Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 38 pages
Exam (elaborations)

ACG CXA EXAM QUESTIONS WITH VERIFIED ANSWERS 2026 | Complete Review Pack | A+

Document preview thumbnail
Preview 4 out of 38 pages

ACG CXA EXAM QUESTIONS WITH VERIFIED ANSWERS 2026 | Complete Review Pack | A+

Content preview

ACG CXA EXAM QUESTIONS WITH VERIFIED
ANSWERS 2026 | Complete Review Pack | A+
• ASHRAE. CORRECT ANSWER: American Society of Heating, Refrigerating and Air-
Conditioning Engineers

• ANSI. CORRECT ANSWER: American National Standards Institute

• ASTM. CORRECT ANSWER: ASTM International, formerly known as American
Society for Testing and Materials

• ISO. CORRECT ANSWER: International Organization for Standardization

• ASME. CORRECT ANSWER: American Society of Mechanical Engineers

• NFPA. CORRECT ANSWER: National Fire Protection Association

• SMACNA. CORRECT ANSWER: Sheet Metal and Air Conditioning Contractors'
National Association

• What does EBCx stand for?. CORRECT ANSWER: Existing Building Commissioning

• What does FIM stand for?. CORRECT ANSWER: Facility improvement measure

• What does NETA stand for?. CORRECT ANSWER: International Electricl Testing
Associaiton

• What does NFPA stand for?. CORRECT ANSWER: National Fire Protection
Associaiton

• What does NICET stand for?. CORRECT ANSWER: National Institute for Certificaiton
in Engineering Technology

• What does CFR stand for?. CORRECT ANSWER: Current Facility Requirements

• Define ACG. CORRECT ANSWER: AABC Commissioning Group. A non-profit
association dedicated to the advancement of the building commissioning industry

• What does AABC stand for?. CORRECT ANSWER: Associated air balance council

• What does AI stand for?. CORRECT ANSWER: Analog Input

• What does AO stand for?. CORRECT ANSWER: Analog Output

• What does ATC stand for?. CORRECT ANSWER: Automatic Temperature Controls

,• What does BAS stand for?. CORRECT ANSWER: Building Automation system

• What does CA stand for?. CORRECT ANSWER: Commissioning Authority

• What does CT stand for?. CORRECT ANSWER: Cooling Tower

• What does CHWR stand for?. CORRECT ANSWER: Chilled water return

• What does CHWS stand for?. CORRECT ANSWER: Chilled water supply

• What does CWR stand for?. CORRECT ANSWER: Condenser water return

• What does CWS stand for?. CORRECT ANSWER: Condenser water supply

• What does DDC stand for?. CORRECT ANSWER: Direct Digital Control

• What does DI stand for?. CORRECT ANSWER: Digital Input

• What does DID stand for?. CORRECT ANSWER: Design Intent Document

• What does DO stand for?. CORRECT ANSWER: Digital output

• Define FPT. CORRECT ANSWER: Functional Preformance Test. Process of testing
the DDC/BAS/EMS in every possible condition and verifying correct equipment
response. This is the "Heart of the commissioning process".

• What does HVAC stand for?. CORRECT ANSWER: Heating, Ventilation & Air
Conditioning

• What does IAQ stand for?. CORRECT ANSWER: Indoor Air Quality

• What does LEED stand for?. CORRECT ANSWER: Leadership in Energy and
Environmental Design, USGBC trademarked "Green Building Rating System"

• What doesO&M stand for?. CORRECT ANSWER: Operation and Maintenance

• What does OA stand for?. CORRECT ANSWER: Outside Air

• What does PM stand for?. CORRECT ANSWER: Preventive Maintenance

• What does RFP stand for?. CORRECT ANSWER: Request for proposal

• What does RFT stand for?. CORRECT ANSWER: Resolution Tracking Form

• What does SVC stand for?. CORRECT ANSWER: System Verificaiton Checklist

,• Define TAB. CORRECT ANSWER: Testing, Adjusting, and Balancing or Test and
Balance. Process of controlling air and water flow through HVAC equipment.
Recommended that a third party be directly contracted with owner

• What does TBE stand for?. CORRECT ANSWER: Test and Balance Engineer

• What does USGBC stand for?. CORRECT ANSWER: United States Green Building
Council

• What does ECM stand for?. CORRECT ANSWER: Energy Conservation Measure

• What does ANSI stand for?. CORRECT ANSWER: Americans National Standards
Institute

• What does ASTM stand for?. CORRECT ANSWER: American Society for Testing and
Materials International

• What does ISO stand for?. CORRECT ANSWER: International Organization for
Standards

• What does ARI or AHRI stand for?. CORRECT ANSWER: Air Conditionaing,
(Heating), and Refrigeration Instiute

• What does ACCA stand for?. CORRECT ANSWER: Air Conditioning Contractors of
America

• Define UL. CORRECT ANSWER: Underwriters Laboraories - Demonstrates safety,
conformance, sustainablility, etc.

• What does ASME stand for?. CORRECT ANSWER: American Society for Mechanical
Enginners

• What does SMACNA stand for?. CORRECT ANSWER: Sheet Metal and Air
Conditioning Contractos National Institute

• Define Commissioning. CORRECT ANSWER: A systematic process that facilities and
ensure the required communication, coordination testing, and verification and results in
the delivery of a building whose HVAC systems preform as intended.

• During what phase should Commissioning be incorporated?. CORRECT ANSWER:
For best results Commissioning should be included in all phases of the design and
construction process

• Typically how much does Commissioning cost?. CORRECT ANSWER:
Comprehensive HVAC Comissioning cost 2%-5% of HVAC construction cost

, • Define RFQ. CORRECT ANSWER: Request for Qualifications. Document asking for
details concerning previous relevant Cx experience. Information includes:

• Define Re-Commissioning. CORRECT ANSWER: Periodically Re-commissioning
systems that were commissioned when they were new. The purpose is to diagnose the
cause of ongoing, unresolved problems or as part of a planned preventive maintenance
program to prevent issued from arising over time.

• Define Retro-Commissioning. CORRECT ANSWER: Commissioning of existing
systems that were not commissioned when they were new.

• Name the different contruciton models. CORRECT ANSWER: Plan and spec, Design-
Build

• What is included in the Pre-design phase for Comprehensive HVAC Cx?. CORRECT
ANSWER: 1. Cx is established as part of project
2. Owner select CxA
3. Develop Cx Scope
4. CxA review design intent document

• What is included in the Design phase for Comprehensive HVAC Cx?. CORRECT
ANSWER: 1. Review design to ensure it accommodates Cx
2. Write Cx specifications defining contractor responsibilities
3. Establish project schedule

• What is included in the Construction phase for Comprehensive HVAC Cx?. CORRECT
ANSWER: 1. CxA reviews contractor submittals
2. CxA updated Cx plan
3. Cx process is coordinated-through project schedule, Cx plan, and commissioning
meetings
4. Carry out document systems verification checks
5. Carry out the document equipment and system start-ups
6. TAB agency completes and documents test and balance work

• What is included in the Acceptance phase for Comprehensive HVAC Cx?. CORRECT
ANSWER: 1. Carry out functional performance tests on all HVAC systems
2. Train the O&M staff for effective, ongoing operations and maintenance of all systems
3. Provide full documentation

• What is included in the Post-Acceptance phase for Comprehensive HVAC Cx?.
CORRECT ANSWER: 1. Correct any deficiencies, and carry out any required re-testing
2. Carry out any required "off-season" tests
3. Update documentation as required

Document information

Uploaded on
June 10, 2026
Number of pages
38
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
CA$19.96

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
PACKPASS
3.5
(6)
Sold
51
Followers
1
Items
7324
Last sold
4 days ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions