Forward and Backward Pass
Give this one a try later!
Project managers can determine the early start (ES), early finish (EF), late
start (LS) and late finish (LF) of each activity through the
Level of precision
Give this one a try later!
The degree to which activity cost estimates will be rounded up or down
(e.g., US$100.49 to US$100, or US$995.59 to US$1,000), based on the scope
of the activities and magnitude of the project.
,How to develop project schedule
Give this one a try later!
- Identify all activities and determine logical order
- Assign resources to each activity
- Estimate time required for that activity
-Consider project budget, quality and risk factor
risk response control
Give this one a try later!
Executing the risk response strategy
v Monitoring the triggers
v Initiating contingency plans
v Watching for new risks
v Repeating risk identification
v Assigning and document responsibility for managing risks
Work breakdown structure
Give this one a try later!
deliverable -oriented decomposition of the activities specified in the
project scope.
root cause analysis
,Give this one a try later!
an analytical technique used to determine the basic underlying reason that
causes a variance or defect or risk.
may underlie more than one variance or defect or risk
organizational risks
Give this one a try later!
Lack of prioritization of projects
Inadequate funding
Inadequate resource assignment
Just in Time (JIT)
Give this one a try later!
inventory management method whereby materials. goods, and labor are
scheduled to arrive or be replenished exactly when needed in the
production process
Level of Accuracy
Give this one a try later!
, The acceptable range used in determining realistic activity duration
estimates is specified and may include an amount for contingencies.
plan risk responses
Give this one a try later!
the process of figuring out options and actions needed to reduce threats
and enhance opportunities to project objectives
Project Management Plan
Give this one a try later!
used to identify approaches to plan and manage scope and to develop an
overall scope management plan
project cost management
Give this one a try later!
The processes involved in planning, estimating, budgeting, financing,
funding, managing, and controlling costs so that the project can be
completed within the approved budget.
Pessimistic time estimate (P):
Give this one a try later!
Project managers can determine the early start (ES), early finish (EF), late
start (LS) and late finish (LF) of each activity through the
Level of precision
Give this one a try later!
The degree to which activity cost estimates will be rounded up or down
(e.g., US$100.49 to US$100, or US$995.59 to US$1,000), based on the scope
of the activities and magnitude of the project.
,How to develop project schedule
Give this one a try later!
- Identify all activities and determine logical order
- Assign resources to each activity
- Estimate time required for that activity
-Consider project budget, quality and risk factor
risk response control
Give this one a try later!
Executing the risk response strategy
v Monitoring the triggers
v Initiating contingency plans
v Watching for new risks
v Repeating risk identification
v Assigning and document responsibility for managing risks
Work breakdown structure
Give this one a try later!
deliverable -oriented decomposition of the activities specified in the
project scope.
root cause analysis
,Give this one a try later!
an analytical technique used to determine the basic underlying reason that
causes a variance or defect or risk.
may underlie more than one variance or defect or risk
organizational risks
Give this one a try later!
Lack of prioritization of projects
Inadequate funding
Inadequate resource assignment
Just in Time (JIT)
Give this one a try later!
inventory management method whereby materials. goods, and labor are
scheduled to arrive or be replenished exactly when needed in the
production process
Level of Accuracy
Give this one a try later!
, The acceptable range used in determining realistic activity duration
estimates is specified and may include an amount for contingencies.
plan risk responses
Give this one a try later!
the process of figuring out options and actions needed to reduce threats
and enhance opportunities to project objectives
Project Management Plan
Give this one a try later!
used to identify approaches to plan and manage scope and to develop an
overall scope management plan
project cost management
Give this one a try later!
The processes involved in planning, estimating, budgeting, financing,
funding, managing, and controlling costs so that the project can be
completed within the approved budget.
Pessimistic time estimate (P):