Construction Duration Classifications - Answer Contingency classifications: Organic (up to 90 days), Initial (6 months), Temporary (5 years), Semi-permanent (2-10 Years) Enduring Classification: permanent (5 years or longer) When making a road, what is the reason that more than one layer or material is used? - Answer Save money because top layers cost more Layers of a road - Answer Surface Base course Sub base select materials compacted subgrade Two levels of quality control - Answer Unit quality management program and project quality management program What are CDRs of construction units responsible for? - Answer Establishing and using a company quality management program performance work statement - Answer a part of the Statement of Work that is performance based and directly explains what the contractor is going to do Steps to clearing and repairing a crater on the minimum operating strip (MOS) - Answer 1. Clear area of debris (Air field clearance team with chem lights, e tools, etc) Clear 20 ft. 2. Conduct profile measurements. ID area of upheaval using line of sight method and stanchions parallel to runway surface. 3. Remove debris with IHMEE, shovel or other dig asset. 4. Sort debris and stockpile away from MOS (30 ft away, no higher than 3 feet to ensure aircraft clearance) 5. Choose Expedient Repair Methods: Debris backfill repair, choke ballast over debrist, choke ballast repair, sand grid repair 6. Cover with FOD 12" around crater with FOD kit (FRP panels, anchor bolts) 7. Reinforce using concrete or stone and grout repair for permanent repair 8. QAQC the whole time through methods like checking compaction for CBR

Vista previa del contenido

Construction: PE Exam – Construction
Questions Fully Solved 2026 Updated
Types of Loads - Answer Dead, Live, Construction, Environmental, and Lateral Earth Pressure



Available Design Methods for Construction Loads - Answer Allowable Stress Design (ASD)

Load and Resistance Factor Design (LRFD)



Building Type & Construction Method - Answer Residential: Light wood stick framing

Commercial: Wood, steel, or masonry

High-rise and other commercial: heavy steel framing or reinforced concrete

Long-Span Bridges: steel cables



Wood Framing - Answer Most common way to build houses in NA



Simplified Building Procedure for Wood House - Answer 1. Place concrete foundation

2. Place first floor walls

3. Construct wood platform to build second floor

4. Place second floor walls

5. Place roof on top of 2nd floor walls



Steel Framing - Answer Most common for high-rise and commercial buildings

Similar to wood but with less flexibility

High strength & relatively light weight

Expensive compared to other materials



Concrete Structures - Answer Concrete systems are commonly used in high-ride buildings

More resistant to fire than steel or wood

Less prone to corrosion than steel (common for UG structures)



Simplified Building Procedure for Concrete Structures - Answer 1. Prepare concrete mix
design

2. Prepare formwork

3. Pour steel reinforcement

4. Pour Concrete

,5. Allow for concrete curing process

6. Disassemble formwork



Advantage of Precast Concrete - Answer Higher quality fabrication from casting off-site

Can accelerate construction schedules



A two-story multi-family residential structure is being construction in a high seismic area. Which
construction type is most likely to be used? - Answer Wood Framing

(2-story, low rise residential)

"High-seismic" is a distractor



Temporary Structures - Answer May be removed at end of construction (usually)

May be incorporated into the finished structure

Concrete formwork is a common example of temporary structure



Design Considerations of Concrete formwork - Answer Dead Load: weight of fresh concrete
plus form self weight

Live Load: 50-75 psf depending on equipment used (to pour concrete)

Lateral pressure exerted by fresh concrete



Typical formwork material - Answer 3/4" plywood that is coated on one side



Types of concrete formwork - Answer Slab Formwork

Beam Formwork

Column/Wall Formwork (look at photos)



Equation for Lateral Pressures of Concrete - Answer ACI 347R-14 Table 4.2.2.1a(a)



Project Management Process Groups - Answer Initiation -> Planning -> executing ->
Controlling and monitoring (loop back to planning) -> closing

Ex. of loop (Value Engineering)



Gantt Chart - Answer Small to mid-size projects

Forecast & manage resources (labor, equipment, budgets, etc)

Disadvantage: doesn't show all the links/sequencing

, Critical Path Method (CPM) - Answer Project modeling technique that identifies the most
critical activities on a schedule

Helps monitor the assets, expenses, and advancement of the project

Activity on Node (AON) is most common



PERT - Answer Program Evaluation Review Technique (also known as CPM)



Float Time (slack time) - Answer Amount of time that an activities can be delayed without
affecting the overall schedule (applies to activities not on CP)



Applying the CPM (steps) - Answer 1. Specify each activity

2. Sequence the activities

3. Draw the network diagram

4. Identify the CP

5. Update to show progress



AOA (Activity on Arc)

Define Dummy Nodes & Dummy Activities - Answer Dummy Node: Used when 2 activities
have the same starting and ending event

Dummy Activity: Have no duration, used to prevent an activity from occurring in more than 2
spot



Contract Documents (what is included?) - Answer Contract Terms

Quantity and cost estimates

project and task descriptions (SOW)

Specification of the deliverables

Time, resources, and payment



Design Sequencing Phases - Answer Schematic Design

Design Development

Construction Documents

Bidding Process



Project Costs - Answer Direct Costs (Raw materials, labor, fuel, etc)

Indirect Costs (Overhead, taxes, administrative)

Información del documento

Subido en
30 de junio de 2026
Número de páginas
22
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$12.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TestSolver9
3.6
(185)
Vendido
1058
Seguidores
131
Artículos
33290
Última venta
1 día hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes