100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

EXAC Study Cards - Section 4 Questions with Correct Answers Latest Update 2026/2027

Rating
-
Sold
-
Pages
42
Grade
A+
Uploaded on
15-01-2026
Written in
2025/2026

EXAC Study Cards - Section 4 Questions with Correct Answers Latest Update 2026/2027 To reply lien claimant on info request - Answers 21 Cross-examination notice for lien claimsnt - Answers 7 Preservation of lien - Answers 45 Perfection of lien - Answers 45 Expiry of lien from perfection action - Answers 2 years To reply to application for Substantial - Answers 10+7 To reply to application for Certificate Statement of completion - Answers 10+7 To pay after issuance of certificate of completion - Answers 5 To pay holback - Answers 45 from a) publish in newspaper, b) completion of contract, or c) contract is abandoned Mail notice - Answers 5 excl. Holidays Email notice - Answers 0 (only working hours) 2% interest on delayed payments - Answers 60 4% interest on delayed payments - Answers Per annum, after 60 days Submit Schedule of values prior to first application for payment - Answers 15 To reply to application for typical payment - Answers 10 Owner to pay typical payment - Answers 20 from a) application for payment, or b) last day of monthly payment period Owner to deposit holdback monies in joint account - Answers 10 before end of holdback period To give notice of concealed conditions - Answers 5 To give notice of delays outside owner/arch. Fault - Answers 10 (and no extra money!) Architect to decide on claim for a change in price - Answers 30 GC to act on owner's termination notice - Answers 5 GC right to terminate work due to delays - Answers 20 to act on GC's termination notice - Answers 5 Termination of Broad Form insurance(from start work date) - Answers Earliest of a) 10 after substantial, b) occupancy or c) 30 of activity ceased Boiler insurance (from start operation) - Answers 10 after substantial Contractor's equipment insurance - Answers 1 year after substantial General liability insurance - Answers 1 year after substantial indemnification for negligence or failure to contract - Answers 6 years Appoint mediator - Answers 20 from contract award or notice from any party Party to submit dispute notice after architect's finding - Answers 15 Party to respond to dispute notice - Answers 10 Party to request mediator for a dispute - Answers 10 Party to solve dispute - Answers 10 Party to refer to arbitration after mediation fails - Answers 10 Recalibrate cost if construction hasn't started - Answers 3 months Owner's notice to suspend Architect - Answers 7 Unpaid period before Architect gives suspension notice to owner - Answers 45 Owner's notice of arbitration to architect - Answers 10 Bid period large project - Answers 6 weeks bid period small project - Answers 2 weeks Circulate minutes - Answers 48 hours Deadline for addenda - Answers 4days Respond to bidders - Answers 10 Subs to send final docs to Architect before bidding - Answers 2 weeks Subs to contribute to adde da - Answers 60 Statute of limitations for negligence - Answers 2 years Statute of limitations for breach of contract - Answers 2 years Ultimate Statute of limitations - Answers 15 years Schedulling beyond completion - Answers 60 Copyright - Answers Life+remainder of year+50 years Patent - Answers 20 years Architect's notice to suspend client - Answers 7 Client to pay invoice for suspension or terminatio of services - Answers 30 Architect's contract Termination after abandonment of the project - Answers 7 AIBC Bulletin 66, AIBC Bylaw 16.3 & Architect's Act

Show more Read less
Institution
EXAC
Module
EXAC











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
EXAC
Module
EXAC

Document information

Uploaded on
January 15, 2026
Number of pages
42
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

EXAC Study Cards - Section 4 Questions with Correct Answers Latest Update 2026/2027

To reply lien claimant on info request - Answers 21

Cross-examination notice for lien claimsnt - Answers 7

Preservation of lien - Answers 45

Perfection of lien - Answers 45

Expiry of lien from perfection action - Answers 2 years

To reply to application for Substantial - Answers 10+7

To reply to application for Certificate Statement of completion - Answers 10+7

To pay after issuance of certificate of completion - Answers 5

To pay holback - Answers 45 from a) publish in newspaper, b) completion of contract, or c)
contract is abandoned

Mail notice - Answers 5 excl. Holidays

Email notice - Answers 0 (only working hours)

2% interest on delayed payments - Answers 60

4% interest on delayed payments - Answers Per annum, after 60 days

Submit Schedule of values prior to first application for payment - Answers 15

To reply to application for typical payment - Answers 10

Owner to pay typical payment - Answers 20 from a) application for payment, or b) last day of
monthly payment period

Owner to deposit holdback monies in joint account - Answers 10 before end of holdback period

To give notice of concealed conditions - Answers 5

To give notice of delays outside owner/arch. Fault - Answers 10 (and no extra money!)

Architect to decide on claim for a change in price - Answers 30

GC to act on owner's termination notice - Answers 5

GC right to terminate work due to delays - Answers 20

to act on GC's termination notice - Answers 5

,Termination of Broad Form insurance(from start work date) - Answers Earliest of a) 10 after
substantial, b) occupancy or c) 30 of activity ceased

Boiler insurance (from start operation) - Answers 10 after substantial

Contractor's equipment insurance - Answers 1 year after substantial

General liability insurance - Answers 1 year after substantial

indemnification for negligence or failure to contract - Answers 6 years

Appoint mediator - Answers 20 from contract award or notice from any party

Party to submit dispute notice after architect's finding - Answers 15

Party to respond to dispute notice - Answers 10

Party to request mediator for a dispute - Answers 10

Party to solve dispute - Answers 10

Party to refer to arbitration after mediation fails - Answers 10

Recalibrate cost if construction hasn't started - Answers 3 months

Owner's notice to suspend Architect - Answers 7

Unpaid period before Architect gives suspension notice to owner - Answers 45

Owner's notice of arbitration to architect - Answers 10

Bid period large project - Answers 6 weeks

bid period small project - Answers 2 weeks

Circulate minutes - Answers 48 hours

Deadline for addenda - Answers 4days

Respond to bidders - Answers 10

Subs to send final docs to Architect before bidding - Answers 2 weeks

Subs to contribute to adde da - Answers 60

Statute of limitations for negligence - Answers 2 years

Statute of limitations for breach of contract - Answers 2 years

Ultimate Statute of limitations - Answers 15 years

,Schedulling beyond completion - Answers 60

Copyright - Answers Life+remainder of year+50 years

Patent - Answers 20 years

Architect's notice to suspend client - Answers 7

Client to pay invoice for suspension or terminatio of services - Answers 30

Architect's contract Termination after abandonment of the project - Answers 7

AIBC Bulletin 66, AIBC Bylaw 16.3 & Architect's Act

Depends on the province; in BC Architects are not required to have any liability insurance
according to AIBC Bylaw 16.2d but Bulletin 66 requires that (before entering into an agreement
to provide architectural services) a Certificate of Practice holder must notify the client in writing
whether or not professional liability insurance is held and under what terms.

Section 24.2h in the Architect's Act states that an institute's bylaws may or may not include
requirements for liability insurance; in BC, there is no requirement. - Answers How much liability
insurance is an architect in Canada required to have?

This allows the release of holdbacks to subcontractors or suppliers in advance of the
substantial performance of the work. - Answers What is the purpose of progressive release of
holdbacks?

1. feasibility studies

2. business cases

3. functional programming

4. submissions to authorities

5. life cycle cost studies - Answers what are 5 examples of additional services not covered
under RAIC document 6?

AIBC Bulletin 31

Under Section 60 of the Architects Act...



Group A (Part 3) - Public Assembly:

-- any one-storey building with an unsupported span exceeding 9 m or gross area exceeding 275
m²;

, -- any building of more than one storey with gross area exceeding 235 m²; and

-- all schools, any size



Group B - (Part 3) - Hospital, Sanatorium, or Home for the Aged, Institutional:

-- any building (excluding veterinary hospital) with a

capacity exceeding 12 beds

-- any building with gross area exceeding 470 m²



Group C - Residential, Hotel or similar occupancy:

-- any building containing 5 or more dwelling units

-- any building containing 11 or more guest rooms



Group D & E - Commercial:

-- any building with gross area exceeding 470 m²



Group F (F1: Part 3) - Industrial:

-- any building with gross area exceeding 470 m² - Answers What buildings require the services
of an architect?

CHOP 2.1.10 - Client-Architect Agreements

Canadian Standard Form of Contract for Architectural Services Between Client and Architect. It
is the accepted national standard contract used by architects. - Answers What is RAIC
Document Six?

Guide to the Letters of Assurance in the B.C. Building Code

Schedule A - Confirmation of Commitment by Owner and Coordinating Registered Professional



Schedule A is a confirmation of commitment by the owner and coordinating registered
professional to coordinate design work and field reviews of the registered professionals of

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
TutorJosh Chamberlain College Of Nursing
Follow You need to be logged in order to follow users or courses
Sold
361
Member since
1 year
Number of followers
16
Documents
29352
Last sold
1 day ago
Tutor Joshua

Here You will find all Documents and Package Deals Offered By Tutor Joshua.

3.5

57 reviews

5
19
4
15
3
12
2
0
1
11

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions