• Wrong document? Swap it for free
  • Written by students who passed
  • Immediately available after payment
  • Read online or as PDF
Sell
Where do you study
Your language
Document preview thumbnail
Preview 4 out of 100 pages
Exam (elaborations)

Virginia Contractors License Exam – Advanced (Class A) Examination Complete Questions And Detailed Solutions Latest Update This Year Just Released

Document preview thumbnail
Preview 4 out of 100 pages

VIRGINIA CONTRACTORS LICENSE EXAM – ADVANCED (CLASS A) EXAMINATION COMPLETE QUESTIONS AND DETAILED SOLUTIONS LATEST UPDATE THIS YEAR JUST RELEASED

Content preview

VIRGINIA CONTRACTORS LICENSE EXAM – ADVANCED
(CLASS A) EXAMINATION COMPLETE QUESTIONS AND
DETAILED SOLUTIONS LATEST UPDATE THIS YEAR JUST
RELEASED



1. A Class A contractor is preparing a bid and discovers that the drawings conflict
with a written specification. What should the contractor do before submitting the
bid?
A. Automatically use the less expensive interpretation
B. Ignore the conflict until construction begins
C. Request clarification through the established bidding process
D. Select whichever interpretation benefits the contractor most

Answer: C
Rationale: Requesting clarification before bidding reduces ambiguity, protects
pricing accuracy, and establishes the intended requirements before contractual
obligations arise.




2. A contractor estimates direct labor at $82,000, materials at $146,000, and
equipment costs at $22,000. What are total direct costs?
A. $250,000
B. $228,000
C. $246,000
D. $250,000

Answer: A
Rationale: Adding labor, materials, and equipment produces $82,000 + $146,000
+ $22,000, resulting in $250,000 of direct costs.

,3. During contract negotiations, the owner requests extensive additional work but
refuses to modify the written contract. What should the contractor generally do?
A. Perform everything immediately without documentation
B. Document and obtain written authorization for changed work
C. Stop all project activities permanently
D. Bill the owner afterward without notifying anyone

Answer: B
Rationale: Written change authorization establishes scope, price, and schedule
adjustments while reducing later disputes regarding whether additional work was
authorized.




4. A contractor's overhead is $180,000 annually and anticipated annual revenue is
$1,200,000. What percentage of revenue represents overhead?
A. 12%
B. 15%
C. 18%
D. 20%

Answer: B
Rationale: Dividing $180,000 by $1,200,000 produces 0.15, meaning overhead
represents 15 percent of anticipated annual revenue.




5. Which financial statement most directly summarizes a company's assets,
liabilities, and owner's equity at a specific point in time?
A. Income statement
B. Cash-flow forecast

,C. Balance sheet
D. Job-cost report

Answer: C
Rationale: A balance sheet presents the company's financial position by listing
assets, liabilities, and equity at a specified reporting date.




6. A contractor notices that a subcontractor repeatedly performs work outside
the subcontract's defined scope. What is the most appropriate management
response?
A. Allow the work and resolve payment later
B. Immediately terminate the subcontractor
C. Ignore the additional work
D. Review the scope and document any authorized changes

Answer: D
Rationale: Reviewing contractual scope and documenting authorized changes
prevents unauthorized costs while preserving an orderly process for legitimate
modifications.




7. A project manager wants to determine whether a project is progressing
according to the approved schedule. Which document provides the most useful
comparison?
A. Original baseline schedule
B. Employee handbook
C. Equipment inventory
D. General ledger

, Answer: A
Rationale: Comparing current progress with the approved baseline schedule helps
identify deviations, delays, critical activities, and necessary corrective measures.




8. A contractor estimates $400,000 in direct costs and applies a 12% markup for
overhead. What amount does the 12% markup represent?
A. $36,000
B. $42,000
C. $48,000
D. $52,000

Answer: C
Rationale: Multiplying $400,000 by 0.12 gives $48,000, representing the amount
added for the stated overhead markup.




9. Why should a contractor maintain detailed records supporting requests for
payment on a large construction project?
A. To eliminate the need for inspections
B. To support earned amounts and resolve potential disputes
C. To avoid preparing project schedules
D. To guarantee immediate payment

Answer: B
Rationale: Detailed records demonstrate completed work, approved changes,
costs, and supporting documentation when payment amounts are questioned.




10. A contractor discovers that a critical material has a twelve-week delivery
period when the schedule allows only six weeks. What should happen first?

Document information

Uploaded on
October 1, 2026
Number of pages
100
Written in
2026/2027
Type
Exam (elaborations)
Contains
Questions & answers
CA$39.36

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Charitywairimu
3.9
(306)
Sold
2224
Followers
1506
Items
4390
Last sold
6 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions