Project Management Professional (PMP) 6th edition PMBOK With Questions And 100% SURE ANSWERS

Instelling
Project Management Professional
Vak
Project Management Professional










Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Project Management Professional
Vak
Project Management Professional

Documentinformatie

Geüpload op
19 oktober 2024
Aantal pagina's
23
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

JACKLINE




Project Management Professional (PMP) 6th edition
PMBOK With Questions And 100% SURE ANSWERS

Terms in this set (88)


Jack Jones the project manager of the Electricity
Cost Reduction project remarks to one of his
peers that his project has 300 communications
channels. She replies, "wow that's a lot of
communications channels, how many people are
you dealing with 150?" Jack says nowhere near
that, communications channels grow
exponentially, actually there are...
A member of a project team tells the project PMO
manager that he is not sure which of the many
projects he is working on is most important and
since he is assigned to help on several projects,
he's not sure which one should receive his
priority if there is a time conflict. Who should
determine priorities among multiple projects?




Project Management Professional (PMP) 6th edition PMBOK



1/23

,A project manager is approached by a member escalate the resource requirement to the program manaager
of senior management and informed that
resource that is essential to the project needs to
be moved to a different project because the
other project needs that person's skillset. How
should the project manager react?

It is important to have scheduled status meeting
to keep the project on track. Many people don't
like going to meeting because their schedule is
so crammed, and they try to avoid meetings
whenever possible. Sometimes it makes sense to
cancel a meeting, other times it doesn't, of the
following scenarios, which one is not a good
reason to cancel a meeting
Jan Plotte, of the PMO is giving an orientation
presentation to the new group of summer interns
at her organization. One of the topics she is
covering is project reporting requirements. She
tells the interns that each project is expected to
provide forecast reports on a monthly basis to
the PMO, these reports...
Two project managers are discussing the
challenges they face in bringing their project in
on time, on budget, and in scope. One of them
says, the hardest part of managing a project is
dealing with the conflicts between team
members, both among themselves, and with
stakeholders. The other project manager notes
that good communications are essential in
conflict resolution because...
Two project managers are discussing
communications management. During this
discussion, one project manager points out that
communication management tends to focus on
the infrastructure used to get timely and accurate
project communications to the right people. She
emphasizes this point by noting that the
following is a tool and technique of the Manage
Communications process
Project Management Professional (PMP) 6th edition PMBOK
2/23

, 10/19/24, 2:38 AM
The project is approximately 80% complete, and
Mary Stokes, the project manager is
communicating with stakeholders regarding the
status of the project. What will provide guidance
to her in determining which stakeholder gets
which reports?
Gulfport Manufacturing has created a project to
determine the best course of action to take in
response to the regulatory requirements that
have been recently enacted by the state
legislature for its industry. The company has three
plants located in the state, two of which were
built 20+ years ago, and will likely not be cost
effective to modernize. The CEO has warned that
this project will succeed or fail as a result of
effective communications. During the plan
communications management process, the
project manager and his team will rely on two
key inputs, specifically...
Bill Neison is the project manager of the Retail
Rebranding project. The production of the
rebranding new interior furniture is being
outsourced to an offshore furniture company
that specializes in the furniture design required.
There have been a number of communication
challenges with many requirements being
misinterpreted and on time delivery of furniture
to the stores as the rollout has proceeded. What
communication dimension should be employed
to minimize these problems?
Jan Plotte, of the PMO is giving an orientation
presentation to the new group of summer interns
at her organization. One of the topics she is
covering is project reporting requirements. She
tells the interns that each project is expected to
provide variance reports on a monthly basis to
the PMO, these reports...




Project Management Professional (PMP) 6th edition PMBOK
3/23

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Queenstin University Of California - Los Angeles (UCLA)
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
54
Lid sinds
1 jaar
Aantal volgers
8
Documenten
5752
Laatst verkocht
2 weken geleden
Tutor Queenstin

I am a professional writer/tutor. I help students with online class management ,exams ,essays ,assignments and dissertations . Improve your grades by buying my documents

3,2

5 beoordelingen

5
2
4
0
3
1
2
1
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen