Exam 2024
Which employee labor rate is typically used to produce a
project budget?
salaries
burdened rates
billable rates
salaries plus bonus - ✔✔ANSW✔✔..salaries
Why do you analyze requirements before finalizing them?
- ✔✔ANSW✔✔..all of these
Why is it challenging to develop a problem statement for a
project? What action can you take to work around this
challenge to identify the problem? - ✔✔ANSW✔✔..people
tend to offer solutions
Why is the critical path critical?
any delay affects the project finish date
the tasks where resources are allocated
it represents the tasks that are delayed
the tasks on the critical path are the most important -
✔✔ANSW✔✔..
You and your team have identified several potential
strategies for a project. What is the first step you would
, take to eliminate candidates? - ✔✔ANSW✔✔..satisfies the
project objectives?
A description of the processes you use to ensure that
results meet the specified quality standards is a _____. -
✔✔ANSW✔✔..quality assurance
A risk that has become reality in your project has led to a
cost increase. You have already used the funds reserved
to handle this risk and have concluded that you need
additional funds that the project does not have. Who is the
most likely person or group you need to ask for help? -
✔✔ANSW✔✔..your organization's management team
Agile project management is superior to traditional project
management in which of the following situations? -
✔✔ANSW✔✔..when the goal and solution are not clearly
defined
Almost all tasks in a project will be connected using either
_____ or _____ dependencies. - ✔✔ANSW✔✔..finish to
start; start to start
How does a project charter support the project manager in
getting things for the project from other people? -
✔✔ANSW✔✔..documenting the work the project manager
does