100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4.2 TrustPilot
logo-home
Tentamen (uitwerkingen)

Project Management 2nd Edition by Pinto chapter 11

Beoordeling
-
Verkocht
1
Pagina's
36
Geüpload op
27-10-2015
Geschreven in
2014/2015

Project Management 2nd Edition by Pinto chapter 11 Test bank

Instelling
Vak









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
Studie
Vak

Documentinformatie

Geüpload op
27 oktober 2015
Aantal pagina's
36
Geschreven in
2014/2015
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Voorbeeld van de inhoud

Project Management, 2e (Pinto)
Chapter 11 Critical Chain Project Scheduling

11.1 True/False

1) Once the organization elevates its constraint, its system has no constraint.
Answer: FALSE
Diff: 2
Section: 11.1 The Theory of Constraints and Critical Chain Project Scheduling
Skill: Definition
AACSB Tag: Reflective

2) An organization's budget estimating process routinely misses the actual cost of a project by
25%. For the most recent project, the budget variance was a ridiculous 23%, but this must be
considered common cause variance.
Answer: TRUE
Diff: 2
Section: 11.1 The Theory of Constraints and Critical Chain Project Scheduling
Skill: Factual
AACSB Tag: Reflective

3) In order to estimate completion of a Gaussian distributed activity with a 90% or higher degree
of confidence, the time may be overestimated by as much as 200%.
Answer: TRUE
Diff: 2
Section: 11.2 CCPM and the Causes of Project Delay
Skill: Analytical
AACSB Tag: Reflective

4) If people believe that they built extra time into their initial estimates, they are usually more
likely to begin project work right away.
Answer: FALSE
Diff: 1
Section: 11.3 How Project Teams Waste the Extra Safety They Acquire
Skill: Conceptual
AACSB Tag: Reflective

5) Both positive and negative variation are usually passed downstream during a project.
Answer: FALSE
Diff: 2
Section: 11.3 How Project Teams Waste the Extra Safety They Acquire
Skill: Factual
AACSB Tag: Reflective




1
Copyright © 2010 Pearson Education, Inc.

, 6) The Central Limit Theorem states that if a number of probability distributions are summed,
the variance of the sum equals the sum of the variances of individual distributions.
Answer: TRUE
Diff: 2
Section: 11.4 The Critical Chain Solution to Project Scheduling
Skill: Analytical
AACSB Tag: Analytic Skills

7) A feeder buffer is a buffer that is created for a non-critical path activity.
Answer: TRUE
Diff: 1
Section: 11.4 The Critical Chain Solution to Project Scheduling
Skill: Definition
AACSB Tag: Reflective

8) An important element in critical chain scheduling is to change from a late-finish
(procrastination) approach to an early-start approach.
Answer: FALSE
Diff: 2
Section: 11.4 The Critical Chain Solution to Project Scheduling
Skill: Definition
AACSB Tag: Reflective

9) The critical chain is usually the same as the critical path.
Answer: FALSE
Diff: 2
Section: 11.4 The Critical Chain Solution to Project Scheduling
Skill: Factual
AACSB Tag: Reflective

10) The legal department is needed to review all contracts a project organization enters. The legal
department is continually swamped with work and all other departments find themselves waiting
on legal before they can begin their work. Legal is the drum for this organization.
Answer: TRUE
Diff: 2
Section: 11.6 Critical Chain Project Portfolio Management
Skill: Conceptual
AACSB Tag: Reflective

11.2 Fill in the Blank

1) Critical Chain Project Management is based on the __________.
Answer: Theory of Constraints
Diff: 1
Section: 11.1 The Theory of Constraints and Critical Chain Project Scheduling
Skill: Definition
AACSB Tag: Reflective

2
Copyright © 2010 Pearson Education, Inc.
€3,49
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
smith2324 European Business School, London
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
94
Lid sinds
10 jaar
Aantal volgers
39
Documenten
196
Laatst verkocht
1 jaar geleden

4,5

24 beoordelingen

5
13
4
9
3
2
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen