Which of the following is an example of work performance information? a. A project manager realizes that a late shipment will delay the entire project by 4 days b. A project manager manager shares a report with stakeholders that contains an updated project schedule. c. A develop informs you that a task takes 3 hours to perform d. A QA analyst writes a blog post containing tornado diagrams from the latest round of testing. - ANSWER a. A project manager realizes that a late shipment will delay the entire project by 4 days The realization by the project manager about the impact that a late shipment has on the project is work performance information. This is information because the raw data has been analyzed and assessed

Mostrar más Leer menos
Institución
PMP
Grado
PMP









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
PMP
Grado
PMP

Información del documento

Subido en
7 de octubre de 2024
Número de páginas
13
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

  • pmp exam prep
  • pmp

Vista previa del contenido

PMP Exam Prep 2024 LATEST UPDATE
CORRECT 100%
Which of the following is an example of work performance information?



a. A project manager realizes that a late shipment will delay the entire project by 4 days



b. A project manager manager shares a report with stakeholders that contains an updated project
schedule.



c. A develop informs you that a task takes 3 hours to perform



d. A QA analyst writes a blog post containing tornado diagrams from the latest round of testing. -
ANSWER a. A project manager realizes that a late shipment will delay the entire project by 4 days



The realization by the project manager about the impact that a late shipment has on the project is work
performance information. This is information because the raw data has been analyzed and assessed for
the impact on the project. The developer's statement about duration is simply raw data; there is no
assessment of this data to qualify it as information. The report on the project schedule and blog post
containing diagrams are both examples of reports because this information has been distributed and can
be acted on.



Rose has a student intern shadowing her for the day to learn about project management. Rose is
discussing change management with the intern when she is asked about the project manager's role in
the change management process. Which of the following is not a responsibility of the project manager?



A. The project manager is responsible for approving or rejecting change requests.



B. The project manager should prevent the root causes of changes

, C. The project manager is responsible for developing the change management plan.



D. The project manager is responsible for assessing the impacts of proposed changes. - ANSWER A. The
Project Manager is responsible for approving or rejecting change requests.



Conducting a stakeholder analysis will help ensure that all project benefits are identified. This allows all
stakeholders to voice what it is they hope that the project will achieve. Sharing all project reports may be
unnecessary and will not help identify project benefits. Composing a requirements traceability matrix
will help ensure that requirements are met, but these are only known requirements. This may overlook
unknown project benefits. Approving all change requests is unnecessary and not helpful for identifying
project benefits.



Which of the following represents a compliance risk?



A. A strike near the Panama Canal threatens a project's on-time delivery



B. A key technical contributor left the company for another job



C. A software developer does not enable two-factor authentication in a database containing customers'
financial data



D. A rare material required for manufacturing may not be available in the quantity needed. - ANSWER C.
A software developer does not enable two-factor authentication in a database containing customers'
financial data.



Every example here is an example of a risk, however, only the lack of two-factor authentication is an
example of compliance risk. This is a compliance risk because of the lack of extra security, two-factor
authentication. This is a legal risk when handling customer data. All other examples here are general
project risks, not compliance risks.



Joanna is the project manager for Project ICS. Marcey is the project manager for FSL. Both projects have
similar objectives that benefit the Development department of their firm. A portion of Joanna's project is
experiencing some delays. This harms some resource availability requirements for Marcey's project. Who
should be responsible for managing this issue?

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Lecchris West Virgina University
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
40
Miembro desde
2 año
Número de seguidores
15
Documentos
3203
Última venta
1 mes hace
LECCHRIS

3.8

6 reseñas

5
2
4
1
3
3
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes