backward pass correct answer To set construct the critical path using a ___________, you can start from the end date. Concurrent Activities correct answer ____________ are sets of activities can be done at the same time. Crashing correct answer _________ is obtaining the greatest amount of compression of the schedule/critical path for the least incremental cost or time. critical chain correct answer The ____________ builds on the critical path method by going a step further by adding time buffers to account for limited resources. Fast-tracking correct answer ____________ is the process of executing activities that were originally scheduled sequentially in parallel. Finish-to-Finish Relationships (FF) correct answer ______________ is a task relationship where the successor task cannot be completed until the first task is completed. The second task will begin after some initial progress on the first task has occurred. Both tasks will finish at the same time.

Meer zien Lees minder
Instelling
Project Managememt
Vak
Project Managememt








Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Project Managememt
Vak
Project Managememt

Documentinformatie

Geüpload op
2 juli 2025
Aantal pagina's
4
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

WGU C722 Unit 7 Module 25, 26:
Network Diagram/Critical Path Questions
with Accurate Answers
backward pass correct answer To set construct the critical path using a
___________, you can start from the end date.


Concurrent Activities correct answer ____________ are sets of
activities can be done at the same time.


Crashing correct answer _________ is obtaining the greatest amount of
compression of the schedule/critical path for the least incremental cost
or time.


critical chain correct answer The ____________ builds on the critical
path method by going a step further by adding time buffers to account
for limited resources.


Fast-tracking correct answer ____________ is the process of executing
activities that were originally scheduled sequentially in parallel.


Finish-to-Finish Relationships (FF) correct answer ______________ is a
task relationship where the successor task cannot be completed until
the first task is completed. The second task will begin after some initial
progress on the first task has occurred. Both tasks will finish at the
same time.

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
starwid Yale University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
13
Lid sinds
6 maanden
Aantal volgers
1
Documenten
8058
Laatst verkocht
4 dagen geleden

3,3

4 beoordelingen

5
1
4
0
3
2
2
1
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen