You are inspecting a construction site and notice that the soil appears to be a fine-grained, cohesive material with good bearing capacity. What type of soil is this likely to be? a. Clay b. Sand c. Gravel d. Loam - Correct Ans-a. Clay You are inspecting the clearing and grubbing of a construction site and notice that a large tree has been removed within the limits of disturbance. What should you do? a. Notify the project manager and request that a replacement tree be planted b. Document the removal in the construction logs and move on c. Issue a stop work order until a replacement tree can be planted d. Request that the tree be replaced, but do not issue a stop work order - Correct Ans-d. Request that the tree be replaced, but do not issue a stop work order You are inspecting the placement of an embankment and notice that the compaction is below the required specification. What should you do? a. Accept the work and move on b. Notify the project manager and request that the compaction be corrected c. Issue a stop work order until the compaction can be corrected d. Document the issue in the construction logs and move on - Correct Ans-b. Notify the project manager and request that the compaction be corrected You are asked to calculate the excavation and embankment quantities for a construction project. What information do you need to complete this task? a. The dimensions of the excavation and embankment areas b. The weight of the soil and other materials c. The density of the soil and other materials d. All of the above - Correct Ans-d. All of the above You are inspecting a construction site and notice that temporary erosion and sediment controls are not properly installed. What should you do? a. Accept the work and move on b. Notify the project manager and request that the controls be corrected c. Issue a stop work order until the controls can be corrected d. Document the issue in the construction logs and move on - Correct Ans-c. Issue a stop work order until the controls can be corrected You are inspecting the placement of a subgrade and notice that the undercutting is not to the specified depth. What should you do? a. Accept the work and move on b. Notify the project manager and request that the undercutting be corrected c. Issue a stop work order until the undercutting can be corrected d. Document the issue in the construction logs and move on - Correct Ans-b. Notify the project manager and request that the undercutting be corrected You are asked to determine the acceptability of the results of a soil compaction test. What criteria should you use to make this determination? a. The compaction meets or exceeds the specified density b. The compaction meets or exceeds the specified moisture content c. The compaction meets or exceeds both the specified density and moisture content d. The compaction meets or exceeds the specified density or moisture content - Correct Ans-c. The compaction meets or exceeds both the specified density and moisture content You are inspecting the placement of an aggregate subbase and notice that the finish tolerances are not being met. What should you do? a. Accept the work and move on b. Notify the project manager and request that the finish tolerances be corrected c. Issue a stop work order until the finish tolerances can be corrected d. Document the issue in the construction logs and move on - Correct Ans-b. Notify the project manager and request that the finish tolerances be corrected You are asked to identify the limits of disturbance on a construction site. What are the limits of disturbance? a. The area where trees, shrubs, and other vegetation will be removed or damaged during construction b. The area where the construction activities will take place c. The area where the construction activities will have an impact on the environment d. All of the above - Correct Ans-d. All of the above You are inspecting a construction site and notice that materials testing and certification are not being properly carried out. What should you do? a. Accept the work and move on b. Notify the project manager and request that the testing and certification be corrected c. Issue a stop work order until the testing and certification can be corrected d. Document the issue in the construction logs and move on - Correct Ans-b. Notify the project manager and request that the testing and certification be corrected You are inspecting a construction site and notice that the soil appears to be a well-graded mixture of fine and coarse particles. What type of soil is this likely to be? a. Clay b. Sand c. Gravel d. Loam - Correct Ans-d. Loam

Meer zien Lees minder
Instelling
NICET .
Vak
NICET .











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
NICET .
Vak
NICET .

Documentinformatie

Geüpload op
9 januari 2025
Aantal pagina's
36
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

NICET



NICET Level 2 Full Exam Study
Questions and Answers 2025
You are inspecting a construction site and notice that the soil appears to be a fine-
grained, cohesive material with good bearing capacity. What type of soil is this likely to
be?
a. Clay
b. Sand
c. Gravel
d. Loam - Correct Ans-a. Clay

You are inspecting the clearing and grubbing of a construction site and notice that a
large tree has been removed within the limits of disturbance. What should you do?
a. Notify the project manager and request that a replacement tree be planted
b. Document the removal in the construction logs and move on
c. Issue a stop work order until a replacement tree can be planted
d. Request that the tree be replaced, but do not issue a stop work order - Correct Ans-d.
Request that the tree be replaced, but do not issue a stop work order

You are inspecting the placement of an embankment and notice that the compaction is
below the required specification. What should you do?
a. Accept the work and move on
b. Notify the project manager and request that the compaction be corrected
c. Issue a stop work order until the compaction can be corrected
d. Document the issue in the construction logs and move on - Correct Ans-b. Notify the
project manager and request that the compaction be corrected

You are asked to calculate the excavation and embankment quantities for a
construction project. What information do you need to complete this task?
a. The dimensions of the excavation and embankment areas
b. The weight of the soil and other materials
c. The density of the soil and other materials
d. All of the above - Correct Ans-d. All of the above

You are inspecting a construction site and notice that temporary erosion and sediment
controls are not properly installed. What should you do?
a. Accept the work and move on
b. Notify the project manager and request that the controls be corrected
c. Issue a stop work order until the controls can be corrected
d. Document the issue in the construction logs and move on - Correct Ans-c. Issue a
stop work order until the controls can be corrected

You are inspecting the placement of a subgrade and notice that the undercutting is not
to the specified depth. What should you do?



NICET

, NICET


a. Accept the work and move on
b. Notify the project manager and request that the undercutting be corrected
c. Issue a stop work order until the undercutting can be corrected
d. Document the issue in the construction logs and move on - Correct Ans-b. Notify the
project manager and request that the undercutting be corrected

You are asked to determine the acceptability of the results of a soil compaction test.
What criteria should you use to make this determination?
a. The compaction meets or exceeds the specified density
b. The compaction meets or exceeds the specified moisture content
c. The compaction meets or exceeds both the specified density and moisture content
d. The compaction meets or exceeds the specified density or moisture content - Correct
Ans-c. The compaction meets or exceeds both the specified density and moisture
content

You are inspecting the placement of an aggregate subbase and notice that the finish
tolerances are not being met. What should you do?
a. Accept the work and move on
b. Notify the project manager and request that the finish tolerances be corrected
c. Issue a stop work order until the finish tolerances can be corrected
d. Document the issue in the construction logs and move on - Correct Ans-b. Notify the
project manager and request that the finish tolerances be corrected

You are asked to identify the limits of disturbance on a construction site. What are the
limits of disturbance?
a. The area where trees, shrubs, and other vegetation will be removed or damaged
during construction
b. The area where the construction activities will take place
c. The area where the construction activities will have an impact on the environment
d. All of the above - Correct Ans-d. All of the above

You are inspecting a construction site and notice that materials testing and certification
are not being properly carried out. What should you do?
a. Accept the work and move on
b. Notify the project manager and request that the testing and certification be corrected
c. Issue a stop work order until the testing and certification can be corrected
d. Document the issue in the construction logs and move on - Correct Ans-b. Notify the
project manager and request that the testing and certification be corrected

You are inspecting a construction site and notice that the soil appears to be a well-
graded mixture of fine and coarse particles. What type of soil is this likely to be?
a. Clay
b. Sand
c. Gravel
d. Loam - Correct Ans-d. Loam




NICET

, NICET


You are asked to identify the rights-of-way on a construction site. What are the rights-of-
way?
a. The areas where the construction activities will take place
b. The areas where the construction will have an impact on the environment
c. The areas where utilities, such as pipes and cables, are located
d. All of the above - Correct Ans-c. The areas where utilities, such as pipes and cables,
are located

You are asked to differentiate between an easement and a right-of-way. How are they
different?
a. An easement is an area where the construction activities will take place, while a right-
of-way is an area where utilities, such as pipes and cables, are located
b. An easement is a right to use another person's land for a specific purpose, while a
right-of-way is a legal right to pass over another person's land
c. An easement is a legal right to pass over another person's land, while a right-of-way
is a right to use another person's land for a specific purpose
d. There is no difference between an easement and a right-of-way - Correct Ans-b. An
easement is a right to use another person's land for a specific purpose, while a right-of-
way is a legal right to pass over another person's land

You are inspecting the placement of a subgrade and notice that the grading is not to the
specified slope. What should you do?
a. Accept the work and move on
b. Notify the project manager and request that the grading be corrected
c. Issue a stop work order until the grading can be corrected
d. Document the issue in the construction logs and move on - Correct Ans-b. Notify the
project manager and request that the grading be corrected

You are asked to calculate the excavation and embankment quantities for a
construction project. What formula should you use to complete this task?
a. Length x Width x Depth
b. Length + Width + Depth
c. Length x Width / Depth
d. Length / Width x Depth - Correct Ans-a. Length x Width x Depth

You are asked to identify the properties of clay soil. Which of the following is NOT a
property of clay soil?
a. It has a high bearing capacity
b. It is highly porous
c. It has a high water retention capacity
d. It is easy to compact - Correct Ans-b. It is highly porous

You are inspecting the placement of an embankment and notice that the compaction is
above the required specification. What should you do?
a. Accept the work and move on




NICET

, NICET


b. Notify the project manager and request that the compaction be corrected c. Issue a
stop work order until the compaction can be corrected
d. Document the issue in the construction logs and move on - Correct Ans-a. Accept the
work and move on

You are inspecting a construction site and notice that temporary erosion and sediment
controls are not properly installed. What are the potential consequences of this issue?
a. Delays in the construction schedule
b. Increased construction costs
c. Environmental damage
d. All of the above - Correct Ans-d. All of the above

You are asked to identify the properties of sand. Which of the following is NOT a
property of sand?
a. It has a low bearing capacity
b. It is highly porous
c. It has a low water retention capacity
d. It is difficult to compact - Correct Ans-d. It is difficult to compact

ou are inspecting the placement of a subgrade and notice that the finish tolerances are
not being met. What are the potential consequences of this issue?
a. Delays in the construction schedule
b. Increased construction costs
c. Poor road performance
d. All of the above - Correct Ans-d. All of the above

You are asked to identify the properties of gravel. Which of the following is NOT a
property of gravel?
a. It has a high bearing capacity
b. It is highly porous
c. It has a high water retention capacity
d. It is easy to compact - Correct Ans-c. It has a high water retention capacity

You are inspecting the placement of an embankment and notice that the finish
tolerances are not being met. What should you do?
a. Accept the work and move on
b. Notify the project manager and request that the finish tolerances be corrected
c. Issue a stop work order until the finish tolerances can be corrected
d. Document the issue in the construction logs and move on - Correct Ans-b. Notify the
project manager and request that the finish tolerances be corrected

You are inspecting the placement of an aggregate subbase and notice that the
compaction is below the required specification. What should you do?
a. Accept the work and move on
b. Notify the project manager and request that the compaction be corrected
c. Issue a stop work order until the compaction can be corrected



NICET

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Bestzone Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
181
Lid sinds
4 jaar
Aantal volgers
111
Documenten
5004
Laatst verkocht
1 maand geleden
STUDY EXAMS AND STUDY GUIDES SUMMARIES ESSAY ALL VERIFIED

WELCOME!!!

3,9

27 beoordelingen

5
13
4
4
3
6
2
2
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen