During which of the following project development life cycles are the project scope, schedule and budget determined in the early phases of the life cycle? - ANSWER Predictive Life Cycle Which of the following is the correct definition of a project management methodology? - ANSWER System of practices, techniques, rules and procedures used by those who work in a discipline You are helping an organization uplift its project management practices. You have recommended developing a business case for each of the organizational projects followed by development of a project benefits management plan. Who would you recommend to be the owner of the business case? - ANSWER Project Sponsor

Meer zien Lees minder
Instelling
PMP
Vak
PMP










Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
PMP
Vak
PMP

Documentinformatie

Geüpload op
7 oktober 2024
Aantal pagina's
21
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

PMP Practice Exam Questions &
ANSWERS(2024 LATEST UPDATE)CORRECT
100%

During which of the following project development life cycles are the project scope, schedule and budget
determined in the early phases of the life cycle? - ANSWER Predictive Life Cycle



Which of the following is the correct definition of a project management methodology? - ANSWER
System of practices, techniques, rules and procedures used by those who work in a discipline



You are helping an organization uplift its project management practices. You have recommended
developing a business case for each of the organizational projects followed by development of a project
benefits management plan. Who would you recommend to be the owner of the business case? -
ANSWER Project Sponsor

- The project sponsor is generally accountable for the development and maintenance of the project
business case document.



The finance department in your organization approves a number of capital projects on an annual basis.
These projects are then funded by the finance department. You are responsible for constructing a new
manufacturing facility that would require construction of a plant, a couple of warehouses and a few
storage and distribution locations across the state. Your role at this organization is of a: - ANSWER
Program Manager

- Since you are responsible for developing a number of related construction projects, you are managing a
bigger program.



You have been hired by a new startup to develop its process architecture and define its operating model.
The operating model will be used by the business to manage and run its day-to-day business. Your
engagement with this organization is an example of: - ANSWER Project

- This is an example of a project. You have a starting point and an end point (defined and agreed
operating model). The later use of the operating model will be the business' operations but your current
engagement is a project as this is a temporary endeavor.

, Which of the following statements regarding Project Management Body of Knowledge (PMBOK) is
incorrect? - ANSWER The PMO's PMBOK Guide contains the entire Project Management Body of
Knowledge



You have recently helped an organization define its future state operating model. This will be a significant
shift from the current state and will involve significant change. Which of the following would be your
recommendation to the management? - ANSWER Create a transition state between the current and
future state.




Some projects are more complex than others. What are the three factors that influence project
complexity? - ANSWER ambiguity, system behavior, and human behavior



A project manager is managing a research project. Typically, research projects are not clearly defined and
involve a lot of uncertainty. The project has four phases in which a phase can only start when its previous
phase is complete. What project lifecycle and phase-to-phase relationship should the project manager
use for this project? - ANSWER Iterative lifecycle with sequential phase to phase relationship



Are commercial databases considered an enterprise environmental factor or organizational process
asset? - ANSWER enterprise environmental factor



What is the transition from one phase to another within a project's lifecycle that typically involves, and is
usually defined by, some form of technical transfer or handoff? - ANSWER kill point



A single point of failure (SPOF) is the part of a system that, upon failure, stops the entire system from
working or makes the system useless. What event could render a knowledge management system
ineffective? - ANSWER if the project team is not motivated



In what type of organization does the project manager have little or no authority? - ANSWER functional



In what type of organization is the project coordinator likely to be a part-time position with no
administrative support? - ANSWER functional

, In what type of organization is the project manager likely to have a variety of possible budgetary control
models? - ANSWER balanced matrix



Jim is a project manager within the ABC Company. Within his organization there are departments but
these groups provide support services to the various projects. In what kind of organization does Jim
work? - ANSWER projectized



A project manager takes a job with a new firm. He has little experience and will be working in a matrix
organization. Based upon his situation he should expect

communication with his stakeholders to be: - ANSWER complex



A very seasoned project manager leaves a position in an organization that was highly projectized for a
job in an organization that is a balanced matrix. His new

manager is very senior in the organization. Based on this information, he can expect communication to
be: - ANSWER complex



Two project managers in a weak matrix organization argue over which of them is more senior. Eventually
they determine that one of them is actually a project manager and the other is a project expeditor. How
is the expeditor different from the project manager? - ANSWER the expeditor cannot make decisions



A project manager is trying to complete a complicated COTS software project but is struggling to get
enough attention to complete the required work. Most of the resources needed are focused on
completing operational work and the project manager doesn't have authority to shift their focus or
assign other resources. In which type of organization must the project manager be working? - ANSWER
functional



Cathy is a new project manager with very little real experience. She's been assigned to lead a project for
which her boss feels she's perfectly suited. Her

organization is a matrix organization. Based on these characteristics she should expect communications
to be: - ANSWER complex



Ralph is currently leading a project in the planning phase when two key stakeholders come to him and
ask for an explanation of the development methodology being used on the project. They are specifically
interested in where it came from and how it differs from the methodology being used on most of the
projects being done within the organization. As Ralph explains
€11,40
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Lecchris West Virgina University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
40
Lid sinds
2 jaar
Aantal volgers
15
Documenten
3203
Laatst verkocht
1 maand geleden
LECCHRIS

3,8

6 beoordelingen

5
2
4
1
3
3
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen