Collecting a representative sample of concrete to be tested is as important as
executing the test methods to obtain - answer-Accurate results
This practice covers sampling from four types of equipment, which are ___________,
___________, __________, and __________. - answer-stationary mixers, paving mixers,
revolving truck mixers, continuous mixers
The elapsed time between obtaining the first and final portions of a composite
sample shall not exceed - answer-15 min
Portions of a composite sample shall be thoroughly remixed bfore beginning tests
on the sample. True of False? - answer-True, need to recombine
Start the tests for slump, temp, and air content within ______ after obtaining the
final portion of the composite sample? - answer-5 min
Start molding specimens for strength tests within ______ after fabricating the
composite sample? - answer-15 min
The concrete sample must be protected from contamination and - answer-
Evaporation
The minimum size sample for making strength test specimens is - answer-1 cf
When sampling from a stationary mixer, the batch must be sampled at _____ or
more regularly spaced intervals during discharge of the middle portion of the batch
- answer-2
When sampling from a paving mixer, obtain samples from at least ______ different
portions of the pile and combine them into one composite sample for test purposes.
- answer-5
When sampling from a revolving drum truck mixer, sample the concrete by
collecting _____ or more portions taken at regularly spaced intervals during
discharge of the middle portion of this batch. - answer-2
Concrete samples from a truck mixer must be obtained before any water or
admixtures are added to the mixer at the job site. True or False? - answer-False
When the concrete contains aggregate larger than that permitted for a particular
test method, the sample of concrete must be _____ _____ before making the test. -
answer-Wet Screened
The stem of the thermometer is submerged a minimum of ______ into the freshly
mixed concrete. - answer-3 in
, The thermometer shall be capable of accurately measuring the temperature of
freshly mixed concrete to ______ throughout a range of ______. - answer-+/- 1 F, 30-
120 F
The thermometer shall be verified within ______ - answer-at least 1 year of current
use
The temperature of concrete may be measured in a wheelbarrow. True or False? -
answer-True
The temperature of concrete may be measured in a wall form. True or False? -
answer-True
A composite sample of concrete is required even if the only purpose for obtaining
the sample is to determine temperature. True or False? - answer-False
What must be done to the sample container prior to sampling the concrete? -
answer-Dampened
What must be done to the concrete surrounding the thermometer after the device is
submerged in the fresh concrete? - answer-Push concrete around the steam to
ensure the concrete is in full contact with the stem.
How long must the thermometer remain in the freshly mixed concrete? - answer-2-5
min
After the temp of the concrete is read, what is then required? - answer-Record temp
The temperature of the concrete is recorded to the nearest - answer-full degree
There is a specified maximum temp of freshly mixed concrete. True or False? -
answer-False
The sample of concrete used for temp determination must be rodded 25 times. True
or False? - answer-False
When the concrete contains aggregate larger than allowed for the slump test, the
large aggregate must be _____. - answer-Wet screened through 1-1/2 in sieve
The mold for making the slump test is in the shape of _____. - answer-Frustum of a
cone
The height of the slump mold is - answer-12 in
The interior surface of the slump mold is allowed to have minor irregularities. True
or False? - answer-False
For use in the slump test, the end or both ends of the tamping rod must be _____. -
answer-Rounded to a hemispherical tip