100% Zufriedenheitsgarantie Sofort verfügbar nach Zahlung Sowohl online als auch als PDF Du bist an nichts gebunden 4.2 TrustPilot
logo-home
Prüfung

CON 1200V - Final Exam Accurate Questions and accurate Answers Latest Update Grade A+ (Complete Solutions)

Bewertung
-
Verkauft
-
seiten
17
Klasse
A+
Hochgeladen auf
28-10-2025
geschrieben in
2025/2026

CON 1200V - Final Exam Accurate Questions and accurate Answers Latest Update Grade A+ (Complete Solutions)

Hochschule
CON 1200V
Kurs
CON 1200V










Ups! Dein Dokument kann gerade nicht geladen werden. Versuch es erneut oder kontaktiere den Support.

Schule, Studium & Fach

Hochschule
CON 1200V
Kurs
CON 1200V

Dokument Information

Hochgeladen auf
28. oktober 2025
Anzahl der Seiten
17
geschrieben in
2025/2026
Typ
Prüfung
Enthält
Fragen & Antworten

Themen

Inhaltsvorschau

CON 1200V - Final Exam Accurate
Questions and accurate Answers Latest
Update Grade A+ (Complete Solutions)
Which of the following statements is correct regarding the government's policy for describing
agency needs?




When should acquisition planning begin?



When a Source Selection Authority has been identified

When the requirement is received and accepted by the Contracting Officer

When certified funds become available

As soon as the agency need is identified

As soon as the agency need is identified




According to FAR 7.105, a written acquisition plan has two main parts, which are:



Acquisition background and objectives, and plan of action

Competition, and cost

Performance period requirements, and source selection procedures

Risks, and sources

,Acquisition background and objectives, and plan of action




Which of the following is not a factor to be considered in the determination of whether to lease
or purchase equipment?


Net purchase price of equipment

Cumulative rental payments for the estimated period of use

Prior experience with contractors when leasing equipment
Estimated length of time equipment will be used
Prior experience with contractors when leasing equipment




Which of following is not a reason for the government to provide Government Furnished
Property (GFP)?


It is in the best interest of the government

The benefit outweighs the increased cost of administration

Government requirements cannot otherwise be met

It results in decreased competition to enable more efficient source selection
It results in decreased competition to enable more efficient source selection




An acquisition team is developing the Acquisition Plan for a complex requirement. The
following are risks that could impact the acquisition schedule EXCEPT:

, Late deliveries

Use of a Critical Path Method (CPM) schedule type

Political pressure
Changing requirements
Use of a Critical Path Method (CPM) schedule type

Market research should be used to limit competition to save procurement time.

Restrictive provisions can only be used to the extent necessary to meet agency needs or as
authorized by law
Requirements should be defined in terms that encourage offerors to supply government-unique
items
Prime contractors should not be required to incorporate commercial products as components of
the items being supplied to the agency
Restrictive provisions can only be used to the extent necessary to meet agency needs or as
authorized by law




Which of the following types of requirements documents state desired outcomes with associated
standards for the services being acquired?


Design oriented document

Guide

Performance oriented document

Standards
Performance oriented document




What statement is true regarding product and service codes?
10,97 €
Vollständigen Zugriff auf das Dokument erhalten:

100% Zufriedenheitsgarantie
Sofort verfügbar nach Zahlung
Sowohl online als auch als PDF
Du bist an nichts gebunden

Lerne den Verkäufer kennen

Seller avatar
Bewertungen des Ansehens basieren auf der Anzahl der Dokumente, die ein Verkäufer gegen eine Gebühr verkauft hat, und den Bewertungen, die er für diese Dokumente erhalten hat. Es gibt drei Stufen: Bronze, Silber und Gold. Je besser das Ansehen eines Verkäufers ist, desto mehr kannst du dich auf die Qualität der Arbeiten verlassen.
TUTOR007 University Of Houston - Main Campus
Folgen Sie müssen sich einloggen, um Studenten oder Kursen zu folgen.
Verkauft
29
Mitglied seit
1 Jahren
Anzahl der Follower
7
Dokumente
2177
Zuletzt verkauft
3 Jahren vor

3,8

5 rezensionen

5
2
4
1
3
1
2
1
1
0

Kürzlich von dir angesehen.

Warum sich Studierende für Stuvia entscheiden

on Mitstudent*innen erstellt, durch Bewertungen verifiziert

Geschrieben von Student*innen, die bestanden haben und bewertet von anderen, die diese Studiendokumente verwendet haben.

Nicht zufrieden? Wähle ein anderes Dokument

Kein Problem! Du kannst direkt ein anderes Dokument wählen, das besser zu dem passt, was du suchst.

Bezahle wie du möchtest, fange sofort an zu lernen

Kein Abonnement, keine Verpflichtungen. Bezahle wie gewohnt per Kreditkarte oder Sofort und lade dein PDF-Dokument sofort herunter.

Student with book image

“Gekauft, heruntergeladen und bestanden. So einfach kann es sein.”

Alisha Student

Häufig gestellte Fragen