Develop Schedule Process - The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model. Develop Schedule Process - The following tools and techniques are part of this process: •Schedule network analysis •CPM •CCM •Resource optimization techniques •Modeling techniques •Lead and lags •Schedule compression •Scheduling tool Planned Dates - Key benefit of the Develop Schedule process is that it generates ____ ____ for completing project activities.

Meer zien Lees minder
Instelling
MBA 742
Vak
MBA 742









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
MBA 742
Vak
MBA 742

Documentinformatie

Geüpload op
6 februari 2025
Aantal pagina's
13
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

MBA 742 - MODULE 3 QUESTIONS AND
ANSWERS
Develop Schedule Process - ✔✔The process of analyzing activity sequences,
durations, resource requirements, and schedule constraints to create the project
schedule model.

Develop Schedule Process - ✔✔The following tools and techniques are part of this
process:
•Schedule network analysis
•CPM
•CCM
•Resource optimization techniques
•Modeling techniques
•Lead and lags
•Schedule compression
•Scheduling tool

Planned Dates - ✔✔Key benefit of the Develop Schedule process is that it generates
____ ____ for completing project activities.

Schedule Network Analysis - ✔✔The techniques of identifying early and late start dates,
as well as early and late finish dates, for the uncompleted portions of project schedule
activities.

Critical Path - ✔✔the sequence of activities the represents the longest path through the
project, which determines the shortest possible duration

CPM (Critical Path Method) - ✔✔A method used to estimate the minimum project
duration and determine the amount of scheduling flexibility on the logical network paths
within the schedule module.

CCM (Critical Chain Method) - ✔✔A schedule method that allows the project team to
place buffers on any project schedule path to account for limited resources and project
uncertainties.

tasks & resources - ✔✔CPM is focused on ____ and CCM focuses on the ____.

task - ✔✔CPM is a ____ based model

Resource - ✔✔CCM is a ____ based model

, Forward & Backward - ✔✔In order to determine the project's critical path, it is necessary
to perform both a ____ and ____ pass through the network.

Forward - ✔✔In CPM, a ____ pass will ID the early-start and early finish times.

Backward - ✔✔In CPM, a ____ pass will ID the late-start and late-finish times.

Forward Pass - ✔✔A critical path method technique for calculating the early start and
early finish dates by working forward through the schedule model from the project start
date or a given point in time.

Backward Pass - ✔✔A critical path method technique for calculating the late start and
late finish dates by working backward through the schedule model from the project end
date.

Early Start (ES) - ✔✔In CPM, the earliest date the activity can start.

Early Finish (EF) - ✔✔In CPM, the earliest date the activity can finish

Late Finish (LF) - ✔✔In CPM, the latest date that the activity can finish without causing
a delay to the project completion date.

Late Start (LS) - ✔✔In CPM, the latest date that the activity can start without causing a
delay to the project completion date.

Free Float - ✔✔The amount of time that a schedule activity can be delayed without
delaying the early start date of any successor or violating a schedule constraint.

Total Float - ✔✔The amount of time that a schedule activity can be delayed or extended
from its early start date without delaying the project finish date or violating a schedule
constraint.

Critical - ✔✔A useful way of describing the critical path is as a continuous string(s) of
____ activities in the schedule between the start and finish of the project.

Duration - ✔✔The sum of the activity durations in the critical path is equal to the
project's ____; therefore a delay to any critical activity will result in a delay to the project
completion date.

Critical Activity - ✔✔An activity that is on the project's critical path. Does not possess
any float, total float = 0.
€10,51
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten

Maak kennis met de verkoper
Seller avatar
ammon

Maak kennis met de verkoper

Seller avatar
ammon Glendale Community College
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
0
Lid sinds
1 jaar
Aantal volgers
0
Documenten
42
Laatst verkocht
-

0,0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen