According to SAFe, what is recommended first step of Iteration Planning? - Correct
Answer ✔️✔️-Establish Capacity
What is main objective of System Demo in SAFe? - Correct Answer ✔️✔️-Showcase
completed features to stakeholders
The Product Manager makes weekly visits to a customer's site. Which two Agile
Manifesto Values support this behavior? - Correct Answer ✔️✔️-Customer collaboration
over contract negotiation and Individual interactions over processes and tools.
What is one responsiblity of the Product Owner during Team Sync? - Correct Answer
✔️✔️-To clarify story intent
What question helps Product Management in creating a Vision? - Correct Answer ✔️✔️-
What problem(s) will the Solution solve?
What is recommended format for writing User Stories? - Correct Answer ✔️✔️-As a, I
want, So That
What is the primary goal of Lean Agile Leaders in supporting Agile Release Trains
(ART)? - Correct Answer ✔️✔️-Empowering the teams to self-organize and make
decisions
What is one characteristic of writing effective PI Objectives? - Correct Answer ✔️✔️-
Describing the value
,What is one role of Product Management? - Correct Answer ✔️✔️-Connect with the
Customer
What is the primary responsiblity of the Business Owners in SAFe? - Correct Answer
✔️✔️-Aligning Priorities and PI Planning
After resolving dependencies and addressing risks during the PI Planning event, what
activity follows? - Correct Answer ✔️✔️-Confidence Vote
What is one method to establish a team's velocity? - Correct Answer ✔️✔️-Compare the
average Story points completed throughout the previous iterations
What is the recommended frequency for conducting Iteration Planning in SAFe? -
Correct Answer ✔️✔️-Every two weeks
What is one anti-pattern of the Inspect and Adapt? - Correct Answer ✔️✔️-Product
Owners present all of the work in the PI System Demo
What statement accurately describes SAFe Backlog Model? - Correct Answer ✔️✔️-
Features are in the ART backlog
Which of the following is NOT a good practice when working with Epics? - Correct
Answer ✔️✔️-Assigning them to a single team
What is the purpose of the ART (Agile Release Train) in SAFe? - Correct Answer ✔️✔️-
To synchronize the activities of multiple Agile teams
What is one outcome of the Iteration Retrospective? - Correct Answer ✔️✔️-Improvement
items in the Team Backlog
What is the primary purpose of PO Sync? - Correct Answer ✔️✔️-To assess progress of
the Program Increment and adjust scope and priorities as needed.
, What is one anti-pattern related to the System Demo? - Correct Answer ✔️✔️-Team
demos are accepted in place of a System Demon to avoid redundancy
With whom does Product Management collaborate to prioritize Enablers? - Correct
Answer ✔️✔️-System Architect
Which SAFe Core Competency centers on applying Lean and systems thinking to
strategy and investment funding decisions? - Correct Answer ✔️✔️-Lean Portfolio
Management
What is one responsibility of the Product Owner? - Correct Answer ✔️✔️-Prioritizing the
Team Backlog
During PI Planning, Agile Teams estimate user stories using story points. What other
estimation technique is commonly used to estimate the size of Features in SAFe? -
Correct Answer ✔️✔️-T-Shirt Sizing
The Release Train Engineer (RTE) works with the Product Manager to - Correct Answer
✔️✔️-All of the propositions
When explaining why the top 10 features were chosen for PI Planning, which SAFe
Core Value is demonstrated? - Correct Answer ✔️✔️-Transparency
Epics are decomposed into what? - Correct Answer ✔️✔️-Features
Which tool shows dependencies during PI Planning? - Correct Answer ✔️✔️-ART
Planning Board
What is one benefit of capacity allocation? - Correct Answer ✔️✔️-It prevents different
types of backlog items from being compared against another.