used to:
A: Decompose work into manageable components
Rationale: Enables planning, estimating, and assignment of work.




practice exam 2026

,3|Page


Q13: WBS work packages should be:
A: Small enough to estimate duration and cost
Rationale: Helps improve accuracy.



Q14: The process to confirm deliverables with stakeholders is:
A: Validate Scope
Rationale: Ensures acceptance of completed work.



Q15: Scope creep occurs due to:
A: Uncontrolled changes
Rationale: Changes not properly managed lead to scope increase.



Q16: A detailed description of deliverables is found in:
A: Scope Baseline
Rationale: Includes scope statement, WBS, and WBS dictionary.



Q17: Change requests affecting scope must go through:
A: Integrated Change Control
Rationale: Ensures evaluation across all impact areas.



Q18: The process of subdividing project deliverables is:
A: Create WBS
Rationale: Breaks down work for planning and control.



Q19: Project exclusions are part of:
A: Scope Statement
Rationale: Clarifies what is not included.



Q20: “Requirements traceability matrix” helps ensure:
A: Requirements are tracked through project life
Rationale: Ensures work aligns with original objectives.



practice exam 2026

, 4|Page




21–30: Schedule & Time Management

Q21: The first scheduling step is:
A: Define Activities
Rationale: Break down WBS work into schedule tasks.



Q22: Sequence activities output is:
A: Network Diagram
Rationale: Shows logical order of work.



Q23: Critical path determines:
A: Longest path and shortest project duration
Rationale: Tasks on critical path have zero float.



Q24: Fast-tracking means:
A: Performing activities in parallel
Rationale: Shortens schedule but increases risk.



Q25: Crashing a schedule increases:
A: Cost
Rationale: Adds resources to reduce duration.



Q26: A Gantt chart is primarily used to:
A: Visualize schedule over time
Rationale: Helps track start/end dates of tasks.



Q27: Free float refers to:
A: Delay allowed without affecting successor tasks
Rationale: Limited to individual activity.




practice exam 2026

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GEO808 nursing
Follow You need to be logged in order to follow users or courses
Sold
1387
Member since
4 year
Number of followers
1123
Documents
9914
Last sold
9 hours ago
Top Nursing Exam Resources

Hi! I’m a nursing student who creates clear, accurate, and exam-ready study materials for ATI, NCLEX, and core nursing courses. My uploads include complete summaries, verified exam answers, and organized notes designed to save you time and boost your scores. Everything in my store is updated, easy to follow, and built to help you study smarter, not harder.

3.8

221 reviews

5
107
4
35
3
36
2
11
1
32

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions