100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

PJM Exam Questions And 100% Accurate Answers

Puntuación
-
Vendido
-
Páginas
37
Grado
A+
Subido en
13-10-2024
Escrito en
2024/2025

PJM Exam Questions And 100% Accurate Answers...

Institución
PJM
Grado
PJM











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
PJM
Grado
PJM

Información del documento

Subido en
13 de octubre de 2024
Número de páginas
37
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

  • pjm
  • pjm exam

Vista previa del contenido

PJM Exam Questions And 100% Accurate Answers


Leading phase when current is. - ANSWER Capacitive



What is the pass mark for a unit regulation test? - ANSWER 75% compliance with the test
signal



What resource generation is available in less than 10 minutes for offline reserves? -
ANSWER Quick-start



How does PJM avoid dealing with economic issues during transmission related
operational constraints? - ANSWER Cost (offer) capping generation



Which balance control mode does PJM use for normal operations? ANSWER Tie-line
bias



Three modes of control available to PJM dispatcher ACE control modes ANSWER Flat
Frequency Control, Flat Tie Line Control, Tie Line Bias Control



What is Flat Frequency Control? - ANSWER Uses only power system frequency as the
controlling parameter; responds only to frequency deviations; applies only when PJM
balancing area is islanded from the Eastern Interconnection



What is flat tie line control? - ANSWER Utilizes only interconnection tie line flow as the
controlling parameter; only responds to net tie flow deviations & does not adjust
operation for any frequency deviations; limited to special circumstances



What is tie line bias control? - ANSWER most widely used mode of control for
multi-balancing area power systems; responds to both frequency & net tie line flow
deviations

,To lower system voltage, MVAR must be shed in which direction to lower MW? -
ANSWER Decrease MVAR



What percent of regulation does PJM require for a system restoration? - ANSWER 2% of
current load



At what frequency will a system blackout? - ANSWER 57.5 Hz or lower



What minimum threshold is considered to be part of the BES? - ANSWER 100 kV or
greater



What is the Bulk Electric System (BES)? - ANSWER The electrical generation resources,
transmission lines, interconnections with neighboring systems, & associated equipment
generally operated at voltages 100 kV or higher



What are the limits that must be submitted to PJM for generating units? - ANSWER Eco
min, Eco max, Emergency Max



During high geomagnetic activity (>10 amperes at Missouri Ave or Meadowbrook
facility) what must be immediately implemented? - ANSWER Conservative operation



Other triggers that would call for conservative operations? - ANSWER fuel delivery
problems, forest/brush fires, environmental alerts, bad weather, terrorist or sabotage
threats against the BES, actual attacks against critical assets, PJM entering an
"unknown operating state"



What is conservative operations? - ANSWER PJM should implement additional actions
under specific events, conditions, or circumstances that could threaten the reliability of
the BES



What problems usually occur during minimum generation conditions? - ANSWER Excess

,generation online & high voltage



A unit is cost capped - WHEN During transmission related constraints



What is cost capping? - ANSWER Principles used by PJM when considering cost
containment provisions; all offers (cost & price) capped at $1,000/MWh by default and
offers over will need verification



If SCADA and ICCP go down, where should data be updated? - ANSWER EMS (Energy
Management System)



How often is reactive testing completed? - ANSWER Every 5 years



What mechanical device controls deviations in voltage? - ANSWER Load tap changer



For a generator unable to maintain its voltage schedule, who can approve a
replacement schedule? - ANSWER Transmission Owner



Under PJM's consideration, using what two elements for load forecasting? - ANSWER
Weather & day of the week



During system restoration, a generator should not be loaded above what level? -
ANSWER Dynamic Reserve



What is the dynamic reserve? - ANSWER the amount of reserve available to preserve the
system during a frequency disturbance; comprised of reserve on generators & load with
underfrequency relaying



What unit is allowed to set LMP? - ANSWER A unit that is dispatched for constraint
control

, At what fuel limit must PJM be notified for a black start unit? - ANSWER 10 hours



What is a black start unit? - ANSWER Generating units that are able to start without an
outside electrical supply or a unit with high operating factor to remain operating at
reduced levels when automatically disconnected from the grid



Why are black start units needed? - ANSWER necessary to restore the PJM transmission
system following a blackout; designate specific generators whose location &
capabilities are required to re-energize the system



Where does MET (meteorological) tower are used? - ANSWER Wind farms



Which generators must go through ICAP (installed capacity) testing? - ANSWER All
except wind & solar generators



What is ICAP (installed capacity)? - ANSWER The summer net capability of a generating
unit



What allows a circuit breaker between two control areas to be manually closed? -
ANSWER Synchroscope - shows the extent to which two systems are in sync with each
other



What does PJM monitor for three types of transmission constraints? - ANSWER
Reactive, Stability, Thermal (transfer limits)



To lower system voltage, it is necessary to reduce --- in order to reduce --- - ANSWER
MW, MVAR



The winter load shape in PJM has two peaks, true/false? - ANSWER TRUE



When corrections are made for the time error and the system schedule frequency must

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Easton West Virgina University
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
501
Miembro desde
2 año
Número de seguidores
221
Documentos
21905
Última venta
6 horas hace

3.9

111 reseñas

5
53
4
21
3
21
2
7
1
9

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes