3 keys to inspect and adapt are... - answer-the PI system demo
quantitative measurement
the problem-solving workshop
3 Pillars of Scrum - answer-transparency, inspection, adaptation
4 core values of SAFe - answer-built-in quality, program execution, alignment, transparency
4 program events - answer-PI planning
ART sync
System Demo
Inspect and Adapt event
5 parts of every team increment - answer-plan, build, test, integrate, review
9 SAFe Lean-Agile principles - answer-1. take an economic view
2. apply systems thinking
3. assume variability; preserve options
4. build incrementally with fast, integrated learning cycles
5. base milestones on objective evaluation of working systems
6. visualize and limit WIP, reduce batch sizes, and manage queue lengths
7. apply cadence, synchronize with cross domain planning
8. unlock the intrinsic motivation of knowledge workers
9. decentralize decision making
A good scrum coach moves toward - answer-* coaching the team to collaborate
* being a facilitator
* being invested in the team's overall performance
* asking the team for the answer
* letting the team find their own way
* guiding
* focusing on business value delivery
* doing the right thing for the business right now
* facilitating team problem-solving
Adding new team members - answer-moves a team back to the forming stage
Agile Release Train - answer-a virtual organization of 5-12 teams (50-125+) that plans, commits, and
executes together
agile teams are not just committed to the work, they are committed to (3)... - answer-other teams
the program
the stakeholders
, agile teams commit to iteration ____ not stories - answer-goals
architectural runway - answer-existing code, hardware components, etc., that technically enable near-
term business features
art sync timebox - answer-1 hour
assumptions - answer-many arguments are anchored in unexamined ___.
At the conclusion of PI planning teams should have - answer-Velocity (capacity) and load for each
iteration
draft PI objectives
program risks and impediments
attendees for inspect and adapt - answer-teams and stakeholders
automation - answer-dev ops response to continuous delivery pipeline
backlog refinement timebox - answer-1 - 2 hours weekly
benefit hypothesis - answer-justifies feature implementation cost and provides business perspective
when making scope decisions
business owners - answer-key stakeholders on the agile release train
BVIR - answer-big
visible
information
radiator
CALMR approach to dev ops - answer-Culture
Automation
Lean flow
Measurement
Recovery
capability - answer-dev ops is a ___ of every agile release train
CFD - answer-cumulative flow diagram
Common Anti-Patterns for Iteration Planning - answer-* delving too deep into technical discussions
* commitment is unrealistic
* velocity and load are exactly the same
* SM is more focused on technical hat than facilitator hat
* team under-commits due to fear of failure
* no time reserved for support activities