1) A major function of the DOT is to carry out Construction and Reconstruction programs to provide the public with adequate transportation service. - CORRECT ANSWER-True For the DOT, the management of Construction and reconstruction projects involves the following specific responsibilities: A. Planning, Programming and design B. Contract administration C. Contractor payments D. Design and Contract Management E. All of the above - CORRECT ANSWER-E. All of the above 3) To pay for the work performed by Contractors, progress and Final Estimates are needed. True or False? - CORRECT ANSWER-True DESIGN STANDARDS - CORRECT ANSWER-These standards are made available for Design, Construction, Maintenance, and Utility operations on the State Highway System. This booklet provides guidelines and technical drawings for design and Construction personnel. SUPPLEMENTAL AGREEMENTS (SA) - CORRECT ANSWER-SA'S are work of a different characteristic from that shown in the original plans and contract; such as to clarify the Specifications, or pay for unforeseen work.

Mostrar más Leer menos
Institución
CTQP Estimates Level 1
Grado
CTQP Estimates Level 1









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
CTQP Estimates Level 1
Grado
CTQP Estimates Level 1

Información del documento

Subido en
24 de febrero de 2025
Número de páginas
11
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

CTQP Final Estimates Level 1 Exam
Questions With Guaranteed Pass Latest
Update 2025/2026

1) A major function of the DOT is to carry out Construction and Reconstruction
programs to provide the public with adequate transportation service. - CORRECT
ANSWER-True



For the DOT, the management of Construction and reconstruction projects involves the
following specific responsibilities:

A. Planning, Programming and design

B. Contract administration

C. Contractor payments

D. Design and Contract Management

E. All of the above - CORRECT ANSWER-E. All of the above



3) To pay for the work performed by Contractors, progress and Final Estimates are
needed. True or False? - CORRECT ANSWER-True



DESIGN STANDARDS - CORRECT ANSWER-These standards are made available for
Design, Construction, Maintenance, and Utility operations on the State Highway
System. This booklet provides guidelines and technical drawings for design and
Construction personnel.



SUPPLEMENTAL AGREEMENTS (SA) - CORRECT ANSWER-SA'S are work of a
different characteristic from that shown in the original plans and contract; such as to
clarify the Specifications, or pay for unforeseen work.

, WORK ORDERS (WO) - CORRECT ANSWER-WO's are similar to SA's but can't be
used in all instances. They are used to include additional work into the original contract,
and to do minor changes.



JOINT PARTICIPATION AGREEMENTS (JPA) - CORRECT ANSWER-JPA's or Locally
Funded Agreements (LFA)'s are part of the State Contract with a separate Financial ID
Number. They are legal documents between the Department and other government or
private entities. The work would be a utility relocations or installations, etc.



1) Multiple choice. Which of the following is NOT officially considered to be a "Contract
Document"?

A. Supplemental Agreements and Work Orders.

B. Notebooks and Estimates Procedure Manual.

C. Standard Specifications.

D. Construction Manual.

E. Answers B &D - CORRECT ANSWER-E. Answer B & D



2) Multiple choice. Between printings of the Standard Specifications, what does the
Department publish to identify and describe changes in the Specifications?

A. CPAM

B. Supplemental Specifications

C. Work orders

D. Specifications Changes - CORRECT ANSWER-B Supplemental Specifications



3) Multiple choice. Select the correct sequence of documents in order of precedence,
with the document highest in authority listed first.

A. Contract Plans, Development Specifications, Standard Specifications, Special
Provisions, Technical Special Provisions, Supplemental Specifications, Design
Standards.

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
remojudytask Chamberlain College Of Nursing
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
82
Miembro desde
2 año
Número de seguidores
30
Documentos
3120
Última venta
5 días hace

3.2

25 reseñas

5
6
4
3
3
11
2
0
1
5

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes