and CORRECT Answers
Keys to a successful project - CORRECT ANSWER - 1. Get the team together as early as
possible
2. Open Communication
3. Early sub participation
4. Budge
5. Schedule
Fast Track - CORRECT ANSWER - Schedule method that starts activities at the earliest
possible time to push subsequent up in their execution
Planning - CORRECT ANSWER - The who, what, where, and how
Stakeholders in planning - CORRECT ANSWER - Owner, design team, builders,
agencies, providers (elec, etc)
Evolution of a schedule - CORRECT ANSWER - 1. Pre-con phase
2. Construction Phase
WBS Level 1 examples - CORRECT ANSWER - Pre-con, construction, turn over
WBS Level 2 examples - CORRECT ANSWER - Sitework, core & shell, interior buildout,
MEPF
Milestones - CORRECT ANSWER - Key dates that meet project goals and objectives