CORRECT Answers
1. a In what deliverable does a PM identify phases & deliverables, create WBS, estimate
tasks, create dependencies, and assign people to tasks?
point
a. Work Plan
b. Triple Constraint
c. Critical Path
2. c Which of the following diagrams can be used to document a business process?
point
a. Swim-lane diagram
b. Flow charts
c. All of the above
3. b What diagram includes a system, external entities, processes, boundaries, inputs,
and outputs?
point
a. Swim-lane diagram
b. Context diagram
4. b What are the four phases of SDLC methodology in order?
point
a. Analyze, Plan, Design, Implement
b. Plan, Analyze, Design, Implement
c. Plan ,Design, Analyze, Implement
5. b What differentiates RAD from Waterfall?
point
a. Prototyping
b. Iteration
6. a What differentiates Agile from Waterfall?
point
1/8
, ITA203c - Coursera 2 UPDATED ACTUAL Questions and
CORRECT Answers
a. Iteratively delivers features via sprints
b. Clearly defined phases with deliverables
7. e In what phase(s) of SDLC does an ideal Business Analyst contribute?
point
a. Plan
b. Analyze
c. Design
d. Implement
e. All of the above
8. a In what phase(s) is a System Request document introduced?
point
a. Plan
b. Analyze
c. Design
d. Implement
9. e What does a feasibility analysis focus on?
point
a. Time
b. Money
c. Quality
d. All of the above
e. None of the above
10. e In what phase of SDLC methodology does Organizational Readiness occur?
point
a. Plan
b. Analyze
c. Design
d. Implement
e. All of the above