100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

PMP Exam Prep Simplified - Definitions – 2024 LATEST UPDATE!!!

Puntuación
-
Vendido
-
Páginas
14
Grado
A+
Subido en
07-10-2024
Escrito en
2024/2025

Acceptance Criteria - ANSWER A set of conditions that are met before deliverables are accepted by the customers or sponsors. Activity - ANSWER A distinct, scheduled portion of work performed during the course of a project. Actual Cost (AC) - ANSWER The actual cost incurred for the work performed on an activity during a specific time period. Analogous Estimating - ANSWER A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.

Mostrar más Leer menos
Institución
PMP
Grado
PMP









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
PMP
Grado
PMP

Información del documento

Subido en
7 de octubre de 2024
Número de páginas
14
Escrito en
2024/2025
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

PMP Exam Prep Simplified - Definitions –
2024 LATEST UPDATE!!!
Acceptance Criteria - ANSWER A set of conditions that are met before deliverables are accepted by the
customers or sponsors.



Activity - ANSWER A distinct, scheduled portion of work performed during the course of a project.



Actual Cost (AC) - ANSWER The actual cost incurred for the work performed on an activity during a
specific time period.



Analogous Estimating - ANSWER A technique for estimating the duration or cost of an activity or a
project using historical data from a similar activity or project.



Assumption - ANSWER A factor in the planning process that is considered to be true, real, or certain,
without proof or demonstration.



Backward Pass - ANSWER A critical path method technique for calculating the late start and late finish
dates by working backward through the schedule model from the project end date.



Baseline - ANSWER The accepted version of work product that can be changed using formal change
control processes and is used as the basis for comparison to actual results.



Bottom-Up Estimating - ANSWER A method of estimating project duration or cost by aggregating the
estimates of the lower-level components of the work breakdown structure (WBS).



Budget at Completion (BAC) - ANSWER The amount of all budgets established for the work to be
performed.



Change Control - ANSWER A process whereby modifications to documents, deliverables, or baselines
associated with the project are identified, documented, approved, or rejected.

, Change Control Board - ANSWER A formally commissioned group responsible for reviewing, assessing,
approving, deferring, or rejecting changes to the project, and for recording and communicating such
decisions.



Change Control System - ANSWER A set of procedures that describes how modifications to the project
deliverables and documentation are managed and controlled.



Change Request - ANSWER A formal proposal to modify any document, deliverable, or baseline in the
project management plan.



Communications Management Plan - ANSWER a component of the project management plan that
describes how, when, and by whom information about the project will be administered and distributed



Configuration Management System - ANSWER A collection of procedures used to track project artifacts
and monitor and control changes to these artifacts.



Constraint - ANSWER A restrictive feature that affects the execution of a project.



Contigency Reserves - ANSWER Time or money assigned in the schedule or cost baseline form known
risks with response strategies.



Corrective Action - ANSWER A planned activity that restores the performance of the project work with
the project management plan.



Cost Baseline - ANSWER The approved version of work package cost estimates and contingency reserve
that can be changed using formal change control procedures.



Cost Management Plan - ANSWER A component of a project or program management plan that
describes how costs will be planned and controlled.



Cost Performance Index (CPI) - ANSWER A measure of the cost efficiency of budgeted resources
expressed as the ratio of earned value to actual cost.
$10.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Lecchris West Virgina University
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
40
Miembro desde
2 año
Número de seguidores
15
Documentos
3203
Última venta
1 mes hace
LECCHRIS

3.8

6 reseñas

5
2
4
1
3
3
2
0
1
0

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes