While trying to obtain the formal acceptance of the completed project scope and associated deliverables, with whom should the project manager validate the product?

a. The sponsor, key stakeholders and customers

b. The customers

c. The quality control team members

d. Then change control board members - ANSWERSa. The sponsor, key stakeholders and customers



The scope baseline, which consists of the project scope statement, the WBS, and the WBS dictionary, is used as an input to all the follo...