ARE 5.0 - PJM - Project Execution UPDATED ACTUAL Exam Questions and CORRECT Answers Best approach to meeting client expectations for construction budgets - CORRECT ANSWER - carefully monitor the relationship between scope, quality, and cost as a design is being developed When a conflict, sit with the client and review and adjust one or more of the project parameters of quality, time, and cost before proceeding to the next step in the design process To stay on top of issue, budget compliance & adjustment problems added to mtg agendas and discussed regularly w client and proj team

Meer zien Lees minder
Instelling
ARE 5.0
Vak
ARE 5.0










Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
ARE 5.0
Vak
ARE 5.0

Documentinformatie

Geüpload op
30 januari 2025
Aantal pagina's
25
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

ARE 5.0 - PJM - Project Execution
UPDATED ACTUAL Exam Questions and
CORRECT Answers
Best approach to meeting client expectations for construction budgets - CORRECT
ANSWER - carefully monitor the relationship between scope, quality, and cost as a design is
being developed
When a conflict, sit with the client and review and adjust one or more of the project parameters
of quality, time, and cost before proceeding to the next step in the design process
To stay on top of issue, budget compliance & adjustment problems added to mtg agendas and
discussed regularly w client and proj team


Challenges of managing consultants that PM must allot time and resources for - CORRECT
ANSWER - Consultant coordination
1. Reaching finish line at the same time and avoiding disruption when docs are issued
2. Making sure all parties using same versions of plan backgrounds
3. Uncovering and coordinating conflicts bet work of diff disciplines


Quality management responsibilities of PM - CORRECT ANSWER - PM to manage and
control project's quality level
Must be a daily concern
Redlines
Helping w specs and dwgs
Most of all, know the status of work at all times
Oversee and direct quality management controls as they are performed


PM responsibilities for Document Reviews - CORRECT ANSWER - Doc reviews as
opportunity to find uncover mistakes before they create problems during construction
Schedule time/resources for internal reviews of CDs before bidding
Reviewer could be PM, leader from another proj, or spec writer

,External reviews also helpful and should be welcomed (engineers, consultants, owners,
constractors, agencies that give permits.)


Managing expectations of client tips - CORRECT ANSWER - Help client set expectations
Have frank discussion of potentially tough issues
Use technique of creative conflict (process of engaging in debate to be able to recall issues later
on to gain concensus. Do this when change is requested, not after. Even is architect overruled,
owner will remember concerns were expressed)
Dont use jargon that is "undefined" or absolute by client or might be setting unreslistic
expectations ("our docs are %100 complete)


Suitable alternative for
"We look forward to designing a first-class new school for you."


"100% Complete Construction Documents"


"50% Schematic Design Set"


The masonry walls have been completed." - CORRECT ANSWER - We look forward to
designing your new school project.


Issued for Construction"


"Interim Schematic Review Set"


"The masonry walls appear complete."


Explaining consequences as a responsibility of PM - CORRECT ANSWER - For example, if
a client decides to eliminate waterproofing on the basement walls, it is not enough for the
architect to simply disagree with the decision. The project manager should go a step further and
explain that the decision could result in water leaking into the basement, causing damaged

, finishes and expensive repair costs. While such consequences may seem obvious to the
experienced project manager, they might not be so obvious to the owner.


Client wanting to save money on building system. Architect to explain increase of cost of
building maintenance


Monitoring tips for PM - CORRECT ANSWER - Most projects require a montly evaluation



Monitoring terms - CORRECT ANSWER - Net service revenue
Planned cost
Job-to-date
Estimate-to-complete
Estimate-at-completion
Planned estimate at completion
Percent complete
Multipliers (break even, overhead, effective multiplier, target, planned multiplier, estimate at
completion multiplier)
Billed/invoiced amounts
Earned revenue amounts
Billed-not-earned
Earned-not-billed


Net service revenue - CORRECT ANSWER - Net fee determined by subtracting consultant
fees from the gross fee for the project


Planned cost: - CORRECT ANSWER - Labor hours and dollar amounts planned at project
initiation


Job-to-date (JTD): - CORRECT ANSWER - Labor hours and dollar amounts spent as of
current date
€10,17
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
MGRADES Stanford University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1053
Lid sinds
1 jaar
Aantal volgers
100
Documenten
68976
Laatst verkocht
4 uur geleden
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3,8

166 beoordelingen

5
72
4
30
3
42
2
8
1
14

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen