Exam Bank for OMIS 352- Questions with Verified Solutions Latest Version _____ involves identifying and controlling the functional and physical design characteristics of products and their support documentation, and ensures that the descriptions of the project's products are correct and complete. a.Configuration management b.Project management information systems c.Project time management d.NPV analysis - Answers a. Configuration management The outputs of the _____ process include change request status updates, project management plan updates, and project document updates. ating ting ing oring and controlling - Answers d. monitoring and controlling The first step in the planning process is _____. perform a business area analysis tie the information technology strategic plan to the organization's overall strategic plan choose which projects to do and assigning resources to work on them start defining potential IT projects in terms of their scope, benefits, and constraints - Answers to tie the information technology strategic plan to the organization's overall strategic plan The _____ section of the project plan should describe the major project functions and activities and identify those individuals who are in charge of them. izational charts ement objectives ct responsibilities organizational or process-related information - Answers c. project responsibilities A _____ is a document that recognizes the existence of a project and provides direction on the project's objectives and management. ct charter tive holder register register - Answers ct charter An organization's information technology project selection process should guide the strategic plan. True False - Answers False Payback period is the amount of time it will take to recoup, in the form of net cash inflows, the total dollars invested in a project. True False - Answers True Interface management involves identifying and managing the points of interaction between various elements of a project. True False - Answers False The number of interfaces in a single project is limited, and does not depend on the number of people involved in the project. True False - Answers False Projects that arise as a result of problems and directives must be resolved quickly to avoid hurting an organization's business. True False - Answers True Which of the following is true of return on investment or ROI? a.It is always a percentage. b.It is always a positive number. c.The lower it is, the better. d.It is the result of adding the project costs to the profits. - Answers a.It is always a percentage. In the _____ stage of selecting information technology projects, organizations select information technology projects. mation technology strategy planning ct planning ess area analysis rce allocation - Answers rce allocation Which of the following is a proactive process undertaken to reduce the probability of negative consequences associated with project risks? a.Defect repairs b.Preventive actions c.Performance reports d.Corrective actions - Answers b. Preventive actions The _____ is the minimum acceptable rate of return on an investment. unt rate nal rate of return alization rate red rate of return - Answers red rate of return A _____ is a document used to coordinate all project planning documents and help guide a project's execution and control. ct management plan statement ess case ment of work - Answers ct management plan Payback period is the amount of time it will take to recoup, in the form of net cash inflows, the total dollars invested in a project. True False - Answers True Project integration management must occur just within the context of a particular project. True False - Answers False The number of interfaces in a single project is limited, and does not depend on the number of people involved in the project. True False - Answers False The organization should complete low-priority projects before high-priority ones, if the low-priority ones take less time. True False - Answers False Interface management involves identifying and managing the points of interaction between various elements of a project. True False - Answers False Which of the following is a proactive process undertaken to reduce the probability of negative consequences associated with project risks ? - Answers Preventive actions _ are new requirements imposed by management, government, or some external influence. - Answers Directives _involves working with stakeholders to create the document that formally authorizes a project. - Answers Developing the project charter Benefits minus costs is known as the - Answers Cash flow In the _ stage of selecting information technology projects, organizations select information technology projects. - Answers resource allocation It is necessary that IT project managers have prior technical experience in creating and managing IT products. - Answers False

Meer zien Lees minder
Instelling
OMIS 352
Vak
OMIS 352









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
OMIS 352
Vak
OMIS 352

Documentinformatie

Geüpload op
25 december 2024
Aantal pagina's
7
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

Exam Bank for OMIS 352- Questions with Verified Solutions Latest Version 2024-2025



_____ involves identifying and controlling the functional and physical design characteristics of products
and their support documentation, and ensures that the descriptions of the project's products are correct
and complete.

a.Configuration management

b.Project management information systems

c.Project time management

d.NPV analysis - Answers a. Configuration management

The outputs of the _____ process include change request status updates, project management plan
updates, and project document updates.

a.initiating

b.executing

c.planning

d.monitoring and controlling - Answers d. monitoring and controlling

The first step in the planning process is _____.

a.to perform a business area analysis

b.to tie the information technology strategic plan to the organization's overall strategic plan

c.to choose which projects to do and assigning resources to work on them

d.to start defining potential IT projects in terms of their scope, benefits, and constraints - Answers to tie
the information technology strategic plan to the organization's overall strategic plan

The _____ section of the project plan should describe the major project functions and activities and
identify those individuals who are in charge of them.

a.organizational charts

b.management objectives

c.project responsibilities

d.other organizational or process-related information - Answers c. project responsibilities

, A _____ is a document that recognizes the existence of a project and provides direction on the project's
objectives and management.

a.project charter

b.directive

c.stakeholder register

d.risk register - Answers a.project charter

An organization's information technology project selection process should guide the strategic plan.

True

False - Answers False

Payback period is the amount of time it will take to recoup, in the form of net cash inflows, the total
dollars invested in a project.

True

False - Answers True

Interface management involves identifying and managing the points of interaction between various
elements of a project.

True

False - Answers False

The number of interfaces in a single project is limited, and does not depend on the number of people
involved in the project.

True

False - Answers False

Projects that arise as a result of problems and directives must be resolved quickly to avoid hurting an
organization's business.

True

False - Answers True

Which of the following is true of return on investment or ROI?

a.It is always a percentage.

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TutorJosh Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
355
Lid sinds
1 jaar
Aantal volgers
16
Documenten
29264
Laatst verkocht
5 uur geleden
Tutor Joshua

Here You will find all Documents and Package Deals Offered By Tutor Joshua.

3,6

55 beoordelingen

5
19
4
14
3
12
2
0
1
10

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen