ACI CONCRETE FIELD TESTING TECHNICIAN- GRADE I

Instelling
ACI
Vak
ACI









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
ACI
Vak
ACI

Documentinformatie

Geüpload op
22 februari 2025
Aantal pagina's
11
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

ACI CONCRETE FIELD TESTING TECHNICIAN- GRADE
I

The sensor of the temperature measuring device shall be submerged a minimum of
_____ in. [_____mm] into the freshly mixed concrete. - Answers - 3 in. [75 mm]

The temperature measuring device shall have a capacity of measuring temperature of
freshly mixed concrete to +- _____ degrees F [+- _____ C] throughout a range of
_____. - Answers - 1 degree F [0.5 C], 30 degrees F to 120 F [0 C to 50 C]

The temperature measuring device shall be calibrated _____, or whenever there is a
question of _____. - Answers - Annually, accuracy

The temperature of concrete may be measured in a wheelbarrow. True or False? -
Answers - True

The temperature of concrete may be measured in a wall form. True of False - Answers -
True

A composite sample of concrete is required even if the only purpose for obtaining the
sample is to determine temperature. True of False? - Answers - False

What must be done to the sample container prior to sampling the concrete? - Answers -
Dampen (with water)

What must be done to the concrete surrounding the temperature measuring device after
the device is submerged in the fresh concrete. - Answers - Gently press the concrete
around the temperature measuring device at the surface of the concrete

How long must the temperature measuring device remain in the freshly mixed concrete?
- Answers - At least 2 minutes but not more than 5 minutes

Sampling by this method is required when tests are to be made to determine _____ with
specification requirements. - Answers - Compliance

This method covers sampling from four types of mixtures which are _____, _____,
_____, and _____. - Answers - Stationary mixers, paving mixers, revolving drum mixers,
and open top mixers

The maximum allowable time between obtaining the first and final portions of a
composite sample is _____ minutes. - Answers - 15

Portions of a composite sample shall be thoroughly remixed bfore beginning tests on
the sample. True of False? - Answers - True

, The maximum elapsed time allowed between obtaining the final portion of the
composite sample and beginning the tests for slump, temperature, and air content is
_____ minutes. - Answers - 5

The molding of strength test specimens shall begin within _____ minutes after
fabricating the composite sample. - Answers - 15

The concrete sample must be protected from contamination and _____. - Answers -
Rapid evaporation

The minimum size sample for making strength test specimens is _____. - Answers - 28
L (1ft^3)

When sampling from a stationary mixer, the batch must be sampled at _____ or more
regularly spaced intervals during discharge of the middle portion of the batch - Answers
-2

The composite sample for a paving mixer must represent a minimum of _____ different
portions of the batch of concrete taken from the pile after discharge. - Answers - 5

After the temperature of the concrete is read, what is required? - Answers - Reporting of
temperature

The temperature of concrete is reported to the nearest _____ degrees F [_____ C] -
Answers - 1 degree F [0.5 C]

According to ASTM C1064, what is one reason to take the temperature of concrete? -
Answers - Verify conformance to a specified requirement for temperature of concrete

A maximum temperature of freshly mixed concrete is specified in ASTM C1064. True of
False? - Answers - False

The sample of concrete used for temperature determination must be rodded 25 times.
True or False? - Answers - False

When sampling from a revolving drum truck mixer, concrete must be sampled at a
minimum of _____ regularly spaced intervals during discharge of the middle portion of
this batch. - Answers - 2

Concrete samples from a truck mixer must be obtained before any water or admixtures
are added to the mixer at the job site. True or False? - Answers - False

The composite samples from a truck mixer must be obtained from the _____ portion of
the batch. - Answers - Middle

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
GEEKA YALA UNIVERSITY
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1998
Lid sinds
3 jaar
Aantal volgers
1444
Documenten
46903
Laatst verkocht
4 dagen geleden

3,8

342 beoordelingen

5
170
4
61
3
44
2
16
1
51

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen