Rose leads the advertising of an innovative product, Teckos, just launched by her
company. She has determined the advertising for Teckos is an individual project
consisting of 7 activities. Information pertinent to these activities is included in the table
that follows.
12 weeks
Seven activities are to be considered for this problem. Additional information about
these activities such as their activity time and immediate predecessors are included in
the table that follows. Use this information to figure out the earliest completion time for
this project using a Gantt chart.
18 weeks
Which PMBOK activity is responsible for determining activity resource requirements,
and for determining a resource breakdown structure?
Estimate activity resources
Select the most accurate statement with regards to the Critical Path Method (CPM).
It assumes that activities are independent of one another, with clearly defined start and
finish dates.
The district magistrate of Arkham City has decided to rebuild the busiest road in the city.
She plans to close the street for the duration of the work, causing immense
inconvenience to the people who typically use the road. The project has 3 parallel paths
defined as the following:
Path A-B-C-H will take 16 days.
Path A-D-E-H will take 22 days.
Path A-F-G-H will take 30 days.
Given the information on hand, which of the following statements is true?
Path A-F-G-H is the critical path.
Katniss Everdeen hates assumptions, but understands they're necessary sometimes.
Choose the statement that is an assumption made by the critical path method (CPM)?
The activity time estimates are accurate and stable.
Which of the following dictates the duration of any project?
The longest path through the project network
, Which of the following is not one seven processes that make up the PMBOK knowledge
area known as time (schedule) management?
Monitor activities
Which of the following are discrete tasks which require resources and time, within the
context of projects?
Activities
How is the slack time (ST) for an activity calculated? Answer this question using what
you know of the Critical Path Method (CPM).
The latest start (LS) time minus the earliest start (ES) time
The term ____ refers to a system's ability to handle increased business volume and
transactions in the future.
Scalability
In a(n) ____ structure, which usually is based on interpersonal relationships, some
people have more influence or knowledge than appears on an organization chart.
Informal
The choice between developing versus purchasing software often is called a ____
decision.
build or buy
In MS Project, by default, working weeks are assumed to be ________.
All of these alternatives are correct.
a. eight-hour days
b. five-day weeks
c. no work on Saturdays or Sundays
In MS Project, the tool that is used to designate subordination as displayed in the WBS
is ________.
indent arrow on the tool bar
According to Larson and Gray chapter 8, cost estimates are not a budget until
________.
budgets have been time-phased
In MS Project, by default any link between tasks (activities) is assumed to be ________.
Finish-to-Start
In MS Project, the tool that is used to establish sequencing among the activities is the
________.
linking tool on the tool bar