Describes what a critical path analysis is, what a manager needs to know to use the technique, features of a critical path, key points of a critical path, and the advantages and disadvantages of it.

Instelling
Vak








Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Study Level
Publisher
Subject
Course

Documentinformatie

Geüpload op
28 september 2020
Aantal pagina's
2
Geschreven in
2019/2020
Type
Samenvatting

Onderwerpen

Voorbeeld van de inhoud

Theme 3 Topic 9
Critical Path Analysis
Critical Path Analysis
Critical Path Analysis – using a network diagram to show
the tasks taken to complete a project in the minimum time
possible

 Shows the sequence of activities required for the
project and the order in which they can be
completed
 Its purpose is to plan projects in a way which
enables a project to be completed in the shortest
time possible

To Use the Technique a Manager Needs to Know:

 What different tasks are involved
 The length of time each task is expected to take
 The order the tasks must be completed in – some can’t be started until another has finished

Features of a Critical Path Analysis:

Feature Explanation
Nodes and Node  The circles represent a point in time at the start or end of an activity
Numbers  Nodes are split into three
 The left half of the node contains the number of the node – provides a unique
identity for each node
Earliest Start  The right half of the node is split in two
Time (EST)  The top segment shows the EST that an activity can commence
 Depends on the completion of the previous activity
 For the starting activity, the EST is always zero
Latest Finishing  The bottom segment shows the LFT
Time (LFT)  The latest time an activity can finish without delaying the overall project
Arrows  Represent production activities, they must go left to right and begin and end
with a node
 Below the line – a number which represents the length of time it takes to
complete that activity
 Above the line – a letter or description of the activity that the line represents
The Critical Path  Critical Path – the sequence of activities in a project that must be completed
within a designated time in order to prevent any delay in overall completion of
the project
 Is shown by the symbol // over the arrow
Total Float  Total Float – the amount of time that an activity can be delayed by without
delaying the entire project
 Total Float for an Activity = LFT – Duration of Activity – EST

Key Points of a Critical Path Analysis:

 Must start and end on a single node
 No lines should cross each other
 There is no limit on the number of activities that link to a single node
 When drawing an activity, do not add the end node until you have looked to see which activity follows
 It is helpful to draw networks with large circles and short lines – able to write figures in the nodes

Advantages of Critical Path Analysis Disadvantages of Critical Path Analysis
€4,10
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
emily1744 Greenhead College
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
42
Lid sinds
5 jaar
Aantal volgers
23
Documenten
168
Laatst verkocht
8 maanden geleden

4,3

15 beoordelingen

5
11
4
1
3
1
2
1
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen