Utah Contractor Exam (Real) Questions and Answers 100% Pass Depreciation is taken on which of the company's assets? a. Loans b. Current assets c. Fixed assets d. None of the above - C ... Explanation: Depreciation is counted from fixed assets. A private employer who employs __ or more people as of July 1, 2010, may not hire a new employee unless the employer is registered with and uses a status verification system such as E -Verify to verify the federal legal working status of any new employee. a. 5 b. 10 c. 15 d. 1 - C ... Explanation: A private employer who employs 15 or more people as of July 1, 2010, may not hire a new employee unless the employer is registered with and uses a status verification system such as E -Verify to verify the federal legal working status of any new employee. If a contractor decides to increase the contract price, the contractor: a. Should get a loan from the bank 2COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED b. May request assistance from the subcontractor c. And the owner must agree to a written and signed change order d. Should request the building inspector to revise the specifications - C ... Explanation: A written and signed change order can allow the contractor to change a contract price. If a subcontractor signs an unconditional waiver and release, this would imply that a: a. Subcontractor cannot ask anything more of the owner b. Owner cannot ask anything more of the subcontractor c. Subcontractor cannot get anything from the prime d. Subcontractor cannot ask anything more of the prime - A ... Explanation: Once the subcontractor signs an unconditional waiver and release, the subcontractor cannot ask anything more of the owner. Any applicant who has been denied a license to practice on the basis of credentials, or failure to pass a required examination, may submit a request for agency review to the executive director ____ following notification of the denial of a license or refusal to renew or reinstate a license. a. Within 10 days b. Within 20 days c. Within 30 days d. Within 60 days - 5. C ... Explanation: Any applicant who has been denied a license to practice on the basis of credentials, character, or failure to pass a required examination, or who has been refused renewal or reinstatement of a license to practice on the basis that the applicant does not meet qualifications for continued licensure in any occupation or profession under the jurisdiction of the division may submit a request for agency review to the executive director within 30 days 3COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED following notification of the denial of a license or refusal to renew or reinstate a license. What should a contractor do if after starting a home improvement project the contractor discovers that the details and specifications do NOT correctly show the existing construction? a. Stop and work on a correction b. Stop the job and inform the owner or his agent c. Continue the work if variations are only minor d. Stop the job and inform the Building Department - B ... Explanation: Any details and specifications are not represented correctly then it is the contractor's duty to inform the owner or his agent. Keeping good accounting records is important for: a. Maintaining financial statements b. Obtaining financing c. Effective management d. All of the above - D ... Explanation: Effective management, maintaining financial statements and obtaining proper financing are all the result of keeping good accounting records. 8. The promise by a party called the guarantor to make good the mistake, debt, or default of another party found in the construction contract law is called: a. Surety b. Guarantee c. Warrantee d. Agreement - B ... Explanation: Guarantee. 9. The plans and specifications of a home improvement project usually describe: 4COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED a. Layout sizes b. Liquidated damages c. Consent to arbitrate d. Neighborhood regulations - 9. A ... Explanation: Layout sizes are usually described in plans and specifications of home improvement projects. The number of years that an employer must keep records of FUTA and other federal taxes is: a. 2 years b. 4 years c. 6 years d. 10 years - B ... Explanatio

Meer zien Lees minder
Instelling
Utah
Vak
Utah











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Utah
Vak
Utah

Documentinformatie

Geüpload op
20 april 2025
Aantal pagina's
168
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

Utah Contractor Exam (Real)
Questions and Answers 100% Pass


Depreciation is taken on which of the company's assets?

a. Loans

b. Current assets

c. Fixed assets

d. None of the above - ✔✔C ... Explanation: Depreciation is counted from fixed
assets.

A private employer who employs __ or more people as of July 1, 2010, may not hire
a new employee unless the employer is registered with and uses a status verification
system such as E -Verify to verify the federal legal working status of any new
employee.

a. 5

b. 10

c. 15

d. 1 - ✔✔C ... Explanation: A private employer who employs 15 or more people as of
July 1, 2010, may not hire a new employee unless the employer is registered with
and uses a status verification system such as E -Verify to verify the federal legal
working status of any new employee.

If a contractor decides to increase the contract price, the contractor:

a. Should get a loan from the bank


COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 1

,b. May request assistance from the subcontractor

c. And the owner must agree to a written and signed change order

d. Should request the building inspector to revise the specifications - ✔✔C ...
Explanation: A written and signed change order can allow the contractor to change a
contract price.

If a subcontractor signs an unconditional waiver and release, this would imply that
a:

a. Subcontractor cannot ask anything more of the owner

b. Owner cannot ask anything more of the subcontractor

c. Subcontractor cannot get anything from the prime

d. Subcontractor cannot ask anything more of the prime - ✔✔A ... Explanation: Once
the subcontractor signs an unconditional waiver and release, the subcontractor
cannot ask anything more of the owner.

Any applicant who has been denied a license to practice on the basis of credentials,
or failure to pass a required examination, may submit a request for agency review to
the executive director ____ following notification of the denial of a license or refusal
to renew or reinstate a license.

a. Within 10 days

b. Within 20 days

c. Within 30 days

d. Within 60 days - ✔✔5. C ... Explanation: Any applicant who has been denied a
license to practice on the basis of credentials, character, or failure to pass a required
examination, or who has been refused renewal or reinstatement of a license to
practice on the basis that the applicant does not meet qualifications for continued
licensure in any occupation or profession under the jurisdiction of the division may
submit a request for agency review to the executive director within 30 days




COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 2

,following notification of the denial of a license or refusal to renew or reinstate a
license.

What should a contractor do if after starting a home improvement project the
contractor discovers that the details and specifications do NOT correctly show the
existing construction?

a. Stop and work on a correction

b. Stop the job and inform the owner or his agent

c. Continue the work if variations are only minor

d. Stop the job and inform the Building Department - ✔✔B ... Explanation: Any
details and specifications are not represented correctly then it is the contractor's duty
to inform the owner or his agent.

Keeping good accounting records is important for:

a. Maintaining financial statements

b. Obtaining financing

c. Effective management

d. All of the above - ✔✔D ... Explanation: Effective management, maintaining
financial statements and obtaining proper financing are all the result of keeping
good accounting records.

8. The promise by a party called the guarantor to make good the mistake, debt, or
default of another party found in the construction contract law is called:

a. Surety

b. Guarantee

c. Warrantee

d. Agreement - ✔✔B ... Explanation: Guarantee.

9. The plans and specifications of a home improvement project usually describe:



COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 3

, a. Layout sizes

b. Liquidated damages

c. Consent to arbitrate

d. Neighborhood regulations - ✔✔9. A ... Explanation: Layout sizes are usually
described in plans and specifications of home improvement projects.

The number of years that an employer must keep records of FUTA and other federal
taxes is:

a. 2 years

b. 4 years

c. 6 years

d. 10 years - ✔✔B ... Explanation: 4 years is the amount of time an employer must
keep records of FUTA and other federal taxes.




Page: 5-2

What is the term for a detailed compilation of the quantity of each elemental work
item?

a. Summary sheet

b. Bid invitation

c. Takeoff

d. Specification - ✔✔C ... Explanation: Estimators use construction blueprints, either
manually or electronically, and start "taking off" quantities of items they will need
from those blueprints in order to prepare part of the estimate.




Page: 6-3




COPYRIGHT © 2025 BY SOPHIA BENNETT, ALL RIGHTS RESERVED 4
€12,18
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
SophiaBennett Howard Community College
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
132
Lid sinds
1 jaar
Aantal volgers
5
Documenten
9104
Laatst verkocht
1 dag geleden
EXAM GAME-CHANGER

Exam Questions and Answers Section : Study Like a Pro, Study Smart, Study with Sophia.

3,7

26 beoordelingen

5
10
4
5
3
7
2
1
1
3

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen