1) A major function of the DOT is to carry out Construction and Reconstruction
programs to provide the public with adequate transportation service. - CORRECT
ANSWER-True
For the DOT, the management of Construction and reconstruction projects involves the
following specific responsibilities:
A. Planning, Programming and design
B. Contract administration
C. Contractor payments
D. Design and Contract Management
E. All of the above - CORRECT ANSWER-E. All of the above
3) To pay for the work performed by Contractors, progress and Final Estimates are
needed. True or False? - CORRECT ANSWER-True
DESIGN STANDARDS - CORRECT ANSWER-These standards are made available for
Design, Construction, Maintenance, and Utility operations on the State Highway
System. This booklet provides guidelines and technical drawings for design and
Construction personnel.
SUPPLEMENTAL AGREEMENTS (SA) - CORRECT ANSWER-SA'S are work of a
different characteristic from that shown in the original plans and contract; such as to
clarify the Specifications, or pay for unforeseen work.
, WORK ORDERS (WO) - CORRECT ANSWER-WO's are similar to SA's but can't be
used in all instances. They are used to include additional work into the original contract,
and to do minor changes.
JOINT PARTICIPATION AGREEMENTS (JPA) - CORRECT ANSWER-JPA's or Locally
Funded Agreements (LFA)'s are part of the State Contract with a separate Financial ID
Number. They are legal documents between the Department and other government or
private entities. The work would be a utility relocations or installations, etc.
1) Multiple choice. Which of the following is NOT officially considered to be a "Contract
Document"?
A. Supplemental Agreements and Work Orders.
B. Notebooks and Estimates Procedure Manual.
C. Standard Specifications.
D. Construction Manual.
E. Answers B &D - CORRECT ANSWER-E. Answer B & D
2) Multiple choice. Between printings of the Standard Specifications, what does the
Department publish to identify and describe changes in the Specifications?
A. CPAM
B. Supplemental Specifications
C. Work orders
D. Specifications Changes - CORRECT ANSWER-B Supplemental Specifications
3) Multiple choice. Select the correct sequence of documents in order of precedence,
with the document highest in authority listed first.
A. Contract Plans, Development Specifications, Standard Specifications, Special
Provisions, Technical Special Provisions, Supplemental Specifications, Design
Standards.