ALABAMA (AL) DRAINAGE & CULVERT CONTRACTOR PRACTICE EXAM LATEST QUESTIONS
AND CORRECT ANSWERS GRADE A



**1. According to Alabama state regulations, what is the minimum required bond amount
for a Drainage & Culvert contractor?**

A) $5,000

B) $10,000

C) $15,000

D) $20,000



**Answer: B**

**Explanation:** Alabama Code § 34-14-10 requires a minimum $10,000 surety bond for
drainage and culvert contractors licensed by the Alabama Licensing Board for General
Contractors.



**2. Which Alabama state agency regulates stormwater management during construction
activities?**

A) Alabama Department of Environmental Management (ADEM)

B) Alabama Department of Transportation (ALDOT)

C) Alabama Soil and Water Conservation Committee

D) All of the above



**Answer: D**

**Explanation:** All three agencies have regulatory authority over stormwater
management, with ADEM administering the NPDES permit program, ALDOT having road
construction standards, and the Conservation Committee overseeing erosion control.

,**3. What is the minimum required pipe cover for culverts under unpaved roads according
to ALDOT standards?**

A) 6 inches

B) 12 inches

C) 18 inches

D) 24 inches



**Answer: B**

**Explanation:** ALDOT Standard Specifications typically require minimum 12 inches of
cover for culverts under unpaved roads, with 24 inches for paved roads.



**4. According to Alabama regulations, what is the maximum allowable velocity for unlined
drainage ditches in sandy soil?**

A) 1.5 feet per second

B) 2.0 feet per second

C) 2.5 feet per second

D) 3.0 feet per second



**Answer: B**

**Explanation:** Alabama Erosion and Sediment Control Handbook recommends
maximum 2.0 fps for sandy soils to prevent erosion.



**5. Which type of pipe is NOT approved for permanent storm drainage installations in
Alabama?**

A) Corrugated polyethylene

B) Reinforced concrete

C) PVC Schedule 40

,D) Corrugated metal with asphalt coating



**Answer: C**

**Explanation:** PVC Schedule 40 is typically not approved for permanent storm drainage;
SDR 35 or stronger PVC is required for structural reasons.



**6. What is the minimum required slope for drainage pipes according to ALDOT
standards?**

A) 0.3%

B) 0.5%

C) 1.0%

D) 2.0%



**Answer: B**

**Explanation:** ALDOT typically requires minimum 0.5% slope (0.5 feet per 100 feet) for
drainage pipes to ensure self-cleaning velocity.



**7. According to Alabama regulations, what is the maximum depth for trench excavation
without shoring in stable soil?**

A) 4 feet

B) 5 feet

C) 6 feet

D) 8 feet



**Answer: B**

**Explanation:** OSHA and Alabama regulations allow maximum 5-foot depth without
shoring in Type A or B soils under certain conditions.

, **8. Which of the following requires a NPDES permit in Alabama?**

A) All drainage projects over 1 acre

B) Projects disturbing more than 1 acre

C) Only projects near waterways

D) Projects over 5 acres only



**Answer: B**

**Explanation:** ADEM requires NPDES permits for construction activities disturbing 1
acre or more of land.



**9. What is the minimum required thickness for galvanized corrugated metal pipe (CMP)
under roads in Alabama?**

A) 16 ga

B) 14 ga

C) 12 ga

D) 10 ga



**Answer: A**

**Explanation:** ALDOT typically requires minimum 16 ga galvanized CMP for most
applications, with thicker gauges for higher loads or corrosive conditions.



**10. According to Alabama regulations, how often must erosion control measures be
inspected?**

A) Daily

B) Weekly

C) After each rain event

Written for

Institution
Finance
Module
Finance

Document information

Uploaded on
January 18, 2026
Number of pages
34
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

£63.37
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller
Seller avatar
GerryBlair

Get to know the seller

Seller avatar
GerryBlair University Of Texas - Arlington
Follow You need to be logged in order to follow users or courses
Sold
1
Member since
2 months
Number of followers
0
Documents
60
Last sold
1 week ago

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Trending documents

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions