Plumbing Statues and Rules Exam Graded A+
A construction contract must be in writing and contain the nine minimum elements of a
contract when the dollar amount is more than _______. - ANSWER-$1,000
A contract must be in writing and include the nine minimum elements of a contract if the
dollar amount is more than _________. - ANSWER-$1,000
A contractor cannot file a lawsuit for payment in Arizona unless they are licensed on the
date the contract was entered into and the __________. - ANSWER-Date the alleged
cause for action occurred
A contractor installs a new roof for a homeowner on January 1st. On February 1st the
roof leaks in the northeast corner. On March 1st the contractor returns to fix the leak.
When does the statute of limitations expire for the areas of the roof other than the
northeast corner? - ANSWER-2 years from January 1st
A contractor installs a new roof for a homeowner on January 1st. On February 1st the
roof leaks in the northeast corner. On March 1st the contractor returns to fix the leak.
When does the statute of limitations expire for the northeast corner of the roof? -
ANSWER-2 years from March 1st
A contractor may satisfy the bond requirement with a ___________. (Surety bond, Cash
bond, Certificate of deposit) - ANSWER-All of the above
A contractor paints a door for a homeowner on January 1st. On February 1st, the paint
peels. On March 1st, the contractor returns to repaint the door. When does the statute
of limitations expire for painting the door? - ANSWER-2 years from March 1st
A contractor who fails to file a response to a citation from the Registrar may face the
following consequence (s). (Failure to file deemed admission of allegations, Failure to
file deemed cause for revocation of license, Failure to file deemed cause for suspension
of license.) - ANSWER-All of the above
A contractor who owes money to the Residential Contractors' Recovery Fund must
repay the full amount of the claim that was awarded as well as __________. -
ANSWER-10% annual interest
A license that has not been renewed by the renewal date is automatically ________. -
ANSWER-Suspended
A licensed contractor has just received a copy of a lien filed against an owner. The
owner intends to retain the amount owed to the lien from the next progress payment
from the owner to the contractor. The contractor has how many days to dispute the lien?
- ANSWER-10 days
, A licensee may request an informal settlement conference prior to a formal hearing no
less than__________prior to the hearing. - ANSWER-20 days
A licensee who continues to contract after their license has been suspended could face
a civil penalty of up to ______. - ANSWER-$1,000
A licensee who receives notice of a claim to be paid from the Residential Contractors'
Recovery Fund may request a hearing to contest the claim within ______ of when it was
mailed. - ANSWER-15 days
A military spouse who is relocating to Arizona may waive the trade exam if they have
had a license in a comparable classification for ________. - ANSWER-1 year
A new qualifying party must have at least two years of experience performing or
supervising the type of work covered by a license classification within the last ______. -
ANSWER-10 years
A person who has been convicted of contracting without a license is barred from being
part of a license application for _______. - ANSWER-1 year
a surety bond for a contractor must be made out to the ___________. - ANSWER-
Licensee
According to the Prompt Pay Act, late payments to subcontractors and material
suppliers are subject to a monthly interest rate of at least _______. - ANSWER-1.5%
According to the Prompt Pay Act, owners have the right to refuse to certify and approve
a bill or estimate within ________ of receiving the bill or estimate. - ANSWER-14 days
According to the requirements for displaying an ROC license number, contractors may
provide a website instead of an ROC number in what locations? (Vehicle advertising,
Billboard advertisements, Internet advertisements) - ANSWER-All of the above
After an administrative hearing regarding a complaint against a license, the
administrative law judge must issue a recommendation to the Registrar within ______. -
ANSWER-20 days
An ROC license number is only considered to be "prominently displayed" on a website if
it is clearly visible ________. - ANSWER-On the home page
As part of a final administrative decision following an administrative hearing, the
Registrar may file an order to pay restitution to the claimant that may include: (Attorney
fees, Costs to repair damages, loss of income) - ANSWER-Costs to repair damages
Failure to pay a supplier could be grounds for suspension if the licensee owes more
than _________. - ANSWER-$750
A construction contract must be in writing and contain the nine minimum elements of a
contract when the dollar amount is more than _______. - ANSWER-$1,000
A contract must be in writing and include the nine minimum elements of a contract if the
dollar amount is more than _________. - ANSWER-$1,000
A contractor cannot file a lawsuit for payment in Arizona unless they are licensed on the
date the contract was entered into and the __________. - ANSWER-Date the alleged
cause for action occurred
A contractor installs a new roof for a homeowner on January 1st. On February 1st the
roof leaks in the northeast corner. On March 1st the contractor returns to fix the leak.
When does the statute of limitations expire for the areas of the roof other than the
northeast corner? - ANSWER-2 years from January 1st
A contractor installs a new roof for a homeowner on January 1st. On February 1st the
roof leaks in the northeast corner. On March 1st the contractor returns to fix the leak.
When does the statute of limitations expire for the northeast corner of the roof? -
ANSWER-2 years from March 1st
A contractor may satisfy the bond requirement with a ___________. (Surety bond, Cash
bond, Certificate of deposit) - ANSWER-All of the above
A contractor paints a door for a homeowner on January 1st. On February 1st, the paint
peels. On March 1st, the contractor returns to repaint the door. When does the statute
of limitations expire for painting the door? - ANSWER-2 years from March 1st
A contractor who fails to file a response to a citation from the Registrar may face the
following consequence (s). (Failure to file deemed admission of allegations, Failure to
file deemed cause for revocation of license, Failure to file deemed cause for suspension
of license.) - ANSWER-All of the above
A contractor who owes money to the Residential Contractors' Recovery Fund must
repay the full amount of the claim that was awarded as well as __________. -
ANSWER-10% annual interest
A license that has not been renewed by the renewal date is automatically ________. -
ANSWER-Suspended
A licensed contractor has just received a copy of a lien filed against an owner. The
owner intends to retain the amount owed to the lien from the next progress payment
from the owner to the contractor. The contractor has how many days to dispute the lien?
- ANSWER-10 days
, A licensee may request an informal settlement conference prior to a formal hearing no
less than__________prior to the hearing. - ANSWER-20 days
A licensee who continues to contract after their license has been suspended could face
a civil penalty of up to ______. - ANSWER-$1,000
A licensee who receives notice of a claim to be paid from the Residential Contractors'
Recovery Fund may request a hearing to contest the claim within ______ of when it was
mailed. - ANSWER-15 days
A military spouse who is relocating to Arizona may waive the trade exam if they have
had a license in a comparable classification for ________. - ANSWER-1 year
A new qualifying party must have at least two years of experience performing or
supervising the type of work covered by a license classification within the last ______. -
ANSWER-10 years
A person who has been convicted of contracting without a license is barred from being
part of a license application for _______. - ANSWER-1 year
a surety bond for a contractor must be made out to the ___________. - ANSWER-
Licensee
According to the Prompt Pay Act, late payments to subcontractors and material
suppliers are subject to a monthly interest rate of at least _______. - ANSWER-1.5%
According to the Prompt Pay Act, owners have the right to refuse to certify and approve
a bill or estimate within ________ of receiving the bill or estimate. - ANSWER-14 days
According to the requirements for displaying an ROC license number, contractors may
provide a website instead of an ROC number in what locations? (Vehicle advertising,
Billboard advertisements, Internet advertisements) - ANSWER-All of the above
After an administrative hearing regarding a complaint against a license, the
administrative law judge must issue a recommendation to the Registrar within ______. -
ANSWER-20 days
An ROC license number is only considered to be "prominently displayed" on a website if
it is clearly visible ________. - ANSWER-On the home page
As part of a final administrative decision following an administrative hearing, the
Registrar may file an order to pay restitution to the claimant that may include: (Attorney
fees, Costs to repair damages, loss of income) - ANSWER-Costs to repair damages
Failure to pay a supplier could be grounds for suspension if the licensee owes more
than _________. - ANSWER-$750