Which of the following is true for the course's Technology & Business Impact Paper? - Answers
Students are required to submit a 1500-word minimum draft, followed by a 3500-word minimum
final submission after edits and revisions based on comments from the draft
Because we are in a Management Information Systems (MIS) course, the solutions proposed
for these business challenges will need to involve technology integrated into the organization's
business processes. - Answers True
In Lecture 1, we go over the 12 different components of the course, and the order we will
proceed in learning them. Put these components in the correct order. - Answers 1. Business
Challenge
2. Current Business Process
3. Current Business Process' Negative Impact
4. Business Requirements for Improvement
5. Solution Acceptance Criteria's
6. Business Process' Update due to the Potential Solution
7. Choosing the Right Solution for the Business and its Challenge(s)
8. Potential Solution's Positive Impact on the Business Process
9. Integration of the Potential Solution (Architecture)
10. Look & Feel of the Potential Solution (User Interface)
11. Implementation Plans & Scheduling of the Potential Solution
12. Implementation Risks & Risks Responses of the Potential Solution
According to slide 17 in Lecture 1, what is the purpose of "Integration of the Potential Solution
(Architecture)" component? - Answers The organization will more than likely already have IT
systems and tools in place, so it shows how the current systems will be affected by your
recommended solution.
In this course, what are we working to build in order to address the business challenge? -
Answers Project Proposal
Which of the following is true when emailing me (the course's instructor)? - Answers You need
to add "MIS 330-section#" at the beginning of your subject line
You need to use your GMU email
, Which of the following is true about the Experiential Learning course available to students once
they pass MIS 330? - Answers The course focuses on real-world hands-on projects with real
industry clients/participants; and students have to meet mulitiple prerequisite requirements to
be able to enroll
Which of the following is considered the triple constraint of project management? - Answers
Scope, Cost, & Time
On slide 84 of Lecture 2, there are 9 project management areas listed, however there are 10
according to the Project Management Institute. What is the remaining project management area
that is not listed on slide 84? - Answers Integration
Who created the "MIS 330 Writing Tips & Strategies" video? - Answers Brian Ngac's Graduate
Teaching Assistant
Which of the following activities occurs in the Transition stage within the Implementation phase
of the SDLC? - Answers Project team implements new solution while phasing out the old system
that was in place
Which of the following activities occurs in the Observation stage within the Implementation
phase of the SDLC? - Answers Project team monitors the solution's implementation for a period
of time in the live production environment to see if it is performing as planned and tested
There are 10 project management areas according to the Project Management Institute. Which
area deals with the different people, groups, and organizations that would be affected by the
project? - Answers Stakeholder Management
What is gold plating? - Answers When the project team does additional efforts beyond the
requirements stated in the scope/SOW. Approved by the project team's manager and/or
sponsor.
When the project team does additional efforts beyond the requirements stated in the
scope/SOW. Approved by the project team's manager and/or sponsor. - Answers Maintenance
& Operations Phase
Which of the following shows the phases of the Systems Development Life Cycle (SDLC) in the
correct order according to the course's slides? - Answers Planning, Analysis, Design,
Implementation, Maintenance & Operations
Waterfall and Agile are examples of project management _____. These are formalized
approaches to implementing a process or framework, and can be derived from various sources.
- Answers methodologies
What is scope creep? - Answers When additional client requirements are added to the project
scope and are not approved by both parties