Question 1
A project manager is about to start planning a new sales software development project
and will work with the project team to create the project management plan. What will the
project manager and the team not use during planning a project?
A. Work Performance Information
B. Scope Statement
C. Scope Baseline
D. Risk Register
CORRECT ANSWER
Work Performance Information
Question 2
The project manager has received a change request from the project sponsor to reduce the
budget by 20%. After the project manager has reviewed the change, he decides that the
only way this can be done is by removing a part of the project that was not completed yet.
Who would best approve this change?
A. Project Team
B. Change Approval Board
C. Change Management Board
D. Change Control Board
CORRECT ANSWER
Change Control Board
1
,Question 3
The CEO of a small business has requested that the companies accounting software be
upgraded to better support the financial records. He has requested that the software
include a report that can forecast the following month expenses. Where would be the best
place the CEO can outline why this project needs to get done?
A. Business Documents
B. Scope Outline
C. Scope Statement
D. WBS
CORRECT ANSWER
Business Documents
Question 4
Project manager Mike worked with the sponsor Chris to the get the project charter
approved for the new office reorganizing project. While reviewing the requirements both
Mike and Chris is sure that there is no need to upgrade the current wireless network in the
office. Where is the best place Mile and Chis can store this information?
A. Project Charter
B. Business Case
C. Assumption Documentation
D. Assumption Log
CORRECT ANSWER
Assumption Log
2
,Question 5
While working on creating a project management plan, the project manager has brought a
group of expert programmers and planner to ensure it is created correctly. What tool best
describes this approach?
A. Meeting
B. Interpersonal and Team Skills
C. Data Analysis
D. Data Gathering
CORRECT ANSWER
Data Gathering
Question 6
When a project has been executed, what input would best help the project manager
determined how to manage changes to the project?
A. Change Control Plan
B. Project Management Plan
C. Change Control Board
D. Change Control Charts
CORRECT ANSWER
Project Management Plan
Question 7
3
, Company XYZ has been executing a new business development project for the last 4
months. A few stakeholders have requested a few changes to the scope and have gotten
them approved. When a change is approved what is the next best step to conduct on a
project?
A. Execute the approved change request in the process of Direct and Manage Project Work
B. Execute the approved change request in the process of Monitor and Control Project Work
C. Validate the change in the validate scope process
CORRECT ANSWER
Execute the approved change request in the process of Monitor and Control Project Work
Question 8
A change control board has inform the project manager that a change request made by
stakeholder Mark to reduce the schedule of the project by 2 weeks was rejected. What is
the first step the project manager should take?
A. Resubmit the change request
B. Ask Mark to change his request to 1 week
C. Consult the project team to see how to get this change approve
D. Update the change log
CORRECT ANSWER
Update the change log
Question 9
The deliverable for the product improvement project has been accepted by the sponsor.
What should the project manager do next?
4
A project manager is about to start planning a new sales software development project
and will work with the project team to create the project management plan. What will the
project manager and the team not use during planning a project?
A. Work Performance Information
B. Scope Statement
C. Scope Baseline
D. Risk Register
CORRECT ANSWER
Work Performance Information
Question 2
The project manager has received a change request from the project sponsor to reduce the
budget by 20%. After the project manager has reviewed the change, he decides that the
only way this can be done is by removing a part of the project that was not completed yet.
Who would best approve this change?
A. Project Team
B. Change Approval Board
C. Change Management Board
D. Change Control Board
CORRECT ANSWER
Change Control Board
1
,Question 3
The CEO of a small business has requested that the companies accounting software be
upgraded to better support the financial records. He has requested that the software
include a report that can forecast the following month expenses. Where would be the best
place the CEO can outline why this project needs to get done?
A. Business Documents
B. Scope Outline
C. Scope Statement
D. WBS
CORRECT ANSWER
Business Documents
Question 4
Project manager Mike worked with the sponsor Chris to the get the project charter
approved for the new office reorganizing project. While reviewing the requirements both
Mike and Chris is sure that there is no need to upgrade the current wireless network in the
office. Where is the best place Mile and Chis can store this information?
A. Project Charter
B. Business Case
C. Assumption Documentation
D. Assumption Log
CORRECT ANSWER
Assumption Log
2
,Question 5
While working on creating a project management plan, the project manager has brought a
group of expert programmers and planner to ensure it is created correctly. What tool best
describes this approach?
A. Meeting
B. Interpersonal and Team Skills
C. Data Analysis
D. Data Gathering
CORRECT ANSWER
Data Gathering
Question 6
When a project has been executed, what input would best help the project manager
determined how to manage changes to the project?
A. Change Control Plan
B. Project Management Plan
C. Change Control Board
D. Change Control Charts
CORRECT ANSWER
Project Management Plan
Question 7
3
, Company XYZ has been executing a new business development project for the last 4
months. A few stakeholders have requested a few changes to the scope and have gotten
them approved. When a change is approved what is the next best step to conduct on a
project?
A. Execute the approved change request in the process of Direct and Manage Project Work
B. Execute the approved change request in the process of Monitor and Control Project Work
C. Validate the change in the validate scope process
CORRECT ANSWER
Execute the approved change request in the process of Monitor and Control Project Work
Question 8
A change control board has inform the project manager that a change request made by
stakeholder Mark to reduce the schedule of the project by 2 weeks was rejected. What is
the first step the project manager should take?
A. Resubmit the change request
B. Ask Mark to change his request to 1 week
C. Consult the project team to see how to get this change approve
D. Update the change log
CORRECT ANSWER
Update the change log
Question 9
The deliverable for the product improvement project has been accepted by the sponsor.
What should the project manager do next?
4