SOS NERC Prep - RELIABILITY EXAM QUESTIONS & ANSWERS-The Reliability Coordinator just informed you of a slow time error correction which will begin at the top of the next hour. Your EMS system will not let you change your scheduled frequency. Your Frequency Bias Setting is -100 MW/.1Hz. What action should you take? A) Increase Net Interchange Schedule by 20 MWs. B) Inform the Reliability Coordinator that you cannot participate in the time error correction. C) Decrease Net Interchange Schedule by 20 MWs. D) Increase Net Interchange Schedule by 10 MWs. - A) Increase Net Interchange Schedule by 20 MWs. A Balancing Authority has a sudden loss of a large block of load in its area. This loss will be seen instantaneously in the change of which of the following values? 1. Actual Net Interchange 2. Scheduled Frequency 3. Scheduled Net Interchange 4. Area Control Error A) 4 only B) 1 & 3 C) 1 & 4 D) 3 & 4 - C) 1 & 4 Metered Data included in the calculation of ACE are: dynamic schedules, pseudo ties, actual frequency, and all __________. A) Tie lines readings B) Generators output C) Scheduled frequency indications D) Transformer load - A) Tie lines readings Balancing Authority A is currently reading a system frequency of 60.00 Hz. Its Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +200 MW. If Balancing Authority A's frequency bias setting is 100 MW/0.1 Hz, what is ACE? A) -100 B) 0 C) 10 D) 100 - A) -100 A Balancing Authority has a Net Interchange Schedule of -250 MWs from 1200 to 1600 on a summer day. The Net Interchange Actual for those same hours respectively were -230 MW, -275 MW, -250 MW and -270 MW. What was the Balancing Authority's Inadvertent Interchange for the 4-hour period? A) 6 MWs out B) 25 MWs in C) 25 MWs out D) 6 MWs in - B) 25 MWs in For the ACE equation to work properly, dynamic schedules, pseudo ties, frequency, and all ________________ must be metered. A) Generation B) Communications C) Transformers D) Tie lines - D) Tie lines If the frequency bias setting is set to a less negative value than the frequency response of a Balancing Authority and a frequency increase is caused by a sudden loss of load in an external balancing area, what will be the result? A) The ACE will be zero and will take no AGC action B) The ACE will be a negative value and AGC will increase generation

Meer zien Lees minder
Instelling
SOS NERC Prep
Vak
SOS NERC Prep











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
SOS NERC Prep
Vak
SOS NERC Prep

Documentinformatie

Geüpload op
24 februari 2023
Bestand laatst geupdate op
14 januari 2025
Aantal pagina's
69
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

SOS NERC Prep - RELIABILITY EXAM QUESTIONS & ANSWERS

The Reliability Coordinator just informed you of a slow time error correction
which will begin at the top of the next hour. Your EMS system will not let you
change your scheduled frequency. Your Frequency Bias Setting is -100 MW/.1Hz.
What action should you take?

A) Increase Net Interchange Schedule by 20 MWs.

B) Inform the Reliability Coordinator that you cannot participate in the time error
correction.

C) Decrease Net Interchange Schedule by 20 MWs.

D) Increase Net Interchange Schedule by 10 MWs. - A) Increase Net Interchange
Schedule by 20 MWs.

A Balancing Authority has a sudden loss of a large block of load in its area. This
loss will be seen instantaneously in the change of which of the following values?

1. Actual Net Interchange
2. Scheduled Frequency
3. Scheduled Net Interchange
4. Area Control Error

A) 4 only
B) 1 & 3
C) 1 & 4
D) 3 & 4 - C) 1 & 4

Metered Data included in the calculation of ACE are: dynamic schedules, pseudo
ties, actual frequency, and all __________.

A) Tie lines readings
B) Generators output
C) Scheduled frequency indications

,D) Transformer load - A) Tie lines readings

Balancing Authority A is currently reading a system frequency of 60.00 Hz. Its Net
Actual Interchange is +100 MW and its Net Scheduled Interchange is +200 MW. If
Balancing Authority A's frequency bias setting is 100 MW/0.1 Hz, what is ACE?

A) -100
B) 0
C) 10
D) 100 - A) -100

A Balancing Authority has a Net Interchange Schedule of -250 MWs from 1200 to
1600 on a summer day. The Net Interchange Actual for those same hours
respectively were -230 MW, -275 MW, -250 MW and -270 MW. What was the
Balancing Authority's Inadvertent Interchange for the 4-hour period?

A) 6 MWs out
B) 25 MWs in
C) 25 MWs out
D) 6 MWs in - B) 25 MWs in

For the ACE equation to work properly, dynamic schedules, pseudo ties,
frequency, and all ________________ must be metered.

A) Generation
B) Communications
C) Transformers
D) Tie lines - D) Tie lines

If the frequency bias setting is set to a less negative value than the frequency
response of a Balancing Authority and a frequency increase is caused by a sudden
loss of load in an external balancing area, what will be the result?

A) The ACE will be zero and will take no AGC action

B) The ACE will be a negative value and AGC will increase generation

,C) The ACE will be a positive value and AGC will lower generation

D)This will not affect the ACE - B) The ACE will be a negative value and AGC
will increase generation

If the frequency bias setting is less negative than the frequency response of a
Balancing Authority and a frequency decline is caused by a sudden loss of
generation in an external balancing area, what will be the result?

A) The ACE will be a negative value and AGC will increase generation.

B) This will not affect the ACE.

C) The ACE will be a positive value and AGC will lower generation.

D) The ACE will be zero and will take no AGC action. - C) The ACE will be a
positive value and AGC will lower generation.

It is the responsibility of which entity/entities to develop, maintain, and implement
load shedding plans?

A) Transmission Operators and Balancing Authorities

B) Reliability Coordinator

C) Load Serving Entities

D) Balancing Authority - A) Transmission Operators and Balancing Authorities

A Transmission line is loaded 25% above its SOL. A parallel line is out for routine
maintenance and can be placed in service in 10 minutes. What is the first step the
Operator should take to reduce the line loading?

A)Shed load at the downstream bus.

, B) Open the line.

C) Re-Dispatch Generation.

D) Initiate the restoration of the parallel line. - D) Initiate the restoration of the
parallel line.

As a Transmission Operator, you realize that the voltage level is starting to decline
in the North West part of the system. Which of the following devices should you,
as a Transmission Operator, be able to operate, and/or have another entity operate
to raise the voltage level back to normal in the North West part of the system?

A) Transformer Underload Tap Changers
B) Shunt Capacitor Banks
C) Generator Reactive Output
D) All answers are correct - D) All answers are correct

Voltage reduction for load relief should be made on the __________.

A) Distribution system
B) Entire Interconnection simultaneously
C) Tie-lines with other Balancing Authority Areas
D) Transmission System - A) Distribution system

Under Frequency Load Shedding (UFLS) is to stabilize the imbalance between
generation and load that has been created by a system disturbance. This is
accomplished by ____________.

A) Tripping generation first
B) Voltage reduction on the distribution system.
C) Shedding all load to arrest frequency
D) Shedding load prior to generation tripping - D) Shedding load prior to
generation tripping
€11,50
Krijg toegang tot het volledige document:
Gekocht door 2 studenten

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten


Ook beschikbaar in voordeelbundel

Beoordelingen van geverifieerde kopers

Alle 3 reviews worden weergegeven
5 maanden geleden

1 jaar geleden

2 jaar geleden

4,7

3 beoordelingen

5
2
4
1
3
0
2
0
1
0
Betrouwbare reviews op Stuvia

Alle beoordelingen zijn geschreven door echte Stuvia-gebruikers na geverifieerde aankopen.

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
ProfMiaKennedy Arizona State University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1988
Lid sinds
4 jaar
Aantal volgers
1609
Documenten
3279
Laatst verkocht
2 dagen geleden

We all get stuck sometimes, you feel frustrated about exams coming up and not fully prepared? Worry no more mate, with my documents i assure you atleast an A, get unstuck with the most recent, analyzed and graded exams with just a simple mouse click... Download and crash those exams!!

3,9

380 beoordelingen

5
195
4
57
3
56
2
25
1
47

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen