Which one of the following is not an element of the Contract as we
discussed in class? - ANSWERS-Promise
Which of the following is not a condition where a contract will not be
enforced by courts? - ANSWERS-Seniority
Fill in the blank in the following statement: Some contracts must be in
writing under the ____________ as adopted by each state: -
ANSWERS-Statute of Frauds
RFI (Request for Information) is the document that is transmitted to the
General Contractor from the Designer to get clarifications with respect
to design drawings and specifications. - ANSWERS-False
The resident project representative should not supervise, direct, or
control the contractor's means and methods of performing work. -
ANSWERS-True
In Multiple Prime delivery system, the services of a professional
construction management firm (Agency CM) can be essential. -
ANSWERS-True
END OF
PAGE
1
, CON 367 MIDTERM LATEST
EXAM
A professional construction management firm (Agency CM) can
participate in the following phases of a project: - ANSWERS-
Conception, Program Planning, Design, Construction, and Closeout
The design-build process may face some legal barriers when tried to be
implemented in the public sector. - ANSWERS-True
On a multiple-prime project, the owner is responsible for coordinating
the various trade contractors with whom it has contracted. - ANSWERS-
True
The Resident Project Representative does not need to make any
measurement for the progress
payments in the lump-sum projects. - ANSWERS-False
Use of Building Information Modeling (BIM) in construction projects
may result in a reduction in
Requests for Information (RFIs) and change orders. - ANSWERS-True