CGM-C Pre Test Questions and Answers Already Passed Latest Update The purpose of Construction Quality Management is to: - Answers Achieve the quality established by properly developed requirements through the combined responsibility, but separate, efforts of contractor and Government personnel Construction Quality Management is the performance of tasks, which ensure that design and construction is performed: - Answers According to plans and specifications, on time, within a defined budget and a safe work environment. Partnering relationships are based upon: - Answers Building trust and dedication to common goals It is the responsibility of Quality Assurance Personnel to: - Answers Periodically verify that the contractors system of control is working effectively. An effective contractor quality control (CQC) program will: - Answers Be an incentive for work to be done correctly the first time resulting in earlier completion, reduced field overhead costs, and greater profits. The success or failure of all contractors is based upon: - Answers The ability to control costs, finance work, estimate jobs, schedule the work, and maintain effective quality control. Quality Assurance Personnel have the responsibility to: - Answers Require contractors to maintain the quality specified in the plans and specifications. Inspection is: - Answers The process by which ongoing and completed work is examined During the punch-out inspection of a project: - Answers Quality Assurance Personnel must assure that the contractor prepares a punch-list and makes corrections. If there is disagreement whether the contractor's work complies with the contract: - Answers The government makes the final determination Characteristics that describe a definable feature of work (DFOW) include: - Answers Cross-referenced listings to the contractors construction schedule that may have more than one definable feature under a section of the specifications. The _____________________ consists of daily checks of the work to assure continuing compliance with contract requirements. - Answers Follow-up phase The Quality Assurance Plan: - Answers Is a government management tool establishing staffing, training, pre-award activities, and surveillance activities. Testing is extremely important in Construction Quality Management and is performed by: - Answers Both the contractor and the government If the contractor does not provide an adequate superintendent, the contract allows the

Meer zien Lees minder
Instelling
CGM-C
Vak
CGM-C








Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
CGM-C
Vak
CGM-C

Documentinformatie

Geüpload op
9 oktober 2025
Aantal pagina's
3
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

CGM-C Pre Test Questions and Answers Already Passed Latest Update 2025-2026

The purpose of Construction Quality Management is to: - Answers Achieve the quality
established by properly developed requirements through the combined responsibility, but
separate, efforts of contractor and Government personnel

Construction Quality Management is the performance of tasks, which ensure that design and
construction is performed: - Answers According to plans and specifications, on time, within a
defined budget and a safe work environment.

Partnering relationships are based upon: - Answers Building trust and dedication to common
goals

It is the responsibility of Quality Assurance Personnel to: - Answers Periodically verify that the
contractors system of control is working effectively.

An effective contractor quality control (CQC) program will: - Answers Be an incentive for work to
be done correctly the first time resulting in earlier completion, reduced field overhead costs, and
greater profits.

The success or failure of all contractors is based upon: - Answers The ability to control costs,
finance work, estimate jobs, schedule the work, and maintain effective quality control.

Quality Assurance Personnel have the responsibility to: - Answers Require contractors to
maintain the quality specified in the plans and specifications.

Inspection is: - Answers The process by which ongoing and completed work is examined

During the punch-out inspection of a project: - Answers Quality Assurance Personnel must
assure that the contractor prepares a punch-list and makes corrections.

If there is disagreement whether the contractor's work complies with the contract: - Answers
The government makes the final determination

Characteristics that describe a definable feature of work (DFOW) include: - Answers Cross-
referenced listings to the contractors construction schedule that may have more than one
definable feature under a section of the specifications.

The _____________________ consists of daily checks of the work to assure continuing compliance
with contract requirements. - Answers Follow-up phase

The Quality Assurance Plan: - Answers Is a government management tool establishing staffing,
training, pre-award activities, and surveillance activities.

Testing is extremely important in Construction Quality Management and is performed by: -
Answers Both the contractor and the government

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
joshuawesonga22 Liberty University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
27
Lid sinds
7 maanden
Aantal volgers
1
Documenten
10000
Laatst verkocht
2 dagen geleden
Tutor Wes

Hi there! I'm Tutor Wes, a dedicated tutor with a passion for sharing knowledge and helping others succeed academically. All my notes are carefully organized, detailed, and easy to understand. Whether you're preparing for exams, catching up on lectures, or looking for clear summaries, you'll find useful study materials here. Let’s succeed together!

3,3

3 beoordelingen

5
1
4
0
3
1
2
1
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen