100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4.2 TrustPilot
logo-home
Tentamen (uitwerkingen)

INTERCONNECTION RELIABILITY OPERATIONS AND COORDINATION EXAMS WITH ACTUAL CORRECT QUESTIONS AND VERIFIED DETAILED ANSWERS ALREADY GRADED A+ GUARANTEED PASS

Beoordeling
-
Verkocht
-
Pagina's
14
Cijfer
A+
Geüpload op
11-08-2024
Geschreven in
2024/2025

INTERCONNECTION RELIABILITY OPERATIONS AND COORDINATION EXAMS WITH ACTUAL CORRECT QUESTIONS AND VERIFIED DETAILED ANSWERS ALREADY GRADED A+ GUARANTEED PASS

Instelling
INTERCONNECTION
Vak
INTERCONNECTION









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
INTERCONNECTION
Vak
INTERCONNECTION

Documentinformatie

Geüpload op
11 augustus 2024
Aantal pagina's
14
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

INTERCONNECTION RELIABILITY
OPERATIONS AND COORDINATION
EXAMS WITH ACTUAL CORRECT
QUESTIONS AND VERIFIED
DETAILED ANSWERS ALREADY
GRADED A+ GUARANTEED PASS



The RC shall know the current status of all _______ in their whose failure, degradation or disconnection
could result in a system operating limit or an interconnection reliability operating limit violation

Since events in one part of the system can influence operations in all other parts of the system, the RC is
required to monitor and determine any potential SOL and IROL violations

True

Once a Reliability Coordinator issues a directive to preserve the integrity and reliability of the Bulk
Electric System, actions shall be taken without delay, but no longer than ________.

30 minutes

Reliability Coordinator shall initiate control actions or emergency procedures to relieve the violation
without delay and no longer than ___________.

30 minutes

___________ have the duty to continuously assess transmission reliability and coordinate emergency
operations among the operating entities within the region and across the regional boundaries.

Reliability Coordinators

, A portion of a Reliability Coordinator Area is experiencing low voltage, what directives should the
Reliability Coordinator give?

Lower transfers across area and increase generation in area with low voltage

Low voltage is a result of reactive power and losses associated with transferring power to load areas.
Increasing generation in the area with low voltage reduces losses associated with transferring power.

At any time, regardless of prior planned or unplanned events, the Reliability Coordinator should be able
to determine any potential ______________ violations within its Reliability Coordinator Area.

System Operating Limits (SOL) & Interconnection Reliability Operating Limits (IROL)

The _______ as defined by NERC is the electrical generation resources, transmission lines,
interconnections with neighboring systems, and associated equipment, generally operated at voltages
of 100 kilovolts or higher.

Bulk Electric System

Each Reliability Coordinator shall have adequate analysis tools, such as state estimation, contingency
analysis capabilities and ________ to monitor the Bulk Electric System.

wide-area overview displays

Wide-Area view is required therefore, each Reliability Coordinator shall have adequate analysis tools;
such as, state estimation, pre- and post-contingency analysis capabilities (thermal, stability, and
voltage), and wide-area overview displays.

This is stated in the NERC Standard IRO-002 explicitly and applied in the NERC Standard IRO-003 as the
RC shall monitor a wide area view within its Reliability Coordinator Area and that of neighboring
Reliability Coordinators.

Reliability Coordinators that delegate tasks to other entities shall have formal operating _________ with
each entity to which tasks are delegated.

agreements

If Reliability Coordinator tasks are delegated to other entities, the Reliability Coordinator shall verify that
these tasks are carried out by ___________ operating personnel.

NERC certified

Reliability Coordinators shall have clear, comprehensive coordination agreements with adjacent
Reliability Coordinators to ensure that System Operating Limit or Interconnection Reliability Operating
Limit violation mitigation requiring actions in adjacent Reliability Coordinator Areas are __________.

coordinated

Once a Reliability Coordinator issues a directive to preserve the integrity and reliability of the Bulk
Electric System, actions shall be taken without delay, but no longer than ________.
€13,69
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten

Maak kennis met de verkoper
Seller avatar
drjulie
1,0
(1)

Maak kennis met de verkoper

Seller avatar
drjulie john hopkins university
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
8
Lid sinds
1 jaar
Aantal volgers
2
Documenten
593
Laatst verkocht
10 maanden geleden
perfect grades

Quality over Quantity : i am strong believer in quality and reliable educational journey and therefore offer high -quality study docs ,comprehensive resources in variours subjects .meticulously curated ,accurate ,clear, and affordable .update reguarly. Download for excellence .Good luck and all the best .You got this DO NOT HESISTATE TO CONTACT FOR HELP . I WILL BE MORE THAN GLAD TO HELP

1,0

1 beoordelingen

5
0
4
0
3
0
2
0
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen