ACG CXA FINAL EXAM ACTUAL QUESTIONS AND
ANSWERS SURE A+
✔✔What is the objective of scheduling Commissioning Process activities? - ✔✔To
integrate and coordinate with other Construction Phase activities and to allow all
Commissioning Team members to plan their work to achieve the OPR.
✔✔Commissioning activities (should / should not) be integrated into the construction
schedule. - ✔✔Should
✔✔What is the primary method used during the Construction Phase to verify that the
installed systems and assemblies comply with the OPR? - ✔✔Site visits
✔✔When does the Occupancy and Operations Phase (i.e. Post-Acceptance Phase)
begin? - ✔✔At substantial completion
✔✔At a minimum, when does the Occupancy and Operations Phase (i.e. Post-
Acceptance Phase) end? - ✔✔Through the contractual warranty/correction period
✔✔What are the two primary documentation requirements for the Construction Phase
Commissioning Process? - ✔✔1.) Construction Phase Commissioning Process Report
2.) Commissioning elements of the Systems Manual
✔✔What phase is the final project Systems Manual completed? - ✔✔The Occupancy
and Operations Phase
✔✔What are the two primary documentation requirements for the Occupancy and
Operations Phase? - ✔✔1.) Final project Cx Process Report
2.) Final project Systems Manual
✔✔What phase are the Owner training requirements developed? - ✔✔Pre-Design
Phase
✔✔What phase is the commissioning team formed? - ✔✔Pre-Design Phase
✔✔What phase is the OPR developed? - ✔✔Pre-Design Phase
✔✔What phase is the initial Cx Plan developed? - ✔✔Pre-Design Phase
✔✔What phase are design reviews performed? - ✔✔Design Phase
✔✔What phase is the OPR and BOD verified? - ✔✔Design Phase
,✔✔What phase are submittals reviewed and verified? - ✔✔Construction Phase
✔✔What phase are test procedures (FPTs) developed? - ✔✔Construction Phase
✔✔What phase is the systems manual verified? - ✔✔Construction Phase
✔✔What phase are construction checklist verified? - ✔✔Construction Phase
✔✔What phase are functional tests implemented? - ✔✔Construction Phase
✔✔What phase is seasonal testing performed? - ✔✔Occupancy and Operations Phase
✔✔What phase is the warranty review? - ✔✔Occupancy and Operations Phase
✔✔What phase is the systems manual outline-expanded? - ✔✔Design Phase
✔✔Who is responsible for Pre-Deisgn Phase Document Control - ✔✔CxA
✔✔Who is responsible for Pre-Deisgn Phase Develop Cx Scope - ✔✔CxA
✔✔Who is responsible for Pre-Deisgn Phase Review DID/OPR - ✔✔CxA
✔✔Who is responsible for Pre-Deisgn Phase Prepare Cx Outline - ✔✔CxA
✔✔Who is responsible for Pre-Deisgn Phase Attend Meetings - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Document Control - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Identify Systems to Cx - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Design Reviews - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Review Cx Specifications - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Design Phase Cx Plan - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Design Phase Kick-Off Meeting - ✔✔Shared
✔✔Who is responsible for Deisgn Phase Draft SVCs - ✔✔Shared
✔✔Who is responsible for Deisgn Phase Draft FPTs - ✔✔Shared
✔✔Who is responsible for Deisgn Phase Attend Meetings - ✔✔CxA
,✔✔Who is responsible for Deisgn Phase Attend Pre-Bid Meeting - ✔✔CxA
✔✔Who is responsible for Construction Phase Pre-Construction Meeting - ✔✔Shared
✔✔Who is responsible for Construction Phase Document Control - ✔✔CxA
✔✔Who is responsible for Construction Phase Construction Cx Plan - ✔✔CxA
✔✔Who is responsible for Construction Phase Cx Schedule Integration - ✔✔CxA
✔✔Who is responsible for Construction Phase Pre-TAB Report Review - ✔✔CxA
✔✔Who is responsible for Construction Phase Review Submittals - ✔✔CxA
✔✔Who is responsible for Construction Phase Update SVCs - ✔✔CxT
✔✔Who is responsible for Construction Phase Approve SVC Updates - ✔✔CxA
✔✔Who is responsible for Construction Phase Approve SVCs - ✔✔CxA
✔✔Who is responsible for Construction Phase Distribute SVCs - ✔✔CxT
✔✔Who is responsible for Construction Phase Update FPTs - ✔✔CxT
✔✔Who is responsible for Construction Phase Approve FPTs - ✔✔CxA
✔✔Who is responsible for Construction Phase Approve FPT Updates - ✔✔CxA
✔✔Who is responsible for Construction Phase Distribute FPTs - ✔✔CxT
✔✔Who is responsible for Construction Phase Site Observations - ✔✔CxT
✔✔Who is responsible for Construction Phase Write SPQC Reports - ✔✔CxT
✔✔Who is responsible for Construction Phase Approve SPQC Reports - ✔✔CxA
✔✔Who is responsible for Construction Phase Distribute SPQC Reports - ✔✔CxT
✔✔Who is responsible for Construction Phase Create RTFs - ✔✔CxA
✔✔Who is responsible for Construction Phase Approve RTFs - ✔✔CxA
, ✔✔Who is responsible for Construction Phase Distribute RTFs - ✔✔CxT
✔✔Who is responsible for Construction Phase Coordination Meetings - ✔✔CxT
✔✔Who is responsible for Construction Phase Progress Meetings - ✔✔CxT
✔✔Who is responsible for Construction Phase Attend Meetings - ✔✔Shared
✔✔Who is responsible for Construction Phase Supervise/Direct CxT - ✔✔CxA
✔✔Who is responsible for Construction Phase Verify SVC Completion/Spot-Check SVC
Accuracy - ✔✔CxT
✔✔Who is responsible for Construction Phase Witness Install Tests - ✔✔CxT
✔✔Who is responsible for Construction Phase Monitor Controls Install - ✔✔CxT
✔✔Who is responsible for Construction Phase Monitor TAB Execution - ✔✔CxT
✔✔Who is responsible for Construction Phase Facilitate Start-Up of Commissioned
Systems - ✔✔CxT
✔✔Who is responsible for Construction Phase Collect Manuf. Checklists - ✔✔CxT
✔✔Who is responsible for Construction Phase Cx Schedule Updates - ✔✔CxA
✔✔Who is responsible for Construction Phase Review "As-Built" Record - ✔✔Shared
✔✔Who is responsible for Construction Phase Review O&M Documents - ✔✔CxT
✔✔Who is responsible for Construction Phase Facilitate O&M Training - ✔✔CxT
✔✔Who is responsible for Construction Phase Track RFI's/CO's/SI's - ✔✔CxT
✔✔Who is responsible for Construction Phase Monitor Project Team Field Reports -
✔✔CxT
✔✔Who is responsible for Construction Phase Document Control - ✔✔CxA
✔✔Who is responsible for Acceptance Phase Controls P to P Review - ✔✔CxT
✔✔Who is responsible for Acceptance Phase Control Program Review - ✔✔CxT
ANSWERS SURE A+
✔✔What is the objective of scheduling Commissioning Process activities? - ✔✔To
integrate and coordinate with other Construction Phase activities and to allow all
Commissioning Team members to plan their work to achieve the OPR.
✔✔Commissioning activities (should / should not) be integrated into the construction
schedule. - ✔✔Should
✔✔What is the primary method used during the Construction Phase to verify that the
installed systems and assemblies comply with the OPR? - ✔✔Site visits
✔✔When does the Occupancy and Operations Phase (i.e. Post-Acceptance Phase)
begin? - ✔✔At substantial completion
✔✔At a minimum, when does the Occupancy and Operations Phase (i.e. Post-
Acceptance Phase) end? - ✔✔Through the contractual warranty/correction period
✔✔What are the two primary documentation requirements for the Construction Phase
Commissioning Process? - ✔✔1.) Construction Phase Commissioning Process Report
2.) Commissioning elements of the Systems Manual
✔✔What phase is the final project Systems Manual completed? - ✔✔The Occupancy
and Operations Phase
✔✔What are the two primary documentation requirements for the Occupancy and
Operations Phase? - ✔✔1.) Final project Cx Process Report
2.) Final project Systems Manual
✔✔What phase are the Owner training requirements developed? - ✔✔Pre-Design
Phase
✔✔What phase is the commissioning team formed? - ✔✔Pre-Design Phase
✔✔What phase is the OPR developed? - ✔✔Pre-Design Phase
✔✔What phase is the initial Cx Plan developed? - ✔✔Pre-Design Phase
✔✔What phase are design reviews performed? - ✔✔Design Phase
✔✔What phase is the OPR and BOD verified? - ✔✔Design Phase
,✔✔What phase are submittals reviewed and verified? - ✔✔Construction Phase
✔✔What phase are test procedures (FPTs) developed? - ✔✔Construction Phase
✔✔What phase is the systems manual verified? - ✔✔Construction Phase
✔✔What phase are construction checklist verified? - ✔✔Construction Phase
✔✔What phase are functional tests implemented? - ✔✔Construction Phase
✔✔What phase is seasonal testing performed? - ✔✔Occupancy and Operations Phase
✔✔What phase is the warranty review? - ✔✔Occupancy and Operations Phase
✔✔What phase is the systems manual outline-expanded? - ✔✔Design Phase
✔✔Who is responsible for Pre-Deisgn Phase Document Control - ✔✔CxA
✔✔Who is responsible for Pre-Deisgn Phase Develop Cx Scope - ✔✔CxA
✔✔Who is responsible for Pre-Deisgn Phase Review DID/OPR - ✔✔CxA
✔✔Who is responsible for Pre-Deisgn Phase Prepare Cx Outline - ✔✔CxA
✔✔Who is responsible for Pre-Deisgn Phase Attend Meetings - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Document Control - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Identify Systems to Cx - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Design Reviews - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Review Cx Specifications - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Design Phase Cx Plan - ✔✔CxA
✔✔Who is responsible for Deisgn Phase Design Phase Kick-Off Meeting - ✔✔Shared
✔✔Who is responsible for Deisgn Phase Draft SVCs - ✔✔Shared
✔✔Who is responsible for Deisgn Phase Draft FPTs - ✔✔Shared
✔✔Who is responsible for Deisgn Phase Attend Meetings - ✔✔CxA
,✔✔Who is responsible for Deisgn Phase Attend Pre-Bid Meeting - ✔✔CxA
✔✔Who is responsible for Construction Phase Pre-Construction Meeting - ✔✔Shared
✔✔Who is responsible for Construction Phase Document Control - ✔✔CxA
✔✔Who is responsible for Construction Phase Construction Cx Plan - ✔✔CxA
✔✔Who is responsible for Construction Phase Cx Schedule Integration - ✔✔CxA
✔✔Who is responsible for Construction Phase Pre-TAB Report Review - ✔✔CxA
✔✔Who is responsible for Construction Phase Review Submittals - ✔✔CxA
✔✔Who is responsible for Construction Phase Update SVCs - ✔✔CxT
✔✔Who is responsible for Construction Phase Approve SVC Updates - ✔✔CxA
✔✔Who is responsible for Construction Phase Approve SVCs - ✔✔CxA
✔✔Who is responsible for Construction Phase Distribute SVCs - ✔✔CxT
✔✔Who is responsible for Construction Phase Update FPTs - ✔✔CxT
✔✔Who is responsible for Construction Phase Approve FPTs - ✔✔CxA
✔✔Who is responsible for Construction Phase Approve FPT Updates - ✔✔CxA
✔✔Who is responsible for Construction Phase Distribute FPTs - ✔✔CxT
✔✔Who is responsible for Construction Phase Site Observations - ✔✔CxT
✔✔Who is responsible for Construction Phase Write SPQC Reports - ✔✔CxT
✔✔Who is responsible for Construction Phase Approve SPQC Reports - ✔✔CxA
✔✔Who is responsible for Construction Phase Distribute SPQC Reports - ✔✔CxT
✔✔Who is responsible for Construction Phase Create RTFs - ✔✔CxA
✔✔Who is responsible for Construction Phase Approve RTFs - ✔✔CxA
, ✔✔Who is responsible for Construction Phase Distribute RTFs - ✔✔CxT
✔✔Who is responsible for Construction Phase Coordination Meetings - ✔✔CxT
✔✔Who is responsible for Construction Phase Progress Meetings - ✔✔CxT
✔✔Who is responsible for Construction Phase Attend Meetings - ✔✔Shared
✔✔Who is responsible for Construction Phase Supervise/Direct CxT - ✔✔CxA
✔✔Who is responsible for Construction Phase Verify SVC Completion/Spot-Check SVC
Accuracy - ✔✔CxT
✔✔Who is responsible for Construction Phase Witness Install Tests - ✔✔CxT
✔✔Who is responsible for Construction Phase Monitor Controls Install - ✔✔CxT
✔✔Who is responsible for Construction Phase Monitor TAB Execution - ✔✔CxT
✔✔Who is responsible for Construction Phase Facilitate Start-Up of Commissioned
Systems - ✔✔CxT
✔✔Who is responsible for Construction Phase Collect Manuf. Checklists - ✔✔CxT
✔✔Who is responsible for Construction Phase Cx Schedule Updates - ✔✔CxA
✔✔Who is responsible for Construction Phase Review "As-Built" Record - ✔✔Shared
✔✔Who is responsible for Construction Phase Review O&M Documents - ✔✔CxT
✔✔Who is responsible for Construction Phase Facilitate O&M Training - ✔✔CxT
✔✔Who is responsible for Construction Phase Track RFI's/CO's/SI's - ✔✔CxT
✔✔Who is responsible for Construction Phase Monitor Project Team Field Reports -
✔✔CxT
✔✔Who is responsible for Construction Phase Document Control - ✔✔CxA
✔✔Who is responsible for Acceptance Phase Controls P to P Review - ✔✔CxT
✔✔Who is responsible for Acceptance Phase Control Program Review - ✔✔CxT