Trusses shall be __ or __.
- answer-Braced or guyed.
Pre-shores must be at intervals no more than __ft on center.
- answer-8ft
Projectile tools
- answer-ANSI
Pre-jump safety meetings must take place no more than __ hrs prior to jump.
- answer-24hrs
Open excavations can be protected by solid encloser at least __ft__inches.
- answer-3' 6"
Jacks shall be marked by etch or stamp with the __.
- answer-Rated capacity
When using jack, once item has been lifted __ or __ shall be used immediately if
jack does not have built in safety devices.
- answer-Blocking or cribbing
Fuel shall be kept in containers that meet the requirements of the __.
- answer-Fire Department
All house valves shall be provided with __ outlets.
- answer-capped
__ or __ shall be erected to prevent materials from rebounding into street.
- answer-Splash boards or baffles
Abandoned sites require a __ and a __ plan.
- answer-Fence & safety monitoring plan.
,if soil work does not begin you must notify department no more than __hours prior
but no later than the scheduled date.
- answer-24 hours
All open edges of excavation shall have guardrail when greater than __ft in depth.
- answer-6'
Reshoring schedule shall be __.
- answer-Signed and sealed.
Kept on site.
Wood pole splices shall be __ft in legth.
- answer-4 ft
Shall not be used as slings.
- answer-Discarded rope
Space between platforms and uprights on scaffold is no more than __ inch.
- answer-1inch
A __ or __ at least 4"X4" at openings level with or below floor
- answer-Bumper or curb
Lifts and fork trucks shall be provided metal plated with etched/stamped __ __ in
pounds.
- answer-capacity ratings
Structural members shall be __ or __ to prevent swing.
- answer-chained or lashed
Monitoring required during course of excavation when __.
- answer--Buildings are within distance of excavation that is equal to or less than
the max depth of excavation.
-Historic structures contiguous to or within 90ft from edge of lot.
Crane licenses
A__
B__
C__
- answer-200
,unlimited
cherry picker
Smoking is __.
- answer-Prohibited.
A training course shall be considered timely if completed with __ year after
expiration for rigging.
- answer-1 year
Permits shall be posted __ of hoisting equipment.
- answer-In the car or on equipment.
Runways/Ramps for vehicles shall be min __ft wide.
- answer-12ft
Site specific formwork drawings required when __.
- answer-Concrete for major building
shore/form height greater than 14'
vertical load exceeds 150lbs
power buggies are used
multi stage shores are used
slab is 10" or more
concentrated loads 2000lbs
Following adjustment or repair of scaffold an __ is required.
- answer-Inspection
You must notify department __ to __hours prior to soil or foundation work.
- answer-24 to 48hours
Max aggregate indoor acetylene storage not to exceed __scf
- answer-15,000scf
The site safety log shall be kept __.
- answer-At the site.
The SSM shall at a min conduct daily checks to ensure standpipe is __.
- answer-Available and in a state of readiness at all times.
, Protection for storage next to sidewalk shall extend from 4' barrier with mesh to
top of sidewalk shed. 1/2inch.
- answer-Storage next to sidewalk
Medical gases max storage
- answer-1,500scf
If no response is received from adjoining property owner a second written
notification shall be made no more than __ days and no less than __.
- answer-45 days
30 days
Supported scaffolds require a pre-shift __ & __.
- answer-Inspection & checklist.
Notify FDNY soil work
- answer-Explosives
CSFSM is responsible to ensure construction personell are aquatinted with
operation of __.
- answer-Fire extinguishers and other fire protection equipment.
If an alternate SSM comes to relieve primary SSM this shall be noted in the __.
- answer-Site safety log.
When floor is less than 1,000sqft material may be stored __ft from unenclosed
perimeter.
- answer-5ft
FDNY hose connections shall be marked with metal sign reading __ and red light
at night.
- answer-Sprinkler connection
Viewing panels shall be provided every __ft.
- answer-25 linear ft
Platforms shall not deflect more than __ span.
- answer-1/60