Interdependent tasks A firm begins its strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a business management project. Which aspect of project management applies to this firm's project? Improvement in product design A firm begins its strategic business initiative of developing a new business model to enhance its competitiveness. What can be identified as a strategic business initiative for this firm? Project sponsor A firm begins a strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. Which stakeholder would have triggered this strategic business initiative? Closing process group Which group is included in the five process groups? PRojects IN a Controlled Environment What does PRINCE2 stand for? Executing Which PMBOK process group is described as the delivery part of project management where the main activity happens? Lines of authority are clear. Which advantage does the functional (departmentalized) organizational structure provide for a firm with multiple projects? The U.S. Department of State & The U.S Department of Energy Which two organizations are examples of organizations with the functional organizational structure? Project team members gain access to historical data from other projects. An organization expects to use a project management office (PMO) to support multiple projects that will be implemented within a projectized organizational structure. Which implied effect is a benefit to this organization? Projects will coordinate resource usage by monitoring the status of shared resources.

Meer zien Lees minder
Instelling
Vak










Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Vak

Documentinformatie

Geüpload op
2 december 2025
Aantal pagina's
20
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

WGU C722



WGU C722 Practice Test Study Questions
and Answers Top Graded 2026

Interdependent tasks

A firm begins its strategic business initiative of developing a new business
model that will allow the firm to deliver an efficient, tailored service to its
customers. To accomplish this, the firm initiates a business management
project.


Which aspect of project management applies to this firm's project?

Improvement in product design

A firm begins its strategic business initiative of developing a new business
model to enhance its competitiveness.


What can be identified as a strategic business initiative for this firm?

Project sponsor

A firm begins a strategic business initiative of developing a new business
model that will allow the firm to deliver an efficient, tailored service to its
customers.


Which stakeholder would have triggered this strategic business initiative?

Closing process group



WGU C722

,WGU C722


Which group is included in the five process groups?

PRojects IN a Controlled Environment

What does PRINCE2 stand for?

Executing

Which PMBOK process group is described as the delivery part of project
management where the main activity happens?

Lines of authority are clear.

Which advantage does the functional (departmentalized) organizational
structure provide for a firm with multiple projects?

The U.S. Department of State & The U.S Department of Energy

Which two organizations are examples of organizations with the functional
organizational structure?

Project team members gain access to historical data from other projects.

An organization expects to use a project management office (PMO) to
support multiple projects that will be implemented within a projectized
organizational structure.


Which implied effect is a benefit to this organization?

Projects will coordinate resource usage by monitoring the status of shared
resources.




WGU C722

, WGU C722


Regardless of the organizational structure used to manage a project, an
organization elects to use a project management office (PMO).


Which benefit will this organization gain?

Planning

During a certain project phase, specific blueprints are drawn and approved,
materials and labor costs are estimated, prototypes are created, and work
activities and tasks are identified. Also, quality expectations, measurements,
and costs are defined.


During which project phase do these activities occur?

Collecting customer requirements 1


Developing the work breakdown structure 2


Working to produce project deliverable 3


Customers evaluating the project outcomes 4


Capturing lessons learned 5

Place the project activities in order of occurrence from first (1) to last (5).

Executing




WGU C722
€13,57
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
PossibleA Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
977
Lid sinds
4 jaar
Aantal volgers
650
Documenten
12613
Laatst verkocht
14 uur geleden
POSSIBLEA QUALITY UPDATED EXAMS

Choose quality study materials for nursing schools to ensure success in your studies and future career. "Welcome to PossibleA - your perfect study assistant! Here you will find Quality sheets, study materials, exams, quizzes, tests, and notes to prepare for exams and study successfully. Our store offers a wide selection of materials on various subjects and difficulty levels, created by experienced teachers and checked for quality. Our quality sheets are an easy and quick way to remember key points and definitions. And our study materials, tests, and quizzes will help you absorb the material and prepare for exams. Our store also has notes and lecture summaries that will help you save time and make the learning process more efficient.

Lees meer Lees minder
3,9

140 beoordelingen

5
74
4
24
3
20
2
1
1
21

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen