PMT 3600v Exam 2 Questions And Answers Latest
Update With Complete Solution 2026/2027 Helpful
Study Guide
Correct
2.5/2.5 Points
1. Based on Scenario Part I, answer the following six questions (questions 1 to
6):
One of the JUPSA Key Performance Parameter (KPP) requirements does not
appear to be achievable without significant cost impacts. The PM is planning
to recommend a change to this validated requirement since it is not clear that
the additional costs are worth the capability added. Who would have to
approve this Acquisition Category (ACAT) I KPP change?
Scenario Part I. The Program Office is busy preparing the joint, Unmanned
Precision Strike Air-Vehicle (JUPSA) for Milestone B, seeking approval to
conduct the Engineering and Manufacturing Development (EMD) phase
activities. Affordability is a key issue since estimated operating and support
costs are higher than what was estimated at Milestone A. In accordance with
the test and evaluation master plan (TEMP), JUPSA conducted developmental
tests and early operational assessments to support the upcoming Milestone B
decision. Test planning for the EMD phase efforts is ongoing. Congressional
interest is very high since JUPSA is an ACAT I, Major Defense Acquisition
Program (MDAP) and has suppliers in nearly every state. As an MDAP
an Independent Cost Estimate(ICE) and an Independent Technical Risk
Assessment (ITRA) were conducted. Meanwhile at least one country has
expressed an interest in Foreign Military Sales (FMS)as soon as possible. The
JUPSA program is not considered by the Milestone Decision Authority to be a
high cost first article acquisition program.
Under Secretary of Defense for Acquisition and Sustainment USD(A&S)
Joint Requirements Oversight Council (JROC)
Milestone Decision Authority (MDA)
Program Executive Officer (PEO)
Correct
2.5/2.5 Points
2. Which of the following is NOT an activity that will be conducted during the
Engineering and Manufacturing Development (EMD) phase for the JUPSA
program?
Scenario Part I. The Program Office is busy preparing the joint, Unmanned
Precision Strike Air-Vehicle (JUPSA) for Milestone B, seeking approval to
conduct the Engineering and Manufacturing Development (EMD) phase
activities. Affordability is a key issue since estimated operating and support
costs are higher than what was estimated at Milestone A. In accordance with
the test and evaluation master plan (TEMP), JUPSA conducted developmental
tests and early operational assessments to support the upcoming Milestone B
, decision. Test planning for the EMD phase efforts is ongoing. Congressional
interest is very high since JUPSA is an ACAT I, Major Defense Acquisition
Program (MDAP) and has suppliers in nearly every state. As an MDAP
an Independent Cost Estimate(ICE) and an Independent Technical Risk
Assessment (ITRA) were conducted. Meanwhile at least one country has
expressed an interest in Foreign Military Sales (FMS)as soon as possible. The
JUPSA program is not considered by the Milestone Decision Authority to be a
high cost first article acquisition program.
Update With Complete Solution 2026/2027 Helpful
Study Guide
Correct
2.5/2.5 Points
1. Based on Scenario Part I, answer the following six questions (questions 1 to
6):
One of the JUPSA Key Performance Parameter (KPP) requirements does not
appear to be achievable without significant cost impacts. The PM is planning
to recommend a change to this validated requirement since it is not clear that
the additional costs are worth the capability added. Who would have to
approve this Acquisition Category (ACAT) I KPP change?
Scenario Part I. The Program Office is busy preparing the joint, Unmanned
Precision Strike Air-Vehicle (JUPSA) for Milestone B, seeking approval to
conduct the Engineering and Manufacturing Development (EMD) phase
activities. Affordability is a key issue since estimated operating and support
costs are higher than what was estimated at Milestone A. In accordance with
the test and evaluation master plan (TEMP), JUPSA conducted developmental
tests and early operational assessments to support the upcoming Milestone B
decision. Test planning for the EMD phase efforts is ongoing. Congressional
interest is very high since JUPSA is an ACAT I, Major Defense Acquisition
Program (MDAP) and has suppliers in nearly every state. As an MDAP
an Independent Cost Estimate(ICE) and an Independent Technical Risk
Assessment (ITRA) were conducted. Meanwhile at least one country has
expressed an interest in Foreign Military Sales (FMS)as soon as possible. The
JUPSA program is not considered by the Milestone Decision Authority to be a
high cost first article acquisition program.
Under Secretary of Defense for Acquisition and Sustainment USD(A&S)
Joint Requirements Oversight Council (JROC)
Milestone Decision Authority (MDA)
Program Executive Officer (PEO)
Correct
2.5/2.5 Points
2. Which of the following is NOT an activity that will be conducted during the
Engineering and Manufacturing Development (EMD) phase for the JUPSA
program?
Scenario Part I. The Program Office is busy preparing the joint, Unmanned
Precision Strike Air-Vehicle (JUPSA) for Milestone B, seeking approval to
conduct the Engineering and Manufacturing Development (EMD) phase
activities. Affordability is a key issue since estimated operating and support
costs are higher than what was estimated at Milestone A. In accordance with
the test and evaluation master plan (TEMP), JUPSA conducted developmental
tests and early operational assessments to support the upcoming Milestone B
, decision. Test planning for the EMD phase efforts is ongoing. Congressional
interest is very high since JUPSA is an ACAT I, Major Defense Acquisition
Program (MDAP) and has suppliers in nearly every state. As an MDAP
an Independent Cost Estimate(ICE) and an Independent Technical Risk
Assessment (ITRA) were conducted. Meanwhile at least one country has
expressed an interest in Foreign Military Sales (FMS)as soon as possible. The
JUPSA program is not considered by the Milestone Decision Authority to be a
high cost first article acquisition program.