1. Piping should have a minimum and maximum slope of ____ inch
A. 1/16"-1/8"
B. 1/8"-1/4"
C. 1/8"-3/16"
D. 1/4"-1/2" - Correct Answer: B. 1/8"-1/4"
2. What is the appropriate way to clean up a small spill of gasoline?
A. allow the product to evaporate from the area
B. wash the spilled product from the area with water
C. apply absorbent to the affected area and leave to soak up fuel
D. apply absorbent to the affected area, then remove & dispose of
absorbent in accordance with applicable requirements - Correct
Answer: D. apply absorbent to the affected area, then remove &
dispose of absorbent in accordance with applicable requirements
3. Placing a bare copper wire from the ____ to the ____ with it's ends exposed
is helpful with pipe run locating.
A. tank monitor to emergency shut-off switch
B. tank to turbine
C. vapor recovery bucket to interstitial monitor
D. dispenser pipe run to the tank turbine - Correct Answer: D.
dispenser pipe run to the tank turbine
,4. One of the approved methods of overfill prevention is to have an overfill
device that will automatically shut off fill into the tank when the tank is a
maximum of ____ % full.
A. 80
B. 90
C. 95
D. 75 - Correct Answer: C. 95
5. In the PEI #300 manual, pressure decay, dynamic back pressure, and A/L
testing satisfy who's testing requirements?
A. CARB
B. water resources
C. environmental health
D. fire department - Correct Answer: A. CARB
6. When removing liquid from a sump or spill bucket and the liquid contains
fuel, it must ____?
A. be managed as hazardous waste
B. pumped into a bucket to evaporate
C. scooped or bailed onto the concrete pad to evaporate
D. put into a sealed container, then put into the trash container -
Correct Answer: A. be managed as hazardous waste
7. Before working on any electrical circuits always de-energize and use
A. NFPA
B. OSHA
C. ICC
D. UBC - Correct Answer: A. NFPA
, 8. The two point Phase I vapor recovery system requires that a separate vapor
recovery riser pipe be installed in the tank and be equipped with a ____?
A. drop-tube
B. locking block valve
C. P/V vent
D. vapor recovery adaptor - Correct Answer: D. vapor recovery
adaptor
9. The term "hanging hardware" refers to...
A. nozzle, hose breakaway
B. vent cap, nozzle, swivel
C. shear valve, UDC, hose
D. sump sensor, vapor valve, nozzle - Correct Answer: A. nozzle,
hose breakaway
10.A valve installed in a motor-vehicle fueling hose designed to separate with
little or no product spillage when excessive pulling force is placed on the
hose is called ____?
A. breakaway
B. hose clamp
C. shear valve
D. flow limiter - Correct Answer: A. breakaway
11.In the PEI #500 manual, a Level II Qualified Person can do all EXCEPT:
a. open cabinet doors
b. reconnect breakaways
c. measure nozzle flow rates